CED Wheatland v. MPSC

2022 MT 87
Montana Supreme Court·Decided May 10, 2022·No. DA 21-0250·Published

Opinion

05/10/2022

DA 21-0250

Case Number: DA 21-0250

IN THE SUPREME COURT OF THE STATE OF MONTANA 2022 MT 87

CED WHEATLAND WIND, LLC, Petitioner and Appellant, v.

THE MONTANA DEPARTMENT OF PUBLIC SERVICE REGULATION, MONTANA PUBLIC SERVICE COMMISSION and NORTHWESTERN CORPORATION d/b/a NORTHWESTERN ENERGY,

Respondents and Appellees.

CED TETON COUNTY WIND, LLC, and CED PONDERA WIND, LLC, Petitioners and Appellants, v.

THE MONTANA DEPARTMENT OF PUBLIC SERVICE REGULATION, MONTANA PUBLIC SERVICE COMMISSION and NORTHWESTERN CORPORATION d/b/a NORTHWESTERN ENERGY,

Respondent and Appellees, and THE MONTANA CONSUMER COUNSEL, Respondent-Intervenor and Appellee.

APPEAL FROM: District Court of the First Judicial District, In and For the County of Lewis and Clark, Cause No. ADV-2020-1292 Honorable Mike Menahan, Presiding Judge

COUNSEL OF RECORD:

For Appellants:

Michael J. Uda, Anna M. Kecskes, Colson R. Williams, Lowell J. Chandler, Uda Law Firm, P.C., Helena, Montana

For Appellees:

Benjamin J. Alke, Crist, Krogh, Alke & Nord, PLLC, Billings, Montana (for NorthWestern Energy)

Sarah N. Norcott, NorthWestern Energy, Helena, Montana Clark Robert Hensley, NorthWestern Energy, Missoula, Montana Jason Brown, Montana Consumer Counsel, Helena, Montana

Ben W. Reed, Lucas R. Hamilton, Aimee Hawkaluk, Public Service Commission, Helena, Montana

Submitted on Briefs: November 10, 2021 Decided: May 10, 2022

Filed:

q3,,---, 6mal•-.— 4(

Clerk

Justice Laurie McKinnon delivered the Opinion of the Court.

¶1 CED Wheatland Wind, CED Teton County Wind, and CED Pondera Wind—three wholly owned subsidiaries of Consolidated Edison Development (“CED”)—appeal the April 19, 2021, Order on Petitions for Judicial Review issued by the First Judicial District Court, Lewis and Clark County, which partially affirmed and partially reversed two earlier Orders on Reconsideration issued by the Montana Public Service Commission (“The Commission”). The Commission’s orders set the terms and conditions for three CED wind farm projects that were to be undertaken with NorthWestern Energy Corporation (“NorthWestern”). On appeal, CED raises four issues, which we restate as follows:

1. Whether the District Court erred in upholding the Commission’s determination that CED’s three qualifying facilities were responsible for bearing the network upgrade costs required to upgrade NorthWestern’s transmission system for each of the three QFs.

2. Whether the District Court properly upheld the Commission’s decision to calculate avoided energy costs using a proxy model.

3. Whether the District Court properly upheld the Commission’s decision to calculate ancillary service deductions based on NorthWestern’s proposed rates.

4. Whether the District Court properly upheld the Commission’s determination that 15-year contract lengths were appropriate for all three of CED’s projects.

¶2 We affirm in part, reverse in part, and remand for further proceedings.

FACTUAL AND PROCEDURAL BACKGROUND

¶3 Under the Public Utility Regulatory Policies Act of 1978 (“PURPA”), public utility companies are required by federal law to purchase electricity generated by “qualifying . . .

facilit[ies].” 16 U.S.C. § 824a-3(a). NorthWestern, is a public utility company subject to 16 U.S.C. § 824a-3(a). CED Wheatland Wind, LLC, CED Teton County Wind, LLC, and CED Pondera Wind, LLC are self-certified qualifying facilities (“QFs”) under PURPA, which grants them the right to sell energy and capacity to a public utility such as NorthWestern. In the absence of a formal contract between a public utility and a QF, the Federal Energy Regulatory Commission (“FERC”) has stated—under its PURPA authority—that a QF can still sell power to a public utility in the event that a “Legally Enforceable Obligation” (“LEO”) is found to exist between the parties. 18 C.F.R. § 292.304(d)(2).

