Cedar Lumber, Inc. v. The United States

857 F.2d 765, 35 Cont. Cas. Fed. 75,557, 1988 U.S. App. LEXIS 12344, 1988 WL 94391
CourtCourt of Appeals for the Federal Circuit
DecidedSeptember 15, 1988
DocketAppeal 88-1081
StatusPublished
Cited by17 cases

This text of 857 F.2d 765 (Cedar Lumber, Inc. v. The United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cedar Lumber, Inc. v. The United States, 857 F.2d 765, 35 Cont. Cas. Fed. 75,557, 1988 U.S. App. LEXIS 12344, 1988 WL 94391 (Fed. Cir. 1988).

Opinion

RICH, Circuit Judge.

This appeal is from the November 4, 1987, judgment of the United States Claims Court (Bruggink, J.), 13 Cl.Ct. 547 (1987), denying Cedar Lumber's (Cedar's) motion for summary judgment and granting the Government’s cross-motion for summary judgment. We affirm.

BACKGROUND

In 1976, Cedar Lumber entered into a timber sale contract, called the Upper Sardine Timber Sale, with the United States Department of Agriculture, Forest Service (USFS). The contract called for Cedar to purchase, cut, and remove certain timber in the Willamette National Forest, and was originally scheduled to terminate on March 31, 1981. During the term of the contract, the USFS extended the termination date four times, under ¶ B8.21 of the contract. That provision permits contract term adjustments (CTAs) for events beyond Cedar’s control, such as weather or soil conditions, that cause Cedar to lose harvesting days during the Normal Operating Season (NOS) of June 1 through October 31. When the last CTA was granted, the adjusted termination date became September 4, 1984.

Because many timber companies (including Cedar) had bid, and agreed to, purchase prices far in excess of the market price in the late 1970s (presumably expecting existing supplies to remain low and prices to climb), these companies faced a grim economic future several years later when their expectations of high prices for lumber products failed to materialize. It became apparent that the companies could not convert the timber into finished lumber products without incurring substantial losses.

In April 1983, Cedar and several other timber companies filed a class action suit *767 against the Forest Service, seeking, among other things, to prevent enforcement of certain timber sales contracts on the ground of commercial impracticability. North Side Lumber Co. v. Block, Civ. No. 83-490 (D.Or. filed April 5, 1983).

Rather than waiting for timber companies to default on the contracts and resort to bankruptcy, the federal government decided to give qualified companies the option of extending the time specified in the contracts for harvesting the timber. This strategy would allow the companies to mix the timber from the higher-priced contracts with timber harvested under newer, lower-priced contracts, thus achieving a “blending down” of the cost to the companies. The Government also recognized a public interest in softening the economic blow to small- and medium-sized timber companies, in that jobs would be saved and competition in the timber industry would be maintained.

The Government first put this policy into effect through the USFS’s adoption of the Multiple-Sale Extension Program (MSEP) 1 in August and December 1983. The following year, Congress enacted the Federal Timber Contract Payment Modification Act, 2 which codified, with slight alterations, the provisions of MSEP.

As part of a 1985 settlement agreement reached in the North Side litigation, the USFS agreed to accept and approve qualifying contracts under MSEP. On Feb. 4, 1986, the USFS formally notified Cedar that its MSEP was approved. Under this plan, the termination date for the Upper Sardine contract was extended to December 31, 1989. On June 23, 1986, the USFS sent Cedar an “Agreement to Extend and Modify Timber Sale Contract” (Agreement) for the Upper Sardine sale. That proposed agreement included a redetermined rate schedule for “timber scaled on or after January 1, 1986.” Although Cedar’s president signed the modification on August 1, 1986, Cedar protested this rate redetermi-nation, culminating in this lawsuit.

