Azcon Construction Co. v. Golden Hills Resort, Inc.

498 N.W.2d 630, 1993 S.D. LEXIS 32, 1993 WL 103428
CourtSouth Dakota Supreme Court
DecidedApril 7, 1993
Docket18057
StatusPublished
Cited by40 cases

This text of 498 N.W.2d 630 (Azcon Construction Co. v. Golden Hills Resort, Inc.) is published on Counsel Stack Legal Research, covering South Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Azcon Construction Co. v. Golden Hills Resort, Inc., 498 N.W.2d 630, 1993 S.D. LEXIS 32, 1993 WL 103428 (S.D. 1993).

Opinion

WUEST, Justice.

This is an appeal arising from a circuit court’s affirmation of an arbitration panel’s award. The trial court ruled that Golden Hills waived its objection to arbitration by participation therein, affirmed the arbitration panel’s award and denied a motion to vacate the award. We hold that participation by Golden Hills was not a waiver and reverse the trial court on that issue. However, we affirm the trial court on all other issues.

FACTS

On July 20, 1988, Golden Hills Resort, Inc. (Golden Hills) and Azcon Construction Co., Inc. (Azcon) entered into a single, written contract for the design and construction of a hotel-convention center and a connected recreation center to be built in Lead, South Dakota. The contract did not separate costs for the two facilities.

Eleven months later, the City of Lead contracted with Golden Hills to serve as general contractor for the building of a recreation center for the Northern Hills Young Mens Christian Center (YMCA). The YMCA center was the same recreation facility Azcon was in the process of erecting under its contract with Golden Hills.

During the course of construction, disputes arose between Azcon and Golden Hills. On June 23, 1989, they entered into a settlement agreement in which Azcon released claims for extra work, owner delay, weather delay and other claims accrued as of the date of the agreement. The parties agreed not to sue one another or seek arbitration proceedings against one another for the claims settled in the agreement.

On November 9, 1990, Azcon filed a demand for arbitration seeking damages for breach of contract by Golden Hills. The same day Golden Hills objected to jurisdiction claiming the settlement agreement acted as a complete bar to arbitration. In a subsequent brief, Golden Hills took the position that only the claims and issues addressed in the settlement agreement were foreclosed from arbitration.

The arbitration panel responded to Golden Hills’ objection to jurisdiction by ruling claims included in the settlement agreement would not be arbitrated. It deferred ruling on which claims were arbitrable until the hearing and concluded it would entertain Golden Hills’ motion to dismiss after it ruled on arbitrability.

On May 24, 1991, the City of Lead filed suit in circuit court against Azcon and Golden Hills as co-Defendants for alleged breach of contract and construction deficiencies in the YMCA recreation center. Golden Hills filed a cross-claim against Azcon seeking indemnity and contribution against any amount eventually awarded to the City in that action.

*632 Golden Hills then filed an amended answer in the arbitration proceeding objecting to the panel’s jurisdiction of any claims dealing with the recreation center. Its amended answer also asserted a counterclaim against Azcon for damages relating to the convention center.

Both parties participated in selecting the three-man panel for arbitration which started on January 6, 1992 and concluded on January 24, 1992. Both presented evidence, called witnesses and had an opportunity for cross-examination.

The arbitrators determined they had jurisdiction over the claims: 1) by Azcon that Golden Hills failed to pay the amount due under the contract; 2) by Golden Hills that it was damaged by Azcon’s conduct; and 3) by Golden Hills that Azcon built the hotel-convention center in a faulty manner. The panel acknowledged the circuit court had jurisdiction over: 1) claims by City against Azcon and Golden Hills for faulty construction of the recreation center; and 2) Golden Hills’ cross-claims against Azcon for faulty construction of the recreation center.

On February 13, 1992, the arbitration panel awarded Azcon $2,049,484 and Golden Hills $417,800. Pursuant to SDCL 21-25A-23, Azcon filed a motion with the circuit court for affirmation of the award. Golden Hills moved the court to vacate the award on the same grounds it asserts in this appeal. The trial court affirmed the arbitration award and Golden Hills appeals. We will address each issue, adding relevant facts where necessary.

ANALYSIS

I. GOLDEN HILLS’ PARTICIPATION IN THE ARBITRATION HEARING DID NOT WAIVE ITS OBJECTION TO THE JURISDICTION OF THE ARBITRATION PANEL.

Azcon asserts that Golden Hills’ participation in the arbitration proceeding waived its right to raise the issue of arbi-trability after the award notwithstanding Golden Hills’ participation was under objection the panel was exceeding its jurisdiction. Golden Hills asserts the issue of jurisdiction was preserved by timely objections and its participation in arbitration did not waive its right to raise questions of jurisdiction on appeal.

