Citizens' Utility Ratepayer Board v. State Corp. Commission

284 P.3d 348, 47 Kan. App. 2d 1112
CourtCourt of Appeals of Kansas
DecidedJuly 27, 2012
DocketNo. 107,897
StatusPublished
Cited by12 cases

This text of 284 P.3d 348 (Citizens' Utility Ratepayer Board v. State Corp. Commission) is published on Counsel Stack Legal Research, covering Court of Appeals of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Citizens' Utility Ratepayer Board v. State Corp. Commission, 284 P.3d 348, 47 Kan. App. 2d 1112 (kanctapp 2012).

Opinion

Hill, J.:

Introduction

This is an appeal from the order of the Kansas Corporation Commission, referred to as the Commission in this opinion, granting the inclusion of $4.5 million for consultant and attorney fees as rate case expenses for Kansas City Power and Light Company, commonly called KCP&L, a public utility regulated by the Commission.

In 2005, KCP&L agreed with the Commission and its staff (Staff), along with other interested parties, to provide for the future energy needs of Kansas energy users by making substantial improvements in the company’s capacity to generate and transmit [1114]*1114electricity. The parties refer to this agreement as the Plan. When the agreement was made, the parties recognized that KCP&L needed to “make substantial investments in its electric infrastructure over a five-year period” to meet the projected future energy demands of its customers in an environmentally friendly way. This meant that the company would make major improvements to its generating station at latan I in Missouri and construct a new coal-fired plant called latan II at the same location. The Plan contemplated that KCP&L would recover tire costs of its investments through a four-step rate increase application process. The rate application that is the subject of this lawsuit is the fourth and last of that series of applications.

The Citizens’ Utility Ratepayer Board, known by its acronym CURB, is a watchdog group formed by the legislature to represent the interests of residential and small commercial ratepayers in such proceedings. See K.S.A. 66-1222(a). CURB entered its appearance in the rate case and made it known that it opposed granting KCP&L any money in excess of $2.1 million for rate case expenses, die amount initially claimed by KCP&L.

In due course, the Commission approved $4.5 million in rate case expenses to KCP&L. Bodi CURB and KCP&L asked the Commission to reconsider its award. CURB contended that the approved amount was too high, while KCP&L thought the amount was too low. After taking additional evidence and entertaining argument on die matter, the Commission once again approved $4.5 million to KCP&L for rate case expenses.

CURB now appeals that award, seeking our review under the Kansas Judicial Review Act, starting at K.S.A. 77-601. CURB attacks the rate case award on three fronts, claiming: (1) The award is not supported by substantial competent evidence when viewed in die light of the record as a whole; (2) the award is unreasonable, arbitrary, and capricious; and (3) the award results in an erroneous interpretation or application of the law.

The Commission appears in defense of its rulings and KCP&L intervenes in support of the Commission’s award.

Given the standard of review and the extensive legislative power of the Commission to set utility rates in Kansas, our review of this [1115]*1115administrative record reveals no good reason to overturn or modify it in any way. Indeed, the Commission did not roll over and play dead here but instead, vigorously challenged KCP&L to prove the necessity and reasonableness of its expenses. We begin by giving a brief history of the events leading up to this controversy. In our view, CURB tries, unreasonably, to restrict the Commission. Using the Commission’s own findings that explain why it quit analyzing billing statements for want of detail and used a lodestar calculation instead, CURB unsuccessfully contends the Commission could not award a sum for expenses that was greater than the original estimate.

Prior rate proceedings led to this lawsuit.

Citing K.S.A. 66-117, KCP&L filed an application with the Commission in December 2009 seeking to change its rates for electricity provided to Kansas consumers. KCP&L requested an 11.5 percent increase in its rates to cover a claimed gross revenue deficiency of over $55 million dollars for a test year ending September 30,2009.

