Stephen Turner v. KLS Services, LLC

Indiana Court of Appeals·Decided February 28, 2025·No. 24A-PL-01512·Published

Opinion

FILED

Feb 28 2025, 9:21 am

CLERK

Indiana Supreme Court

Court of Appeals

and Tax Court

IN THE

Court of Appeals of Indiana Stephen Turner,

Appellant-Defendant

v.

KLS Services, LLC,

Appellee-Plaintiff

February 28, 2025

Court of Appeals Case No.

24A-PL-1512

Appeal from the Hancock Circuit Court The Honorable R. Scott Sirk, Judge Trial Court Cause No.

30C01-2205-PL-706

Opinion by Judge Bradford Judges Bailey and Foley concur.

Court of Appeals of Indiana | Opinion 24A-PL-1512 | February 28, 2025 Page 1 of 13

Bradford, Judge.

Case Summary [1] In early 2020, Stephen Turner contacted KLS Services, LLC (“KLS”), through

its principal Kenneth Shepherd, about building a house for Turner on the lot he owned in Greenfield (“the House”). Shepherd made it clear to Turner that the amount due to KLS would be its actual costs to build the House plus ten percent. Three versions of a written construction contract were prepared and approved by the parties, with the last version listing the price for construction at $180,000.00 and omitting the term regarding the ten percent in order to secure a loan to Turner in that amount from which KLS could draw to cover construction costs.

[2] Construction began in mid-2020 and was completed in August of 2021, and, while KLS received the entirety of the $180,000.00 loan, its total costs ended up being $246,388.76, attributable mostly to a pandemic-related, dramatic increase in the cost of building materials. KLS billed Turner for $264,000.00, and Turner refused to pay. KLS sued Turner for, inter alia, breach of contract, and the trial court entered judgment in favor of KLS for $66,388.76 and denied Turner’s motion to correct error. Turner contends that the trial court abused its discretion in admitting certain evidence, erred in failing to conclude that KLS had waived all claims against Turner by executing a lien waiver, and erred in entering judgment in favor of KLS. We affirm.

Facts and Procedural History [3] In February of 2020, Turner contacted KLS about building him the House.

Three versions of a written construction agreement were prepared, with the second version a modified version of the first, and the third version a further modified version of the second. The first version (executed on April 2, 2020) listed the price to build the House as $150,000.00 plus a fee of ten percent of the cost of building the House. The second version changed the $150,000 to $180,000.00, included the same cost-plus language, and detailed changes to the foundation, septic, drywall, and overall square footage of the House. The third version (the “Third Contract”) provided that “[t]he total price of [the House] is to be paid by the Owner to the Contractor for the completed [House] is $180,000” but did not contain any cost-plus language, which was removed at the urging of a credit-union representative to secure a loan to Turner to finance construction. Appellant’s App. Vol. II p. 62. While Shepherd signed only the first version on behalf of KLS, he acknowledged initialing the second version and the Third Contract. It was understood by all concerned, however, that the price listed in all three versions was an estimate subject to change during construction.

[4] The Third Contract has a clause providing that “[t]his Agreement supersedes and all [sic] previous agreements, either oral or in writing, between the parties hereto with respect to the subject matter of this Agreement.” Appellant’s App.

Vol. II p. 70. The Third Contract, however, does not contain an integration clause stating that it represents the entirety of the agreement between the parties. After executing the Third Contract, Turner secured a loan in the amount of $180,000.00, from which KLS could draw to pay for construction of the House.

[5] Between January of 2020 and June of 2020 (when construction began), the cost of building materials increased between thirty-five and forty percent. Prior to the start of construction, Turner had indicated to Shepherd that the price he wanted to pay for the House was KLS’s costs plus ten percent. Throughout the construction process, KLS would provide Turner with invoices, and Shepherd would discuss the costs with Turner before the work detailed in the invoices was done. Turner and Shepherd frequently met at the construction site to discuss what was being done, the costs of materials, and how construction costs were aligning with Turner’s budget.

[6] Turner moved into the House on August 7, 2021. Pursuant to the draw schedule of Turner’s loan, KLS received the full amount of the loan in August of 2021, and KLS executed a lien waiver as to the House. Construction on the House was completed in September or October of 2021, and, all told, KLS’s costs to build the House came to $246,388.76. On or about November 17, 2021, KLS sent Turner a bill for $264,000.00 (presumably to be offset by the $180,000.00 that KLS had already received), which Turner refused to pay, indicating that he would pay no more than $180,000.00.

