Stephen Turner v. KLS Services, LLC

CourtIndiana Court of Appeals
DecidedFebruary 28, 2025
Docket24A-PL-01512
StatusPublished

This text of Stephen Turner v. KLS Services, LLC (Stephen Turner v. KLS Services, LLC) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stephen Turner v. KLS Services, LLC, (Ind. Ct. App. 2025).

Opinion

FILED Feb 28 2025, 9:21 am

CLERK Indiana Supreme Court Court of Appeals and Tax Court

IN THE

Court of Appeals of Indiana Stephen Turner, Appellant-Defendant

v.

KLS Services, LLC, Appellee-Plaintiff

February 28, 2025 Court of Appeals Case No. 24A-PL-1512 Appeal from the Hancock Circuit Court The Honorable R. Scott Sirk, Judge Trial Court Cause No. 30C01-2205-PL-706

Opinion by Judge Bradford Judges Bailey and Foley concur.

Court of Appeals of Indiana | Opinion 24A-PL-1512 | February 28, 2025 Page 1 of 13 Bradford, Judge.

Case Summary [1] In early 2020, Stephen Turner contacted KLS Services, LLC (“KLS”), through

its principal Kenneth Shepherd, about building a house for Turner on the lot he

owned in Greenfield (“the House”). Shepherd made it clear to Turner that the

amount due to KLS would be its actual costs to build the House plus ten

percent. Three versions of a written construction contract were prepared and

approved by the parties, with the last version listing the price for construction at

$180,000.00 and omitting the term regarding the ten percent in order to secure a

loan to Turner in that amount from which KLS could draw to cover

construction costs.

[2] Construction began in mid-2020 and was completed in August of 2021, and,

while KLS received the entirety of the $180,000.00 loan, its total costs ended up

being $246,388.76, attributable mostly to a pandemic-related, dramatic increase

in the cost of building materials. KLS billed Turner for $264,000.00, and

Turner refused to pay. KLS sued Turner for, inter alia, breach of contract, and

the trial court entered judgment in favor of KLS for $66,388.76 and denied

Turner’s motion to correct error. Turner contends that the trial court abused its

discretion in admitting certain evidence, erred in failing to conclude that KLS

Court of Appeals of Indiana | Opinion 24A-PL-1512 | February 28, 2025 Page 2 of 13 had waived all claims against Turner by executing a lien waiver, and erred in

entering judgment in favor of KLS. We affirm.

Facts and Procedural History [3] In February of 2020, Turner contacted KLS about building him the House.

Three versions of a written construction agreement were prepared, with the

second version a modified version of the first, and the third version a further

modified version of the second. The first version (executed on April 2, 2020)

listed the price to build the House as $150,000.00 plus a fee of ten percent of the

cost of building the House. The second version changed the $150,000 to

$180,000.00, included the same cost-plus language, and detailed changes to the

foundation, septic, drywall, and overall square footage of the House. The third

version (the “Third Contract”) provided that “[t]he total price of [the House] is

to be paid by the Owner to the Contractor for the completed [House] is

$180,000” but did not contain any cost-plus language, which was removed at

the urging of a credit-union representative to secure a loan to Turner to finance

construction. Appellant’s App. Vol. II p. 62. While Shepherd signed only the

first version on behalf of KLS, he acknowledged initialing the second version

and the Third Contract. It was understood by all concerned, however, that the

price listed in all three versions was an estimate subject to change during

construction.

[4] The Third Contract has a clause providing that “[t]his Agreement supersedes

and all [sic] previous agreements, either oral or in writing, between the parties

hereto with respect to the subject matter of this Agreement.” Appellant’s App.

Court of Appeals of Indiana | Opinion 24A-PL-1512 | February 28, 2025 Page 3 of 13 Vol. II p. 70. The Third Contract, however, does not contain an integration

clause stating that it represents the entirety of the agreement between the

parties. After executing the Third Contract, Turner secured a loan in the

amount of $180,000.00, from which KLS could draw to pay for construction of

the House.

[5] Between January of 2020 and June of 2020 (when construction began), the cost

of building materials increased between thirty-five and forty percent. Prior to

the start of construction, Turner had indicated to Shepherd that the price he

wanted to pay for the House was KLS’s costs plus ten percent. Throughout the

construction process, KLS would provide Turner with invoices, and Shepherd

would discuss the costs with Turner before the work detailed in the invoices

was done. Turner and Shepherd frequently met at the construction site to

discuss what was being done, the costs of materials, and how construction costs

were aligning with Turner’s budget.

