Chas. H. Tompkins Co. v. Lumbermens Mutual Casualty Co.

732 F. Supp. 1368, 1990 U.S. Dist. LEXIS 3167, 1990 WL 31775
CourtDistrict Court, E.D. Virginia
DecidedMarch 16, 1990
DocketCiv. A. 89-1651-A
StatusPublished
Cited by8 cases

This text of 732 F. Supp. 1368 (Chas. H. Tompkins Co. v. Lumbermens Mutual Casualty Co.) is published on Counsel Stack Legal Research, covering District Court, E.D. Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chas. H. Tompkins Co. v. Lumbermens Mutual Casualty Co., 732 F. Supp. 1368, 1990 U.S. Dist. LEXIS 3167, 1990 WL 31775 (E.D. Va. 1990).

Opinion

MEMORANDUM OPINION

ELLIS, District Judge.

Introduction

This case, simply put, amounts to an effort by plaintiff to stretch a bid bond into a payment and performance bond. The effort fails. A bid bond is separate and distinct from a payment and performance bond; it covers different risks. Here, defendant signed a subcontractor’s bid bond as surety. In conformity with the bid bond, the subcontractor delivered an executed contract for the work to be performed. But in violation of that bond, it failed to furnish a payment and performance bond. Plaintiff, the bid bond obligee, did not declare a breach of the bid bond, as it might have done, but chose instead to permit the subcontractor to proceed with performance. A year and one month later, with the job only partially complete, the subcontractor ceased performance and declared bankruptcy. A payment and performance bond, the usual remedy in these circumstances, did not exist. Thus, plaintiff, in an effort to salvage the situation, has seized on the bid bond and, in a three count complaint, claims (i) that defendant, as bid bond surety, was expressly obligated to furnish a payment and performance bond, (ii) that custom and usage in the *1371 trade created an implied obligation for defendant, as bid bond surety, to issue the payment and performance bond, and (iii) that the failure to furnish a payment and performance bond was a breach of the bid bond entitling plaintiff to the penal sum of the bid bond. For the reasons stated herein, all three counts are fatally infirm. By express agreement between defendant and the subcontractor, defendant’s issuance of the bid bond did not obligate defendant to serve as surety on any future bonds. Additionally, the bid bond expressly required that the subcontractor, not the defendant, procure the payment and performance bond. Nor does custom and usage create any obligations in the context of this case. Moreover, the statute of frauds bars enforcement of such an unwritten agreement. Finally, with respect to the third count, the complaint reflects that the general contractor materially altered the surety’s risk, thereby excusing any obligation. That count also seeks impermissibly to recover payment and performance bond damages on the basis of a stale bid bond breach.

This action is before the Court on defendant’s motion to dismiss. As the Court considered matters outside the complaint, this motion has been treated as one for summary judgment. See Rule 12(b), Fed.R.Civ.P. Because no material fact is genuinely disputed, the matter is ripe for summary disposition. See Rule 56, Fed.R. Civ.P.

Facts

Defendant, Lumbermens Mutual Casualty Company (“Lumbermens”) is an Illinois corporation engaged, inter alia, in the business of acting as surety on bid bonds and on payment and performance bonds. Plaintiff, Chas. H. Tompkins Co. (“Tompkins”), is a District of Columbia corporation engaged in the business of a general contractor. It served as the general contractor on a commercial development project in Alexandria, Virginia known as the Trans Potomac Canal Center (“TPCC”). The owner and developer of TPCC was a Virginia company known now as Savage/Fogarty Real Estate, Inc. (“Savage/Fogarty”).

