Citizens Progress Co. v. James O. Held & Co.

438 N.E.2d 1016, 1982 Ind. App. LEXIS 1352
CourtIndiana Court of Appeals
DecidedAugust 17, 1982
Docket2-878A261
StatusPublished
Cited by28 cases

This text of 438 N.E.2d 1016 (Citizens Progress Co. v. James O. Held & Co.) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Citizens Progress Co. v. James O. Held & Co., 438 N.E.2d 1016, 1982 Ind. App. LEXIS 1352 (Ind. Ct. App. 1982).

Opinion

NEAL, Judge.

Plaintiff-appellee James O. Held & Co., Inc. (Held) brought suit for breach of contract against Citizens Progress Company, Inc. (Citizens) in Marion Superior Court. Held claimed Citizens had breached an oral agreement to prepay for material as it arrived in Held’s warehouse. Citizens denied the existence of the agreement and counterclaimed for breach of a written construction contract. After a bench trial the court concluded that neither party was entitled to relief and entered judgment accordingly. Only Citizens appeals.

We affirm.

STATEMENT OF THE FACTS

The facts most favorable to support the judgment are as follows: Citizens was the prime contractor for the construction of buildings, courts, and facilities for tennis and other related activities for Racquet Clubs of America, Inc. (Racquet). Citizens entered into negotiations with Held, a specialty contractor, with the view of subcontracting to Held the installation of interior partitions, walls, flooring, ceilings and other *1018 facilities. Commencing in early 1972 and continuing through the summer and into the fall, Citizens and Held had many conversations and negotiations encompassing cost, time, materials, etc. It was contemplated that many Racquet facilities would be built throughout the United States. Quantity buying with attendant discounts was discussed. The thread of the negotiations contemplated that the material would be stockpiled in Held’s warehouse, and when the metal shell of a Racquet facility was complete, Held would put all the material necessary for its contract on a truck, and with a crew send it to the job site where the work would be expeditiously • completed. Some of the stockpiled material would be Citizens’, bought and paid for by it outside Held’s contract. James 0. Held, Held’s president, testified of his concern as to how his company would be paid; cash flow to pay bills was an important consideration. He stated that storage was important also because Citizens had no place to .store material. Although in the contracting business payments are usually made for 90 percent of the monthly earned estimates, this job was to be different. Held was stockpiling for a number of jobs, and this tied up a lot of money. James Held stated that before Citizens’ letter of intent was issued, Citizens agreed to pay for the material when it reached Held’s warehouse.

On September 27, 1972, at Held’s request, Citizens issued to Held a letter of intent which read as follows:

“This letter will serve as a letter of intent to purchase from you all interior walls, doors and Ceilings as per your quotation for a minimum of six (6) club houses.”

Wynn Fields, Vice President and General Manager of Citizens, acknowledged that the quotation was oral. James 0. Held further testified that the material selection was oral. Thereafter, Held commenced to order material which, when delivered, was stored in its warehouse. Sometime, the record is vague as to when and how, the number of clubhouses was reduced to four. On October 9, 1972, Held issued to Citizens a document entitled “proposal.” An amended version was issued to Citizens on November 8, 1972, entitled proposal no. 951, which stated in pertinent part that:

“Subject to the terms and conditions herein contained we submit this proposal for the installation of: (Listing material and contract price ($11,929))
Terms of payment: net cash on all work started and completed in one calendar month. On all other work, 90% of the contract price of all labor and material furnished during the preceding month shall be paid on the 10th of each month. Final payment shall become due and payable 10 days after completion of the contract. This proposal is subject to written acceptance within 10 days of this date, and will become binding upon us as a contract when finally approved by our Credit department. There are no representations, promises, warranties, agreements, or understandings not expressed herein.”

The proposal was on a printed form and was not addressed to any of the four jobs then being discussed.

