L & M Enterprises, Inc. v. Hartford Accident & Indemnity Co.

700 F. Supp. 517, 1988 U.S. Dist. LEXIS 13500, 1988 WL 128282
CourtDistrict Court, D. Colorado
DecidedNovember 25, 1988
DocketCiv. A. 87-C-1435
StatusPublished
Cited by1 cases

This text of 700 F. Supp. 517 (L & M Enterprises, Inc. v. Hartford Accident & Indemnity Co.) is published on Counsel Stack Legal Research, covering District Court, D. Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
L & M Enterprises, Inc. v. Hartford Accident & Indemnity Co., 700 F. Supp. 517, 1988 U.S. Dist. LEXIS 13500, 1988 WL 128282 (D. Colo. 1988).

Opinion

ORDER

CARRIGAN, District Judge.

Plaintiff L & M Enterprises, Inc. (“L & M”) commenced this action against the defendant Hartford Accident and Indemnity Company (“Hartford”) seeking to recover damages arising out of Hartford’s refusal to issue performance and payment bonds on behalf of the plaintiff. Diversity jurisdiction is alleged to exist pursuant to 28 U.S.C. § 1332.

The following facts appear undisputed: Plaintiff is a landscape contractor based in Berthoud, Colorado. In 1982, it sought to establish a bonding “line of credit” with the defendant Hartford, a Connecticut corporation operating in Colorado. Defendant agreed to consider applications for bonds submitted by the plaintiff on a case by case basis. On March 25, 1982, the parties entered into a General Indemnity Agreement.

In late July 1986, the plaintiff decided to place a bid with the State of Wyoming on a limestone reclamation project known as the Horse Creek Mine Project (the “Horse Creek project”). On July 28, 1986, L & M submitted a request for a bid bond covering the Horse Creek project to Hartford through the Talbert Corporation (“Tal-bert”).

Talbert is an authorized agent of the defendant located in Denver, Colorado. Defendant had authorized Talbert to issue bonds on behalf of the plaintiff in an amount up to $1,500,000 on a single project. In the event that the plaintiff requested a bond for a project with a contract price of more than $1,500,000, Talbert needed to obtain approval of the bond from Hartford’s regional office in Denver before it could issue the bond.

*518 Because the contract price of the Horse Creek project exceeded $1,500,000, Talbert sought approval of the plaintiffs bid bond request from Hartford’s regional office. After determining that the request was within the regional office’s contract of authority, it authorized the issuance of the bid bond, and the bid bond was issued.

The bids for the Horse Creek project were opened on July 29, 1986. Plaintiff’s bid was in the amount of $2,256,338.90, and it was the lowest. The next two lowest bids were in the amounts of $3,786,679 and $4,616,126.

Upon learning of the bid spread, Doug Campbell, of Hartford’s regional office, met with representatives of the plaintiff and received additional information concerning the project and the plaintiff’s bid. During this meeting, representatives of the plaintiff told Campbell that L & M would request performance and payment bonds from the defendant if the project was awarded.

On August 11, 1986, the State of Wyoming awarded the project to L & M, and directed L & M to provide performance and payment bonds within 20 days. Under Hartford’s procedures, the home office needed to approve the issuance of a performance or payment bond if the contractor had submitted a low bid that was less than the second lowest bidder by more than (1) ten percent and (2) two hundred thousand dollars. Accordingly, Campbell forwarded the plaintiff’s request for performance and payment bonds to Hartford’s home office.

After reviewing the project and the plaintiff’s bid, Hartford’s home office decided not to issue the performance and payment bonds, and communicated this decision to the plaintiff on August 12, 1988. Subsequently, L & M advised the defendant of its belief that the State of Wyoming would make a claim on the bid bond since L & M was unable to provide performance and payment bonds, and requested the defendant to reconsider its decision. Hartford reconsidered and on September 26, 1986, it agreed to issue performance and payment bonds subject to certain conditions. However, the plaintiff refused to agree to all of the conditions. Accordingly, the performance and payment bonds were not issued.

The State of Wyoming then contracted with the second lowest bidder and made a demand on Hartford’s bid bond. Defendant paid the State $25,000, and, pursuant to the terms of the General Indemnity Agreement, was reimbursed by the plaintiff in the amount of $25,000.

Plaintiff then commenced this action against Hartford. The amended complaint asserts four claims for relief. The first claim alleges breach of an express contract to issue performance and payment bonds. The second claim alleges breach of an implied contract to issue performance and payment bonds. The third claim alleges tortious interference with contractual relations. The fourth claim alleges tortious or bad faith refusal to issue a payment or performance bond.

Currently pending is the defendant Hartford’s motion for summary judgment. The parties have briefed the issues and oral argument would not materially assist my decision.

Under Fed.R.Civ.P. 56(c), summary judgment is proper “if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and the moving party is entitled to judgment as a matter of law.” Celotex Corp. v. Catrett, 477 U.S. 317, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986). In Catrett the Court held that Rule 56 mandates the entry of summary judgment, after adequate time for discovery and upon motion, against a party who fails to make a showing sufficient to establish the existence of an element essential to that party’s case, and on which that party will bear the burden of proof at trial. Id. at 322, 106 S.Ct. at 2552. The Court explained:

“In such a situation there can be ‘no genuine issue as to any material fact,' since a complete failure of proof concerning an essential element of the nonmov-ing party’s case necessarily renders all other facts immaterial. The moving par *519 ty is ‘entitled to judgment as a matter of law’ because the nonmoving party has failed to make a sufficient showing on an essential element of her case with respect to which she had the burden of proof.” Id. at 322-23, 106 S.Ct. at 2553.

Defendant contends that summary judgment should be granted in its favor on all four of the plaintiffs claims. Specifically, it asserts that the the plaintiffs first claim for relief, for breach of an express contract to issue performance and payment bonds, must fail because the agreement between the plaintiff and the defendant is contained in the unambiguous language of the General Indemnity Agreement, and that Agreement expressly provides that Hartford is not obligated to issue any bond.

Defendant next asserts that the second claim, for breach of implied contract to issue performance and payment bonds, must also fail because where an express contract exists parties cannot abandon the express contract and rely on an implied contract.

Defendant contends that the third claim, for tortious interference with contractual relations, must fail because the plaintiff fails to allege an existing contract between the plaintiff and a third party.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chas. H. Tompkins Co. v. Lumbermens Mutual Casualty Co.
732 F. Supp. 1368 (E.D. Virginia, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
700 F. Supp. 517, 1988 U.S. Dist. LEXIS 13500, 1988 WL 128282, Counsel Stack Legal Research, https://law.counselstack.com/opinion/l-m-enterprises-inc-v-hartford-accident-indemnity-co-cod-1988.