Peska Construction Co. v. Portz Investment, Ltd. Liability Partnership

2003 SD 136, 672 N.W.2d 483
CourtSouth Dakota Supreme Court
DecidedNovember 25, 2003
DocketNone
StatusPublished
Cited by5 cases

This text of 2003 SD 136 (Peska Construction Co. v. Portz Investment, Ltd. Liability Partnership) is published on Counsel Stack Legal Research, covering South Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Peska Construction Co. v. Portz Investment, Ltd. Liability Partnership, 2003 SD 136, 672 N.W.2d 483 (S.D. 2003).

Opinion

ZINTER, Justice.

[¶ 1.] Peska Construction Company (Peska) sued Portz Investment (Portz) and Area Steel to foreclose on a mechanic’s lien and recover money due for work performed on Portz’s property. Portz and Area Steel counterclaimed alleging defects in the four concrete slabs constructed by Peska on the property. The parties subsequently entered into an agreement to arbitrate all issues relating to all four slabs. The day before the arbitration hearing, latent defects were discovered, and Portz and Area Steel moved to amend their counterclaims to include those defects in the arbitration. The arbitrator denied the motion to amend, but severed the amended counterclaims for later arbitration. Arbitration then proceeded as scheduled, but only on the first two slabs, and an award was entered against Peska on those two slabs. The award also provided that all severed claims on the two remaining slabs should be arbitrated or litigated later. However, the trial court denied Portz’s and Area Steel’s motion to arbitrate or litigate any claims on the remaining two slabs. The trial court ruled that the parties only agreed to a two-day arbitration, the parties utilized both days arbitrating the first two slabs, and therefore, Peska had fully exhausted its duty to arbitrate or litigate the remaining issues. Portz and Area Steel appeal. We reverse and remand for arbitration on the remaining two slabs.

FACTS AND PROCEDURAL HISTORY

[¶ 2.] Area Steel was the general contractor on a steel storage budding project, and Peska was the concrete subcontractor. Peska poured four concrete slabs that were to be the buildings’ foundations. The contract required the concrete slabs to be four inches thick. The contract also required Peska to use eighteen-inch by twelve-inch footings under each slab.

[¶ 3.] Peska completed the slabs, but was not paid for its work. Therefore, Pes-ka filed a mechanic’s lien on the property. Peska also filed a complaint against Portz and Area Steel seeking to foreclose the mechanic’s lien. Portz and Area Steel each filed answers and counterclaims alleging that Peska’s work was defective.

[¶ 4.] The alleged defects primarily involved two slabs, but there were problems with all four slabs. One of the slabs was constructed “out of square.” This required Peska to saw off some of the concrete in order to make it square. Also, when Area Steel drilled holes in two slabs to anchor the steel storage buildings, it discovered that the concrete was as little as two inches thick. This lack of thickness adversely affected Area Steel’s ability to anchor the buildings to the concrete. Finally, there were problems with “saw-cuts” and potential water penetration around the sills and doorways of all four slabs.

[¶ 5.] After the foreclosure action was commenced in circuit court, the parties engaged in discovery. The circuit court also held a pretrial conference and filed a scheduling order. However, in April 2001, the parties entered into an Agreement For Voluntary Binding Arbitration and Order. This agreement was approved by the circuit court, and the matter was ordered to binding arbitration under SDCL Ch. 21-25A, South Dakota’s version of the Uniform Arbitration Act.

[¶ 6.] Under the arbitration agreement, the parties expressly agreed to arbitrate *486 “all issues” regarding all four slabs. The parties agreed that those issues would be determined by the pleadings, exhibits, depositions, and other written submissions, as well as live testimony of witnesses and arguments of counsel; however, the agreement further provided that motions to amend the pleadings could be submitted. The agreement also provided that the arbitration was to last two days.

[¶ 7.] The day before arbitration, Ryan Shawd (d/b/a Area Steel), Mr. Portz, attorney Ronald G. Schmidt, and an engineering expert met at the project site. They planned to walk through the site to prepare for the arbitration. While they were inspecting the slabs and buildings, they examined the slab that had been poured out of square. In order to determine if Peska’s repair of that slab resulted in the exposure of any iron reinforcing rods, they began to dig around the foundation. Although they only intended to check on the repair, they inadvertently discovered that the required footing had not been poured under the slab. Those present at the walkthrough then dug around the remaining concrete slabs in fifteen to twenty places. They discovered that the required footings were missing on all four slabs.

[¶ 8.] Portz and Area Steel immediately faxed a proposed amendment to the counterclaims to Peska adding the missing footings claim. As with the prior counterclaims, the proposed amendments related to all four slabs. The proposed amendments significantly increased the damages claimed.

[¶ 9.] Peska immediately opposed the proposed amendment. Peska also objected at the commencement of the arbitration hearing. Peska argued that it did not have an opportunity to investigate the footings claim. Consequently, the arbitrator denied the motion to amend, but he severed the amended counterclaim to allow Peska to investigate the missing footings issue. However, for some reason not disclosed by the parties, the arbitrator then somewhat inconsistently severed all claims on two of the slabs/buildings. He ruled that the parties should later “arbitrate the[se] additional two buildings or present th[e] amended counterclaim to Circuit Court.” Consequently, the missing footings and all previously disclosed claims on those two slabs were severed and deferred for later arbitration. The parties then proceeded to arbitrate all claims, including the missing footings, on the first two slabs.

[¶ 10.] On June 12, 2001, after the arbitration hearing, Peska offered to buy the entire storage property from Portz, “without any discounting for faulty cement work.” This settlement offer included all four slabs. Portz declined the offer.

[¶ 11.] The arbitrator issued his final decision on July 5, 2001. The arbitrator ruled that Peska’s mechanic’s lien could not be enforced on the first two slabs because Peska breached the contract with respect to slab thickness, the lack of footings, and other defects. Portz was awarded $115,200.00 in damages for the removal and replacement of the first two buildings and slabs. Consistent with his prior severance ruling, the arbitrator also “expressed] no decision on the other two slabs and foundations.”

[¶ 12.] Peska satisfied the $115,200.00 award on August 29, 2001. In a letter to Portz accompanying the payment, Peska stated that Peska and Portz “are still negotiating at this time, but [Peska] and [Portz] have agreed upon the payment of this amount at this time, and will continue to attempt negotiations as to settlement of the entire matter.” The parties were, however, unable to reach a settlement on the final two slabs. Therefore, in accordance with the decision of the arbitrator, Portz and Area Steel demanded that the *487 claims on the remaining two slabs either be submitted to arbitration or returned to circuit court. Peska refused either alternative.

[¶ 13.] Portz and Area Steel then moved the circuit court to compel arbitration, or alternatively, to schedule a trial date. The court denied the motion. The court concluded that the arbitrator lacked authority to sever the claims.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Black Hills Surgical Physicians, LLC v. Setliff
2014 SD 68 (South Dakota Supreme Court, 2014)
DT-Trak Consulting, Inc. v. Prue
2012 S.D. 39 (South Dakota Supreme Court, 2012)
Chastain v. Union Security Life Insurance
502 F. Supp. 2d 1072 (C.D. California, 2007)
Spiska Engineering, Inc. v. SPM Thermo-Shield, Inc.
2004 SD 44 (South Dakota Supreme Court, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
2003 SD 136, 672 N.W.2d 483, Counsel Stack Legal Research, https://law.counselstack.com/opinion/peska-construction-co-v-portz-investment-ltd-liability-partnership-sd-2003.