On January 31, 1973, Held issued to Citizens invoices for material in their warehouse for each of four contracts, namely, at Lexington, .Kentucky; Lawrence, New York; Fort Wayne, Indiana; and Anderson, Indiana. The billings were on Held’s letterhead, and were identical in terms and amounts, as follows:

“For furnishing and installing Accous-tical Ceilings and Vaughan Walls:
Amount of contract $12,144.00
Value of material and/or work completed to date 7,934.00
Material 7,934.00
Labor -0-
Less 10% retainage 793.40
Difference 7,140.60
Less previous billings -0-
Amount of this billing 7,140.60
Terms of payment: net cash on all work started and completed in one calendar month. On all other work, 90 percent of the contract price of all materials and *1019 labor furnished during the preceding month shall be paid on the 10th of each month. Final payment shall become due and payable 10 days after the completion of the contract.”

On February 6,1973, without having paid the January 31 billings, or disputed them except in regard to their amounts, Citizens issued three purchase orders to Held for contracts at Lexington, Lawrence, and Fort Wayne, which were numbered 3436, 3437, and 3438 respectively, each referring to the November 8, 1972 proposal numbered 951. All three were identical in content, but contained an alteration of the November 8 proposal in that the contract price was $12,-325 instead of $11,929. The purchase orders contained no method of payment. On February 15,1973, Held issued three billings for material in the warehouse to Citizens, one for each of the purchase orders, by number and job. They were identical in amounts and are as follows:

“Amount of contract $12,325.00
Value of work and/or material completed to date 6,284.00
Material 6,284.00
Labor -0-
Less 10% retainage 628.00
Difference 5,656.00
Less previous billings -0-
Amount of this billing 5,656.00’

Testimony by Held witnesses referred to these invoices as amended invoices. They were on the same letterhead, used the same format, and specified the same method of payment as the January 31, 1973 billings.

The crux of the controversy in the appeal is that Held claims that it was entitled to be paid for the material when it reached its warehouse. Held presented evidence that such an oral agreement was made prior to September 27, 1972, and that, when billed, Citizens even came and inventoried the material. Citizens claimed that it was not obligated to pay for the material until it was installed or reached its job site.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stephen Turner v. KLS Services, LLC
Indiana Court of Appeals, 2025
Knutson, Roger v. UGS
Seventh Circuit, 2008
Knutson v. UGS CORP.
526 F.3d 339 (Seventh Circuit, 2008)
Truck City of Gary, Inc. v. Schneider National Leasing
814 N.E.2d 273 (Indiana Court of Appeals, 2004)
Paper Manufacturers Co. v. Rescuers, Inc.
60 F. Supp. 2d 869 (N.D. Indiana, 1999)
Scott v. Scott
668 N.E.2d 691 (Indiana Court of Appeals, 1996)
City of Evansville v. Conley
661 N.E.2d 570 (Indiana Court of Appeals, 1996)
Clarkson v. Whitaker
657 N.E.2d 139 (Indiana Court of Appeals, 1995)
OVRS Acquisition Corp. v. Community Health Services, Inc.
657 N.E.2d 117 (Indiana Court of Appeals, 1995)
Oreck Corp. v. Thomson Consumer Electronics, Inc.
796 F. Supp. 1152 (S.D. Indiana, 1992)
Fordeck-Kemerly Electric, Inc. v. Helmkamp
591 N.E.2d 1035 (Indiana Court of Appeals, 1992)
Sand Creek Country Club, Ltd. v. CSO Architects, Inc.
582 N.E.2d 872 (Indiana Court of Appeals, 1991)
Majd Pour v. Basic American Medical, Inc.
512 N.E.2d 435 (Indiana Court of Appeals, 1987)
Indiana & Michigan Electric Co. v. Terre Haute Industries, Inc.
507 N.E.2d 588 (Indiana Court of Appeals, 1987)
In Re Greives
81 B.R. 912 (N.D. Indiana, 1987)
National Fleet Supply, Inc. v. Fairchild
450 N.E.2d 1015 (Indiana Court of Appeals, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
438 N.E.2d 1016, 1982 Ind. App. LEXIS 1352, Counsel Stack Legal Research, https://law.counselstack.com/opinion/citizens-progress-co-v-james-o-held-co-indctapp-1982.