City of Chamberlain v. R.E. Lien, Inc.

521 N.W.2d 130, 1994 S.D. LEXIS 138, 1994 WL 474194
CourtSouth Dakota Supreme Court
DecidedAugust 31, 1994
Docket18370
StatusPublished
Cited by22 cases

This text of 521 N.W.2d 130 (City of Chamberlain v. R.E. Lien, Inc.) is published on Counsel Stack Legal Research, covering South Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Chamberlain v. R.E. Lien, Inc., 521 N.W.2d 130, 1994 S.D. LEXIS 138, 1994 WL 474194 (S.D. 1994).

Opinions

MILLER, Justice.

A trial court ruled SDCL 5-18-11, which requires public contracts include provisions from an AIA standardized form, and SDCL 21-25A-1, which enforces arbitration agreements, were unconstitutional delegations of municipal functions in violation of Article III, § 26, of the South Dakota Constitution. We affirm as to SDCL 5-18-11 and reverse as to SDCL 21-25A-1.

FACTS

On October 26,1991, R.E. Lien, Inc. (Lien) entered into a contract with the City of Chamberlain (City) for construction of water mains and sewer lines in a four-block area of main street. The contract incorporated by reference drawings and specifications prepared by Pierce & Harris Engineering, Co.

The project did not go well. Lien asserted that the plans were grossly inadequate as to existing utilities and resulted in cost overruns and delays. City claimed Lien’s work was deficient and eventually ordered Lien off the job site. City then hired Morris, Inc. to complete the work.

When City refused to pay Lien the final contract price, Lien filed a demand for arbitration with the American Arbitration Association (Association). City claimed the contract contained no agreement to arbitrate, but Association declared it would proceed in the absence of a court order staying the matter. City then requested an order from the circuit court quashing and staying the arbitration proceedings.

On May 20, 1993, the circuit court issued an order quashing and staying the arbitration proceedings. It found SDCL 5-18-11 and SDCL 21-25A-1 compelled City to arbitrate under the American Institute of Architects’ (AIA) standard form, thus violating Article III, § 26, of the South Dakota Constitution as a delegation of a municipal function. It ruled the statutes were unconstitutional. Lien appeals.1

STANDARD OF REVIEW

The issue of the constitutionality of a statute is a question of state law and is reviewed de novo by this court. In re K.O. Lee, 489 N.W.2d 606 (S.D.1992).

To succeed in a constitutional challenge to a legislative act, the challenger must prove beyond a reasonable doubt that the legislature acted outside of its constitutional authority. Associated Gen. Contractors of South Dakota, Inc. v. Schreiner, 492 N.W.2d 916 (S.D.1992). We will review a law’s constitutionality only when necessary for a determination upon the merits of a cause under consideration, and will first ascertain whether a construction of the statute, which avoids the constitutional question, is fairly possible. State v. Big Head, 363 N.W.2d 556 (S.D.1985). This court will uphold legislative enactments unless they are clearly and unmistakably unconstitutional. Oien v. City of Sioux Falls, 393 N.W.2d 286, 289 (S.D.1986); Matter of Certain Territorial Elec. Boundaries, 281 N.W.2d 65 (S.D.1979); Frawley Ranches, Inc. v. Lasher, 270 N.W.2d 366 (S.D.1978); County of Tripp v. State, 264 N.W.2d 213 (S.D.1978).

DECISION

I. SDCL 5-18-11 Is An Unconstitutional Delegation of Municipal Authority.

Municipalities in South Dakota have the freedom to enter into contracts for binding arbitration. L.R. Foy Construction Co. v. Spearfish Sch. Dist., 341 N.W.2d 383 (S.D.1983); City of Hot Springs v. Gunderson’s, [132]*132Inc., 322 N.W.2d 8 (S.D.1982). The question in this case is whether a municipality is bound by an arbitration clause contained in a statutorily required standardized form.

Lien first claims this is an action for enforcement of a contract, not a question of creation of a contract. This claim evades the question; it is elementary that before a court may enforce a contract there must be a determination that a valid contract was created.

The contract between Lien and City contains no express provision agreeing to arbitration. Lien claims that because its contract with City incorporated by reference the drawings and specifications of an engineering firm, SDCL 5-18-11 mandates that the arbitration provisions of the AIA standard form automatically became part of the contract. SDCL 5-18-11 provides:

All contracts shall be made and set forth in writing and shall be signed on behalf of the public corporation by the proper officials thereof and with the formalities required by the governing statutes regulating the particular public corporation involved. The writing shall embody therein all of the terms and conditions of the contract, and, when based upon plans and specifications prepared by an architect or engineer shall contain no general provisions at variance with the general conditions of the latest edition of the standard form of the American institute of architects, except when in conflict with the laws of this state. (Emphasis added.)

The AIA general conditions contain the following provision mandating arbitration:

4.5.1 Controversies and Claims Subject to Arbitration. Any controversy or Claim arising out of or related to the Contract or the breach thereof, shall be settled by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association, and judgment upon the award rendered by the arbitrator or arbitrators may be entered in any court having jurisdiction thereof!.]

City claims that SDCL 5-18-11 violates article III, § 26 of the South Dakota Constitution insofar as it delegates a municipality’s authority to contract to a special commission, private corporation or association. The Constitution provides:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Foshay
2024 S.D. 12 (South Dakota Supreme Court, 2024)
State v. Rolfe
2013 S.D. 2 (South Dakota Supreme Court, 2013)
State v. Gutnik
2010 S.D. 82 (South Dakota Supreme Court, 2010)
VERIZON WIRELESS (YAW) LLC v. Kolbeck
529 F. Supp. 2d 1081 (D. South Dakota, 2007)
Council of Insurance Agents + Brokers v. Viken
408 F. Supp. 2d 836 (D. South Dakota, 2005)
State v. Martin
2003 SD 153 (South Dakota Supreme Court, 2003)
Repass v. Workers' Compensation Division
569 S.E.2d 162 (West Virginia Supreme Court, 2002)
Steinkruger v. Miller
2000 SD 83 (South Dakota Supreme Court, 2000)
Bergee v. South Dakota Board of Pardons & Paroles
2000 SD 35 (South Dakota Supreme Court, 2000)
State v. Allison
2000 SD 21 (South Dakota Supreme Court, 2000)
American Meat Institute v. Barnett
64 F. Supp. 2d 906 (D. South Dakota, 1999)
Wegleitner v. Sattler
1998 SD 88 (South Dakota Supreme Court, 1998)
Wegleiter v. Sattler
1998 SD 88 (South Dakota Supreme Court, 1998)
Texas Boll Weevil Eradication Foundation, Inc. v. Lewellen
952 S.W.2d 454 (Texas Supreme Court, 1997)
McCabe v. North Dakota Workers Compensation Bureau
1997 ND 145 (North Dakota Supreme Court, 1997)
City of Chamberlain v. R.E. Lien, Inc.
521 N.W.2d 130 (South Dakota Supreme Court, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
521 N.W.2d 130, 1994 S.D. LEXIS 138, 1994 WL 474194, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-chamberlain-v-re-lien-inc-sd-1994.