Cedar brought this action in the Claims Court under the Contract Disputes Act, 41 U.S.C. § 601 et seq., challenging a contract officer’s final decision denying Cedar’s claim that the USFS improperly calculated Cedar’s rate redetermination appraisal, under the Agreement executed on August 5, 1986, and incorrectly made the rate effective January 1, 1986. After grant and denial of the cross-motions for summary judgment, this appeal followed.

DISCUSSION

I. USFS Authority to Redetermine Rates

Cedar’s preliminary argument, which it makes for the first time on appeal, is that the USFS was without authority to redetermine rates when it agreed to the contract modification. The Government opposes consideration of this argument, stating the general rule that arguments not presented to the trial court (or initial adjudicatory forum) are deemed waived on appeal. See Borden v. Secretary of Health & Human Servs., 836 F.2d 4, 6 (1st Cir.1987); Kimberlin v. Department of Treasury, 774 F.2d 204, 207 (7th Cir.1985); Sigmon Fuel Co. v. Tennessee Valley Auth., 754 F.2d 162, 164-65 (6th Cir.1985). We agree. Cedar offers no persuasive excuse for its failure to present this argument to the trial court, and the cases that it cites to support consideration of a new argument on appeal are inapposite. We decline to consider Cedar’s “lack of authority” argument.

II. Method Used by USFS to Redetermine Timber Rates

A. Calculation of redetermined rates.

The Claims Court held that the USFS used the correct methods to redetermine and implement timber rates under Cedar’s extended contract. Specifically, the court approved of the USFS’ choice of February 15, 1981 (45 days before the original termination date of the contract) as the date from which the “appraisal data in *768 effect” would be selected, and its choice of January 1, 1986 as the date on which the redetermined rates would go into effect. On the latter point, the court noted that the USFS could have selected an even earlier date, September 4, 1984 (the adjusted termination date of the contract) as the date on which to put the redetermined rates into effect. Instead, USFS chose to be lenient.

Cedar challenges that ruling by urging on this court a reading of the relevant contract terms and governing regulations that would, if accepted, create a needless disharmony among them. The relevant documents that compose the parties’ obligations (original contract, MSEP extension agreement, the settlement agreement, and the MSEP policy statements) almost uniformly concur that any rate reappraisal under an extended contract shall be made using appraisal data in effect 45 days prior to the original termination date.

Cedar seizes upon seemingly contrary language in the USFS’ December 7, 1983 commentary to the MSEP policy.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

MacDonald v. Shulkin
Federal Circuit, 2018
Alpha I, L.P. v. United States
93 Fed. Cl. 280 (Federal Claims, 2010)
Atkins v. Peake
280 F. App'x 986 (Federal Circuit, 2008)
Coast Federal Bank, FSB v. United States
48 Fed. Cl. 402 (Federal Claims, 2000)
Stuckey v. West
13 Vet. App. 163 (Veterans Claims, 1999)
Robin Industries, Inc. v. United States
29 Fed. Cl. 122 (Federal Claims, 1993)
McMillan v. Secretary of Health & Human Services
26 Cl. Ct. 357 (Court of Claims, 1992)
Kollsman v. United States
37 Cont. Cas. Fed. 76,283 (Court of Claims, 1992)
California Sand and Gravel, Inc. v. United States
937 F.2d 624 (Federal Circuit, 1991)
The United States v. Grumman Aerospace Corporation
927 F.2d 575 (Federal Circuit, 1991)
Cleek Aviation v. United States
36 Cont. Cas. Fed. 75,815 (Court of Claims, 1990)
Keene Corp. v. United States
35 Cont. Cas. Fed. 75,670 (Court of Claims, 1989)
Richard R. Radke v. Office of Personnel Management
878 F.2d 1444 (Federal Circuit, 1989)
Underground Construction Co. v. United States
35 Cont. Cas. Fed. 75,604 (Court of Claims, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
857 F.2d 765, 35 Cont. Cas. Fed. 75,557, 1988 U.S. App. LEXIS 12344, 1988 WL 94391, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cedar-lumber-inc-v-the-united-states-cafc-1988.