¶4 Authority to enforce PURPA is also delegated, in part, to state regulatory agencies like the Commission, due to their localized knowledge and expertise. As a result, shortly after PURPA’s passage, Montana enacted its own “Mini-PURPA” law, which provides that if a utility provider and a QF cannot agree on contractual terms, “[t]he [Montana Public Service] Commission shall determine the rates and conditions of the contract upon petition” from either party. Section 69-3-603(2)(a), MCA. CED filed petitions asking the Commission to determine its contract terms with NorthWestern for three projects: a proposed 75-megawatt (“MW”) wind farm to be located in Wheatland County, Montana (“Wheatland facility”), a 19-MW wind farm to be located in Teton County, Montana

(“Teton facility”), and a 20-MW wind farm to be located in Pondera County, Montana (“Pondera facility”).1

¶5 Negotiations between CED and NorthWestern regarding power purchase agreements (PPAs) for each of the three facilities began in July 2018, September 2018, and May 2019 for the Teton, Wheatland, and Pondera facilities, respectively. As part of the negotiation process, CED requested that NorthWestern complete a Large Generation System Impact Study (“LGSIS”) analyzing the potential impact of each facility on NorthWestern’s system. Relating specifically to the Wheatland facility, NorthWestern studied the project as both Network Resource Interconnection Service (“NRIS”) and Energy Resource Interconnection Service (“ERIS”). The LGSIS identified “no additional upgrades beyond the [point of interconnection]” necessary to interconnect through ERIS. However, under NRIS, the LGSIS indicated the Wheatland facility would cause overloads to NorthWestern’s system and identified the corresponding need for a new 230 kilovolt (kV) transmission line to accommodate the increased generation. The LGSIS provided interconnection cost estimates of approximately $6 million for ERIS and $128 million for NRIS, subject to change. CED elected to interconnect through NRIS. The record indicates

1 PURPA and Montana’s “Mini-PURPA” requires that for QFs between 3 and 80 MW avoided-costs be established between the QF and the purchasing public utility through a negotiated contract, on an “as available” basis, or pursuant to an LEO, whereas small QFs under 3 MW receive a standard avoided-cost rate set by the Commission every two years. MTSUN, LLC v. Mont. Dep’t of Pub. Serv. Regulation, 2020 MT 238, ¶ 5, 401 Mont. 324, 472 P.3d 1154 (citations omitted).

CED was aware of the estimated costs for ERIS and NRIS and apparently did not dispute the initial estimates or its responsibility for some of those costs.

¶6 In mid-2019, PPA negotiations for all three facilities stalled. On September 16, 2019, CED filed two separate “Petition[s] to Set Terms and Conditions for a Qualifying Small Power Production Facility Pursuant to [] § 69-3-603[, MCA,]” before the Commission for CED’s Teton and Pondera facilities. Later, on October 4, 2019, CED filed a third petition with the Commission to set the terms for CED’s Wheatland facility (“Wheatland matter”). On October 25, 2019, the Commission consolidated CED’s Teton petition and Pondera petition into a single case before the agency (“Teton-Pondera matter”). The Intervenor in the present matter—the Montana Consumer Counsel (MCC)2—first intervened in both the Teton-Pondera and Wheatland matters before the Commission.

¶7 The Commission held evidentiary hearings in the Teton-Pondera matter from January 22-24, 2020, and entered a Final Order on March 23, 2020 (“Teton-Pondera Final Order”). Both CED and NorthWestern filed motions with the Commission for reconsideration of this decision. On July 9, 2020, the Commission issued its Order on Reconsideration in the Teton-Pondera matter (“Teton-Pondera Reconsideration Order”), which affirmed most aspects of the original Teton-Pondera Final Order.

2 The MCC is an office established by the Montana Constitution to advocate on behalf of the interests of Montana’s utilities consumers. Mont. Const. art. XIII, § 2.

Free access — add to your briefcase to read the full text and ask questions with AI

CED Wheatland v. MPSC, 2022 MT 87 (Mo. 2022).

2022 MT 87 (CED Wheatland v. MPSC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

New York v. Federal Energy Regulatory Commission
535 U.S. 1 (Supreme Court, 2002)
Schlemmer v. North Central Life Insurance
2001 MT 256 (Montana Supreme Court, 2001)
Stevens v. Novartis Pharmaceuticals Corp.
2010 MT 282 (Montana Supreme Court, 2010)
Whitehall Wind, LLC v. Montana Public Service Commission
2010 MT 2 (Montana Supreme Court, 2010)
Krakauer v. State Ex Rel. Commissioner of Higher Education
2016 MT 230 (Montana Supreme Court, 2016)
MTSUN v. PSC
2020 MT 238 (Montana Supreme Court, 2020)
Mcgree Corp. v. Mont. Pub. Serv. Comm'n
2019 MT 75 (Montana Supreme Court, 2019)