Cedar Lumber, Inc. v. United States

34 Cont. Cas. Fed. 75,399, 13 Cl. Ct. 547, 1987 U.S. Claims LEXIS 205
CourtUnited States Court of Claims
DecidedNovember 3, 1987
DocketNo. 30-87C
StatusPublished
Cited by4 cases

This text of 34 Cont. Cas. Fed. 75,399 (Cedar Lumber, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cedar Lumber, Inc. v. United States, 34 Cont. Cas. Fed. 75,399, 13 Cl. Ct. 547, 1987 U.S. Claims LEXIS 205 (cc 1987).

Opinion

OPINION

BRUGGINK, Judge.

Pending before the court are the parties’ cross motions for summary judgment. After consideration of the written submissions and for the reasons stated herein, defendant’s motion for summary judgment is granted, and plaintiff’s motion for summary judgment is denied.

[548]*548I. FACTUAL BACKGROUND

This action arises out of a contract for the sale of timber between Cedar Lumber, Inc. (“Cedar”) and the United States Forest Service (“Forest Service”). The parties have, over time, entered into a number of such contracts. The one at issue is known as the Upper Sardine Timber Sale. It was entered into on May 5, 1976, and originally had a termination date of March 31, 1981. Pursuant to its terms, Cedar agreed to purchase, cut, and remove certain timber in the Willamette National Forest.

A number of events subsequent to 1976 have impacted on the parties’ obligations under the contract. The termination date was extended on four occasions pursuant to ¶ B8.21 of the contract. That paragraph, in substance, permits contract term adjustments (“CTA’s”) for events beyond Cedar’s control, such as weather or soil conditions. Although the precise number of days of adjustment is disputed, the parties agree that as of December 19, 1980, when the last such CTA was granted, the adjusted termination date became September 4,1984. Because such adjustments are not attributable to the purchaser, they do not occasion resort to other contract provisions requiring a recalculation of payment rates.

The next series of events to impact the contract relate to a class action suit brought by Cedar and others against the Forest Service. North Side Lumber Co. v. Block, No. 83-490 (D.Or. filed April 5, 1983). Among other things, the plaintiff class sought to prevent enforcement of certain timber sale contracts on the ground of commercial impracticability. Intense competition in some areas had bid prices beyond a point at which purchasers could profitably harvest and market timber, particularly in light of the housing recession of 1980-82.1

In July 1983, President Reagan authorized the Secretary of Agriculture to extend certain timber sale contracts beyond then-existing termination dates, for a maximum period of five years. The Forest Service made necessary findings and, accordingly, implemented a new contract extension policy. The hope was that by permitting purchasers to mix old, expensive contracts with new, less expensive ones, they might be able to operate profitably. To be eligible for an extension, a contract had to meet certain initial requirements, and the purchaser had to submit a satisfactory Multiple Sale Extension Plan (“MSEP”). See generally 48 Fed. Reg. 38,862, 40,754, 54,812 (1983).

During pendency of the North Side litigation, the district court issued an order enjoining the Forest Service from enforcing any contract, such as Upper Sardine, which was subject to the MSEP provisions. On September 4, 1984, the Upper Sardine contract was conditionally extended until thirty days after lifting of the North Side injunction.2

The litigation was subsequently settled. The parties here signed an agreement on October 21, 1985.3 Pursuant to the settlement, the Forest Service agreed to accept and approve qualifying contracts. In addition to waiving various claims, Cedar agreed that “its performance obligations under its [MSEP] will be calculated as of January 1, 1986,” and that “any contract included in its approved [MSEP] shall not be subject to any further extension of time.”

On February 4, 1986 Cedar was formally notified that the Forest Service approved its MSEP. Under this plan, the termination date for the Upper Sardine contract was extended to December 31, 1989. On June 23, 1986, the Forest Service sent Ce[549]*549dar an “Agreement to Extend and Modify Timber Sale Contract” as to Upper Sardine, which also states that “timber scaled on or after January 1,1986 will be paid for at the following [redetermined] rates.”4 Cedar protested this rate redetermination in a series of written exchanges with the Forest Service. These culminated in a claim by Cedar for a $48,613.02 adjustment. This was denied in a Contracting Officer (“C.O.”) decision on December 31, 1986 holding that Cedar was not entitled to an adjustment, and that defendant was owed the value of the harvested timber at the redetermined rates. It is defendant’s use of January 1,1986 as the effective date for redetermined rates, as well as defendant’s method of arriving at those rates, which Cedar now challenges. Defendant has counterclaimed for $62,533.87.

Applicable Contract Provisions

The contract contemplates that in the event there have been adjustments made in the termination date under 11 B8.21 (i.e., due to circumstances beyond the purchaser’s control), and the contract term is subsequently extended under 11B8.23 (“at the request of the Purchaser” for a reason that doesn’t qualify under HB8.21 for a CTA), “the appraisal for the extension shall be made as of the unadjusted Termination Date, but the date on which the new rates become effective, if higher than Current Contract Rates immediately prior to Termination Date, shall be the adjusted Termination Date.” 1ÍB8.21. The method for doing the calculation is set out in 11 B8.23: “Forest Service shall make an appraisal using standard Forest Service methods and appraisal data in effect 45 calendar days prior to Termination Date.” The joint operation of these two provisions means that in the event of an extension beyond an already-adjusted termination date, the redetermined rates are calculated as of 45 days prior to the original termination date, but not put into effect until the adjusted termination date. Thus, the higher rates apply only for the period of the extension.

In the present case, there is no question that the original termination date was March 31, 1981 and that several CTA’s adjusted the termination date to September 4,1984. Both sides agree that the contract has been extended beyond that date, however. Accordingly, considering only the contract, and ignoring for the present Cedar’s argument that the settlement agreement and MSEP require a different outcome, the redetermined rates would be calculated by appraising data extant on February 15, 1981 (45 days before the original termination date); they would then be applied as of September 4, 1984, the adjusted termination date.

In fact, although the Forest Service calculated new rates based on February 15, 1981 data, it delayed applying those rates until January 1, 1986. In a letter dated July 15, 1986, the C.O. states that “higher rates have been postponed until January 1, 1986, which is after the adjusted termination date of September 4,1984, based on accumulated CTA days.” In its briefing, the Forest Service contends that Cedar has in effect been given a fifteen month delay in application of the higher rates.

II. DISCUSSION

The motions present two principal questions: As of what date are the redetermined rates calculated; and when do those new rates begin to apply? Resolution of both questions turns on whether and how the MSEP and settlement agreement affect the rate redetermination methodology set out in the contract.

A. Calculation of the Redetermined, Rates

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Alaska American Lumber Co. v. United States
37 Cont. Cas. Fed. 76,286 (Court of Claims, 1992)
Cleek Aviation v. United States
36 Cont. Cas. Fed. 75,815 (Court of Claims, 1990)
Underground Construction Co. v. United States
35 Cont. Cas. Fed. 75,604 (Court of Claims, 1988)
Cedar Lumber, Inc. v. The United States
857 F.2d 765 (Federal Circuit, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
34 Cont. Cas. Fed. 75,399, 13 Cl. Ct. 547, 1987 U.S. Claims LEXIS 205, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cedar-lumber-inc-v-united-states-cc-1987.