[6] Turner moved into the House on August 7, 2021. Pursuant to the draw

schedule of Turner’s loan, KLS received the full amount of the loan in August

of 2021, and KLS executed a lien waiver as to the House. Construction on the

House was completed in September or October of 2021, and, all told, KLS’s

costs to build the House came to $246,388.76. On or about November 17,

2021, KLS sent Turner a bill for $264,000.00 (presumably to be offset by the

$180,000.00 that KLS had already received), which Turner refused to pay,

indicating that he would pay no more than $180,000.00.

Court of Appeals of Indiana | Opinion 24A-PL-1512 | February 28, 2025 Page 4 of 13 [7] On June 1, 2022, KLS filed suit against Turner, alleging breach of contract,

unjust enrichment, and quantum meruit. On June 17, 2022, Turner responded

and counterclaimed, alleging claims of frivolous claims, breach of contract, and

unjust enrichment. A bench trial was conducted over several days beginning in

July of 2023 and ending in January of 2024. During trial, Shepherd testified,

without objection, that KLS’s total costs to build the House had been

$246,388.76. Both parties submitted proposed findings and conclusions, and,

on March 28, 2024, the trial court entered judgment in favor of KLS for

$66,388.76. On April 15, 2024, Turner moved to correct error, which motion

the trial court denied on June 25, 2024.

Discussion and Decision [8] Turner contends that the trial court abused its discretion in denying his motion

to correct error because the judgment it had entered in favor of KLS was clearly

erroneous. “[G]enerally, a trial court has wide discretion to correct errors, and

we will reverse only for an abuse of that discretion.” Paulsen v. Malone, 880

N.E.2d 312, 313 (Ind. Ct. App. 2008). “An abuse of discretion occurs when the

trial court’s action is against the logic and effect of the facts and circumstances

before it and the inferences that may be drawn therefrom, or is based on

impermissible reasons or considerations.” Id. The alleged error in this case, of

course, is the entry of an allegedly erroneous judgment.

[9] Where, as here, both parties submitted proposed findings and conclusions, we

cannot affirm the judgment on any legal basis; rather, this Court must determine whether the trial court’s findings are sufficient to support the judgment. Vanderburgh Co. Bd. of Commissioners v.

Court of Appeals of Indiana | Opinion 24A-PL-1512 | February 28, 2025 Page 5 of 13 Rittenhouse, 575 N.E.2d 663, 665 (Ind. Ct. App. 1991), trans. denied.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wilson v. State
765 N.E.2d 1265 (Indiana Supreme Court, 2002)
Appleton v. State
740 N.E.2d 122 (Indiana Supreme Court, 2001)
S.C. Nestel, Inc. v. Future Construction Inc.
836 N.E.2d 445 (Indiana Court of Appeals, 2005)
Fleener v. State
656 N.E.2d 1140 (Indiana Supreme Court, 1995)
Parrish v. Terre Haute Savings Bank
431 N.E.2d 132 (Indiana Court of Appeals, 1982)
Herald Telephone v. Fatouros
431 N.E.2d 171 (Indiana Court of Appeals, 1982)
State v. Daily Express, Inc.
465 N.E.2d 764 (Indiana Court of Appeals, 1984)
DeHaan v. DeHaan
572 N.E.2d 1315 (Indiana Court of Appeals, 1991)
Vanderburgh County Board of Commissioners v. Rittenhouse
575 N.E.2d 663 (Indiana Court of Appeals, 1991)
Citizens Progress Co. v. James O. Held & Co.
438 N.E.2d 1016 (Indiana Court of Appeals, 1982)
Adams v. Reinaker
808 N.E.2d 192 (Indiana Court of Appeals, 2004)
SECO CHEMICALS, INC., ETC. v. Stewart
349 N.E.2d 733 (Indiana Court of Appeals, 1976)
Cooley v. State
682 N.E.2d 1277 (Indiana Supreme Court, 1997)
Nelson v. Marchand
691 N.E.2d 1264 (Indiana Court of Appeals, 1998)
Gold v. CEDARVIEW MANAGEMENT CORP.
950 N.E.2d 739 (Indiana Court of Appeals, 2011)
Claire's Boutiques, Inc. v. Brownsburg Station Partners LLC
997 N.E.2d 1093 (Indiana Court of Appeals, 2013)
Peter Griffith v. State of Indiana
31 N.E.3d 965 (Indiana Supreme Court, 2015)
Burton v. Morrow
32 N.E. 921 (Indiana Supreme Court, 1892)
Hubble v. Berry
103 N.E. 328 (Indiana Supreme Court, 1913)

Cite This Page — Counsel Stack

Bluebook (online)
Stephen Turner v. KLS Services, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stephen-turner-v-kls-services-llc-indctapp-2025.