C.B.C. Enterprises, Inc. v. United States

37 Cont. Cas. Fed. 76,171, 24 Cl. Ct. 187, 1991 U.S. Claims LEXIS 438, 1991 WL 184882
United States Court of Claims·Decided September 18, 1991·No. No. 91-253C·Published·Cited by 6 cases

Opinion

OPINION

LYDON, Senior Judge:

This government contract case is before the court on the parties’ motions for summary judgment on the issue of liability. Specifically, the issue is whether plaintiff is entitled, as a matter of law, to use the Eichleay formula to calculate plaintiff’s recovery of extended home office overhead expenses. After careful consideration of the parties’ submissions, oral argument having been held on September 17, 1991, the court grants defendant’s motion for summary judgment and denies plaintiff’s motion for summary judgment.1

FACTS

The undisputed facts pertinent to the issue before the court are as follows. Plaintiff C.B.C. Enterprises, Inc. (CBC) entered into a fixed-price contract with the Navy on September 29, 1989 for the construction of certain improvements to Building 250, Marine Corps Air Station, Cherry Point, North Carolina. The original contract price was $927,300, and the original contract was to be completed by July 11, 1990. The contract was subsequently modified several times by the Navy. The present dispute concerns unilateral contract modification P00003 issued by the Navy on June 6, 1990 in the amount of $12,358.46. The direct costs associated with this modification are approximately $10,846, and the remaining $1,512 repre[188]*188sents compensation CBC received for home office overhead expenses based on a overhead rate of 13.94%. The parties used this 13.94% rate to compensate plaintiff for overhead expenses with regard to other changes and modifications to the contract, some of which also extended the contract performance period.

Modification P00003 required CBC to perform additional work primarily involving duct work changes, supporting existing overhead electrical conduit and junction boxes, and installation of flanges and a pancake blank in the existing sprinkler system. Also, various painting requirements were deleted. The parties agreed that the modification would extend the contract performance period by twenty-four days, through August 4, 1990, to accommodate the extra work. This extra work led plaintiff to request an equitable adjustment to the contract price, including the extended home office overhead that is the subject of the parties’ dispute. Subsequent modifications extended the contract completion date through August 24, 1990. CBC completed the contract on August 24, 1990.

Before the Navy unilaterally issued modification P00003, the parties tried to negotiate a bilateral modification concerning the additional work and deletions, which later became the subject of modification P00003, but they were unable to agree on the use of the Eichleay formula as the method for calculating extended home office overhead for the twenty-four day extension of the contract performance period.

In modification P00003, the Navy compensated CBC for $1,512 in home office overhead expenses by applying an overhead rate of 13.94% (general and administrative expense rate) to the additional direct costs $10,846 incurred as a result of P00003. At oral argument, plaintiff explained that the 13.94% rate was utilized by the parties to compensate CBC for overhead expenses on other changes to the contract, some of which extended the contract period by an additional twenty days. With regard to modification P00003, however, plaintiff seeks an additional $13,-805.54 for extended home office overhead expenses, over and above the $1,512 CBC has already received as overhead expenses on this modification. Thus, plaintiff seeks a total of $14,317 for overhead expenses on a modification with direct costs of only $10,846, which amounts to an overhead rate of 132% on this modification. In plaintiff’s view, however, the 13.94% overhead rate did not fully compensate it for extended home office overhead attributable to the additional work. It should be noted, however, that in a document attached to the declaration of plaintiff’s Chief Executive Officer, plaintiff indicates that the percentage of plaintiff’s total overhead expenses attributable to Building 250 is 13.4%, which is strikingly similar to the general overhead expense rate of 13.94% used by the parties to compensate CBC for overhead expenses on other modifications to this contract.

On September 14, 1990, CBC submitted a claim to the contracting officer for uncompensated extended home office overhead costs in the amount of $13,805.54. This amount represents the difference between CBC’s calculation of extended home office overhead using the Eichleay formula, and the Navy’s calculation of home office overhead based on a general and administrative expense rate of 13.94%. The contracting officer denied CBC’s claim by final decision dated November 30, 1990, in which he affirmed the Navy’s position that the Eichleay formula is not appropriate to calculate extended home office overhead damages when the contract performance period is extended due to additional work. According to the Navy, the Eichleay formula may only be used to calculate overhead for suspension of work claims. Plaintiff ostensibly argues that, as a matter of law, the Eichleay formula must be used whenever recovery of extended home office overhead is at issue.

CBC appealed the contracting officer’s decision by filing suit directly in this court on January 29, 1991, pursuant to section 609(a), the direct access provision of the Contract Disputes Act of 1978 (CDA), 41 U.S.C. § 601 et seq. Plaintiff moved for summary judgment on May 6, 1991.

DISCUSSION

The issue before the court is whether, as a matter of law, the Eichleay formula is [189]*189the appropriate and correct method for calculating extended home office overhead resulting from an extension of the contract performance period for additional work.2 For over forty-five years, this court, the Federal Circuit, and their predecessor the Court of Claims consistently have held that a government contractor may recover extended home office overhead as part of damages/equitable adjustments for government-caused delay, suspension or extension of the contract performance period. Capital Elec. Co. v. United States, 729 F.2d 743, 747 (Fed.Cir.1984) (Friedman, J., concurring); see also Luria Bros. & Co. v. United States, 177 Ct.Cl. 676, 369 F.2d 701 (1966); J.D. Hedin Constr. Co. v. United States, 171 Ct.Cl. 70, 347 F.2d 235 (1965); Fred R. Comb Co. v. United States, 103 Ct.Cl. 174 (1945); Wilner Constr. Co. v. United States, 23 Cl.Ct. 241, 260 (1991). The various boards of contract appeals also have consistently allowed recovery of extended home office overhead damages resulting from delay. Capital Electric, supra, 729 F.2d at 747 (Friedman, J., concurring).

The courts and boards apply various methods of calculating extended home office overhead, depending on the circumstances of each case. The seminal case, for present purposes, for recovery of extended home office overhead during periods of delay is Fred R. Comb Co. (Comb),

Free access — add to your briefcase to read the full text and ask questions with AI

C.B.C. Enterprises, Inc. v. United States, 37 Cont. Cas. Fed. 76,171, 24 Cl. Ct. 187, 1991 U.S. Claims LEXIS 438, 1991 WL 184882 (cc 1991).

37 Cont. Cas. Fed. 76,171 (C.B.C. Enterprises, Inc. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Swinerton Builders Northwest
Armed Services Board of Contract Appeals, 2017
Yacht West, Ltd. v. Christensen Shipyards, Ltd.
702 F. Supp. 2d 1292 (D. Oregon, 2010)
American Renovation & Construction Co. v. United States
45 Fed. Cl. 44 (Federal Claims, 1999)
C.B.C. Enterprises, Inc. v. The United States
978 F.2d 669 (Federal Circuit, 1992)
C.B.C. Enterprises, Inc. v. United States
978 F.3d 669 (Federal Circuit, 1992)