The trial court determined that Golden Hills’ submission of the question of jurisdiction to the arbitration panel, along with its participation in the proceedings without seeking a judicial stay under SDCL 21-25A-8 constituted a waiver. However, the court went ahead and decided the issues on the merits, apparently to avoid further appeals. This court has never decided whether timely objection will preserve the issue of arbitrability if a party participates in a hearing on the merits.

There is a wide split of authority as to when participation in an arbitration proceeding results in waiver of the right to object. See Annotation, Participating In Arbitration Proceeding As Waiver Of Objections To Arbitrability, 33 A.L.R.3d 1242 (1970). In some jurisdictions it is sufficient to raise an objection to arbitrability before or at the beginning of the hearing and the issue is preserved for appeal. A. & E. Plastik Pak Co. v. Monsanto Co., 396 F.2d 710 (9th Cir.1968); Acme Markets, Inc. v. Retail Clerks Int’l Union, 235 F.Supp. 814 (E.D.Pa.1964); United Mine Workers v. Pittston Co., 210 F.Supp. 781 (N.D.W.Va.1962); Hot Springs County Sch. Dist. v. Strube Constr., 715 P.2d 540 (Wyo.1986). Other jurisdictions hold that once the issue of arbitrability is submitted to the arbitration panel it is waived. O’Malley v. Petroleum Maintenance Co., 48 Cal.2d 107, 308 P.2d 9 (1957); Flint Sch. Disk v. AFL-CIO, 168 Mich.App. 180, 423 N.W.2d 608 (1988) rev’d on other grounds, 431 Mich. 907, 433 N.W.2d 76 (1988); American Motorists Insurance Company v. Llanes, 396 Mich. 113, 240 N.W.2d 203 (1976). Some jurisdictions go so far as to find that when the issue of arbitrability is submitted to the arbitration panel it is waived even if the original agreement did not provide for arbitration of that claim. Collingswood Hosiery Mills Inc. v. American Federation of Hosiery Workers, 28 N.J.Super.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In the Matter of: Jon Amberson
54 F.4th 240 (Fifth Circuit, 2022)
Garlock v. 3DS Properties
303 Neb. 521 (Nebraska Supreme Court, 2019)
Garlock v. 3DS Props., L. L.C.
303 Neb. 521 (Nebraska Supreme Court, 2019)
Bashiti v. Tutu Park, Ltd.
66 V.I. 604 (Supreme Court of The Virgin Islands, 2017)
Konrad v. Stoebner
2016 SD 77 (South Dakota Supreme Court, 2016)
Black Hills Surgical Physicians, LLC v. Setliff
2014 SD 68 (South Dakota Supreme Court, 2014)
DT-Trak Consulting, Inc. v. Prue
2012 S.D. 39 (South Dakota Supreme Court, 2012)
Dolton v. LYNCH, PIERCE, FENNER & SMITH
935 A.2d 295 (District of Columbia Court of Appeals, 2007)
Wein v. Morris
909 A.2d 1186 (New Jersey Superior Court App Division, 2006)
Spiska Engineering, Inc. v. SPM Thermo-Shield, Inc.
2004 SD 44 (South Dakota Supreme Court, 2004)
Nelson v. Livingston Rebuild Center, Inc.
1999 MT 116 (Montana Supreme Court, 1999)
Thunderstik Lodge
1998 SD 110 (South Dakota Supreme Court, 1998)
Thunderstik Lodge, Inc. v. Reuer
1998 SD 110 (South Dakota Supreme Court, 1998)
Elrod v. General Casualty Co. of Wisconsin
1997 SD 90 (South Dakota Supreme Court, 1997)
Alca Construction Co. v. Housing Auth., No. Cv-97-0569696-S (Jun. 3, 1997)
1997 Conn. Super. Ct. 6346 (Connecticut Superior Court, 1997)
City of Chamberlain v. R.E. Lien, Inc.
521 N.W.2d 130 (South Dakota Supreme Court, 1994)
Kovacs v. Kovacs
633 A.2d 425 (Court of Special Appeals of Maryland, 1993)
Schlosser v. Norwest Bank South Dakota, N.A.
506 N.W.2d 416 (South Dakota Supreme Court, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
498 N.W.2d 630, 1993 S.D. LEXIS 32, 1993 WL 103428, Counsel Stack Legal Research, https://law.counselstack.com/opinion/azcon-construction-co-v-golden-hills-resort-inc-sd-1993.