In early October 1984, Savage/Fogarty invited AMPAT/Southern Corporation (“AMPAT”) to bid on the subcontract for the window wall systems, store front systems and curtain wall work on the TPCC project (“the window wall subcontract”). In this connection, Savage/Fogarty provided AMPAT and other prospective bidders with contract documents and a Bid Form. On October 29, 1984, defendant, pursuant to a contractual relationship it had with AMPAT, executed a bid bond as surety for AMPAT’s bid for the window wall subcontractor. The bid bond named Savage/Fo-garty as the obligee 1 and conditioned payment on AMPAT’s failure, should its bid succeed, to enter “into the [window wall subcontract] in writing, and give bond, with Surety acceptable to the Obligee, for the faithful performance of the said contract.” In the event of a breach of the bid bond, defendant’s obligation was to pay “damages which the Obligee may suffer by reason of such failure, not exceeding the penalty [10% of the bid amount] bond....”

Two days after Lumbermens executed the bid bond as surety, AMPAT submitted the $3.2 million bid for the window wall subcontract work at TPCC. 2 Two months later, on December 26, 1984, AMPAT was notified of its selection as the successful window wall subcontract bidder. Under the Bid Form, AMPAT was required to submit an executed window wall subcontract within 10 days, i.e., by January 5, 1985. Yet for reasons not explained in the record, AMPAT waited until October 1985 to submit a signed window wall subcontract for $2,912,200. 3 Also due by January *1372 5, 1985, in accordance with the terms of the Bid Form and the Bid Bond, was a payment and performance bond. AMPAT never provided this bond. At this point, AMPAT was in default of the Bid Bond condition requiring the furnishing of a payment and performance bond. Tompkins in this circumstance could have taken steps to obtain a payment and performance bond or another subcontractor and compelled AMPAT or defendant to pay for any damages incurred in this regard up to 10% of the bid amount. Tompkins pursued neither of these courses of action, electing instead to permit AM-PAT to begin performance of the contract. In February 1986, AMPAT stopped work and filed a voluntary bankruptcy petition under Chapter 11 of the United States Bankruptcy Code. 4 At this point, AMPAT had completed only 21% of the job, for which it had received $614,896.

In April 1986, Savage/Fogarty contracted with another company to complete the window wall subcontract. This subcontract was for $2,297,304, the precise amount remaining under AMPAT’s contract. Before work could be resumed, however, plaintiff and Savage/Fogarty paid $112,500 to regain shop drawings and materials seized by AMPAT’s secured creditor, the Union Trust Company of Maryland. Count I

Count I alleges that the bid bond imposed an express duty on Lumbermens to issue a payment and performance bond. 5 Tompkins asserts its entitlement to performance of this duty in two capacities: (i) as the third party beneficiary of the bid bond contract between Ampat and Lumber-mens, or (ii) as the assignee of Savage/Fogarty’s rights as bid bond Obligee. In neither capacity, however, can Tompkins succeed.

Tompkins’ third party beneficiary claim is thwarted by the General Agreement of Indemnity (the “Agreement”) between Ampat and Lumbermens. 6 This Agreement is an integral part of the contract between Ampat and Lumbermens governing the issuance of bonds. It provides, in pertinent part, as follows:

[Lumbermens] is not required, by reason of any applications for a bond or by reason of having issued a previous bond or bonds

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Trex Co., Inc. v. ExxonMobil Oil Corp.
234 F. Supp. 2d 572 (E.D. Virginia, 2002)
Continental Insurance v. City of Virginia Beach
908 F. Supp. 341 (E.D. Virginia, 1995)
Derthick v. Bassett-Walker, Inc.
904 F. Supp. 510 (W.D. Virginia, 1995)
Killington, Ltd. v. Richards
641 A.2d 340 (Supreme Court of Vermont, 1993)
Dominion Bank, N.A. v. Westside Station, Inc.
28 Va. Cir. 483 (Winchester County Circuit Court, 1992)
Mergentime Corp. v. Washington Metropolitan Area Transit Authority
775 F. Supp. 14 (District of Columbia, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
732 F. Supp. 1368, 1990 U.S. Dist. LEXIS 3167, 1990 WL 31775, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chas-h-tompkins-co-v-lumbermens-mutual-casualty-co-vaed-1990.