The December 2009 rate application, found at Commission Docket No. 10-KCPE-415-RTS (called the 415 docket by the parties), was the fourth in a series of rate cases anticipated as part of a regulatory plan for KCP&L adopted by the Commission in 2004. That plan was part of a stipulation and agreement entered into by KCP&L, Staff, CURB, and other interested parties. (Docket No. 04-KCPE-1025-GIE). We note the parties settled the first three rate cases in 2006, 2007, and 2009.

As a part of the settlement in the third rate case, the parties agreed that certain issues would be raised in a later docket. Those issues addressed the prudence of certain upgrade costs of KCP&L’s latan I electrical generating facility and other latan common plan improvements. The parties needed to resolve how much of those costs would be included in KCP&L’s rate base. As that docket progressed, other parties also asserted that KCP&L imprudently incurred substantial costs in building the latan II facility and tiróse imprudent costs should be excluded from KCP&L’s rate base.

[1116]*1116After approving a partial settlement, the Commission held evidentiary hearings on KCP&L’s rate application from August through September 2010 to resolve any remaining issues. Widr respect to the latan II construction and improvements, the Commission reviewed prefiled testimony and heard the cross-examination of Walter Drabinski, Staff s expert witness. It was Drabinsld’s opinion that KCP&L had been imprudent in many of its decisions made during the construction of latan II and certain environmental upgrades installed at latan I. Drabinski recommended that a substantial part of the construction costs be excluded from KCP&L’s rate base. The Commission also considered the prefiled testimony and cross-examination of at least six witnesses presented by KCP&L to challenge Drabinski’s opinions about the imprudence of KCP&L’s actions.

In its initial rate case application, KCP&L requested $2.1 million in rate case expenses to be included in its operating expenses. CURB objected later at the evidentiary hearings to any amount of increase in rate case expenses in excess of that requested in the application. CURB asserted that if any additional rate expense was being claimed, CURB had a right to examine the evidence supporting any increase and oppose it. During testimony, CURB’S expert witness gave the opinion that tire original amount of rate case expenses requested was reasonable due to the complexity of the case. However, she testified that if the amount finally requested exceeded the original figure, CURB would not say the larger amount was reasonable. She emphasized the high number of attorneys KCP&L had working on the case and the high hourly rates of those attorneys. The witness offered that some states “have a 50/50 rate case sharing routinely” between the shareholders and rate payers.

Then, in posthearing responses to discovery requests (called data requests in the vernacular of rate cases) KCP&L asserted that rate case expenses for this docket exceeded $8.3 million dollars. This total included $1,169,712 for estimated costs incurred by the Commission and CURB, and $7,149,711 in costs incurred by KCP&L.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ellis v. McNeese
Court of Appeals of Kansas, 2024
Doan Family Corp. v. Arnberger
522 P.3d 364 (Court of Appeals of Kansas, 2022)
Northeast Comanche Tribe, Inc. v. Stumpf
Court of Appeals of Kansas, 2022
In re Equalization Appeal of Kansas Star Casino
Court of Appeals of Kansas, 2021
Richardson v. Murray
Court of Appeals of Kansas, 2020
Consolver v. Hotze
Supreme Court of Kansas, 2017
Kansas City Power & Light Co. v. State Corp. Commission
371 P.3d 923 (Court of Appeals of Kansas, 2016)
Bluestem Telephone Co. v. Kansas Corporation Comm'n
363 P.3d 1115 (Court of Appeals of Kansas, 2015)
Consolver v. Hotze
346 P.3d 1094 (Court of Appeals of Kansas, 2015)
Hays v. Ruther
313 P.3d 782 (Supreme Court of Kansas, 2013)
S&T Telephone Cooperative Ass'n v. State Corp. Commission
291 P.3d 490 (Court of Appeals of Kansas, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
284 P.3d 348, 47 Kan. App. 2d 1112, Counsel Stack Legal Research, https://law.counselstack.com/opinion/citizens-utility-ratepayer-board-v-state-corp-commission-kanctapp-2012.