[7] On June 1, 2022, KLS filed suit against Turner, alleging breach of contract, unjust enrichment, and quantum meruit. On June 17, 2022, Turner responded and counterclaimed, alleging claims of frivolous claims, breach of contract, and unjust enrichment. A bench trial was conducted over several days beginning in July of 2023 and ending in January of 2024. During trial, Shepherd testified, without objection, that KLS’s total costs to build the House had been $246,388.76. Both parties submitted proposed findings and conclusions, and, on March 28, 2024, the trial court entered judgment in favor of KLS for $66,388.76. On April 15, 2024, Turner moved to correct error, which motion the trial court denied on June 25, 2024.

Discussion and Decision [8] Turner contends that the trial court abused its discretion in denying his motion

to correct error because the judgment it had entered in favor of KLS was clearly erroneous. “[G]enerally, a trial court has wide discretion to correct errors, and we will reverse only for an abuse of that discretion.” Paulsen v. Malone, 880 N.E.2d 312, 313 (Ind. Ct. App. 2008). “An abuse of discretion occurs when the trial court’s action is against the logic and effect of the facts and circumstances before it and the inferences that may be drawn therefrom, or is based on impermissible reasons or considerations.” Id. The alleged error in this case, of course, is the entry of an allegedly erroneous judgment.

[9] Where, as here, both parties submitted proposed findings and conclusions, we

cannot affirm the judgment on any legal basis; rather, this Court must determine whether the trial court’s findings are sufficient to support the judgment. Vanderburgh Co. Bd. of Commissioners v.

Rittenhouse, 575 N.E.2d 663, 665 (Ind. Ct. App. 1991), trans.

denied. In reviewing the judgment, we must first determine whether the evidence supports the findings and second, whether the findings support the judgment. Id. The judgment will be reversed only when clearly erroneous, i.e., when the judgment is unsupported by the findings of fact and conclusions entered on the findings. DeHaan v. DeHaan, 572 N.E.2d 1315, 1320 (Ind. Ct.

App. 1991), trans. denied. Findings of fact are clearly erroneous when the record lacks any evidence or reasonable inferences from the evidence to support them. Id. To determine whether the findings or judgment are clearly erroneous, we consider only the evidence favorable to the judgment and all reasonable inferences flowing therefrom, and we will not reweigh the evidence or assess witness credibility. Id.

Nelson v. Marchand, 691 N.E.2d 1264, 1267 (Ind. Ct. App. 1998).

I. Admission of Evidence [10] Turner contends that the trial court abused its discretion in admitting evidence

regarding several invoices issued by KLS to Turner.

Free access — add to your briefcase to read the full text and ask questions with AI

Stephen Turner v. KLS Services, LLC, (Ind. Ct. App. 2025).

Stephen Turner v. KLS Services, LLC (Stephen Turner v. KLS Services, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Wilson v. State
765 N.E.2d 1265 (Indiana Supreme Court, 2002)
Appleton v. State
740 N.E.2d 122 (Indiana Supreme Court, 2001)
S.C. Nestel, Inc. v. Future Construction Inc.
836 N.E.2d 445 (Indiana Court of Appeals, 2005)
Fleener v. State
656 N.E.2d 1140 (Indiana Supreme Court, 1995)
Parrish v. Terre Haute Savings Bank
431 N.E.2d 132 (Indiana Court of Appeals, 1982)
Herald Telephone v. Fatouros
431 N.E.2d 171 (Indiana Court of Appeals, 1982)
State v. Daily Express, Inc.
465 N.E.2d 764 (Indiana Court of Appeals, 1984)
DeHaan v. DeHaan
572 N.E.2d 1315 (Indiana Court of Appeals, 1991)
Vanderburgh County Board of Commissioners v. Rittenhouse
575 N.E.2d 663 (Indiana Court of Appeals, 1991)
Citizens Progress Co. v. James O. Held & Co.
438 N.E.2d 1016 (Indiana Court of Appeals, 1982)
Adams v. Reinaker
808 N.E.2d 192 (Indiana Court of Appeals, 2004)
SECO CHEMICALS, INC., ETC. v. Stewart
349 N.E.2d 733 (Indiana Court of Appeals, 1976)
Cooley v. State
682 N.E.2d 1277 (Indiana Supreme Court, 1997)
Nelson v. Marchand
691 N.E.2d 1264 (Indiana Court of Appeals, 1998)
Gold v. CEDARVIEW MANAGEMENT CORP.
950 N.E.2d 739 (Indiana Court of Appeals, 2011)
Claire's Boutiques, Inc. v. Brownsburg Station Partners LLC
997 N.E.2d 1093 (Indiana Court of Appeals, 2013)
Peter Griffith v. State of Indiana
31 N.E.3d 965 (Indiana Supreme Court, 2015)
Burton v. Morrow
32 N.E. 921 (Indiana Supreme Court, 1892)
Hubble v. Berry
103 N.E. 328 (Indiana Supreme Court, 1913)