Abrams, J.
The plaintiff, William J. Casey, sought a judgment declaring that, pursuant to G. L. c. 166, § 39,
the defend
ant, Massachusetts Electric Company (company), is obliged to assume certain costs, including the cost of temporary removal of its poles, to permit the plaintiff to relocate his home within the city of Lynn. G. L. c. 231A, § 2. A judge of the Superior Court reported four questions to the Appeals Court on a statement of agreed facts. See G. L. c. 231, § 111, third par.; Mass. R. Civ. P. 64, 365 Mass. 831 (1974). We transferred this case to this court on our own motion. We conclude that the company must bear the expenses of the cutting or removal of its “wires” but not the additional expenses incurred in the temporary removal of its poles in order to permit the plaintiff’s home to be moved. We also determine that the principles of primary jurisdiction do not require a reference to the Department of Public Utilities (D.P.U.) in order to obtain a construction of the statute. A declaration of the rights of the parties consistent with this opinion should be entered in the Superior Court. See
Attorney Gen.
v.
Kenco Optics, Inc.,
369 Mass. 412, 418 (1976).
The plaintiff is the owner of several parcels of real estate located in the city of Lynn. This controversy arose out of his recent efforts to transport a single family house from one of those lots to another.
The plaintiff’s plan for the house relocation contemplated that it be moved over Lynn public ways a distance of approximately one and one-half miles. In order for the house to pass unobstructed through the streets, it is necessary that certain overhead electric transmission and distribution lines be temporarily removed. Thus, wires and cables would have to be disconnected. Utility poles also would have to be removed and replaced with temporary structures during the move.
The plaintiff asked the company, which provides electric service to Lynn residents, to perform the necessary work on its lines. The company responded that it would bear the cost of cutting and removal of the wires, but that the plaintiff would have to pay a $15,000 fee before it would move the poles. The plaintiff then served the company with formal notice under G. L. c. 166, § 39, demanding that the company assume all costs related to the temporary removal of its lines.
The company estimated the total cost of the work necessary to permit the house relocation to be approximately $35,000. Of this amount, $20,000 is attributed to expenses directly related to the cutting and removal of wires. The company does not dispute liability for the $20,000 amount. The remaining $15,000, for which the company seeks reimbursement, is ascribed to the projected cost of engineering work to survey the proposed route, temporary construction of pole replacement and associated labor costs.
The judge reported four issues.
1.
Primary jurisdiction.
The company disputes the appropriateness of declaratory relief. It asserts that the doctrine of primary jurisdiction requires that this matter be referred to the D.P.U. for an advisory ruling. See G. L. c. 30A, § 8. The company argues that “matters pertaining to electric utilities are uniquely the province of the DPU,” contending that “the DPU is uniquely able to understand the issue of allocation of house moving costs . . . and ... the larger regulatory structure.” Thus, the company concludes “[this matter should be] considdered by the DPU . . . even if the DPU is unable to provide relief.” We do not agree.
In this case, “[n]o exclusive statutory remedy precludes declaratory relief concerning this controversy.”
Metropolitan Dist. Police Relief Ass’n
v.
Commissioner of Ins.,
347 Mass. 686, 689 (1964). See
New England Power Co.
v.
Selectmen of Amesbury,
389 Mass. 69, 70 n.4 (1983);
School Comm, of Greenfields. Greenfield Educ. Ass’n,
385Mass. 70,76 (1982). The issue is one of statutory construction. Well established is the principle that “[t]he duty of statutory interpretation is for the
courts.”Cleary v. Cardullo’s Inc.,
347Mass. 337,344(1964).
We add that the doctrine of primary jurisdiction requires prior resort to an administrative agency “where that procedure would secure ‘[u]niformity and consistency in the regulation of business entrusted to a particular agency,’ ” or “when the issue involves technical questions of fact uniquely within the expertise and experience of an agency.”
Nader v. Allegheny Airlines,
426 U.S. 290, 303-304 (1976), quoting
Far East Conference v. United States,
342 U.S. 570, 574-575 (1952). See
Murphy v. Administrator of the Div. of Personnel Admin.,
377 Mass. 217, 221 (1979). The doctrine “does not apply, however, when the issue in controversy turns on ques
tians of law which have not been committed to agency discretion.”
Id.
at 221-222.
2.
Construction of § 39.
General Laws c. 166, § 39, as amended by St. 1958, c. 130, provides that if a person seeking to move a building over public ways needs the “wires” of a utility company “cut, disconnected or removed, the company shall forthwith cut, disconnect or remove the same” if such person has first served the company with timely notice of the location of the wires and the time at which the person wants the wires removed. Section 39 further provides that if the company neglects or refuses to cut or remove its wires after a proper request has been made, “the inspector of wires, or the selectmen of a town having no such inspector” may remove the wires and recover of the company the cost of so doing.
The plaintiff asserts that the word “wires” in § 39 is generic and embraces all equipment used to transmit electricity along or across the public ways. “The difficulty with this argument is that it overlooks a salient principle of statutory construction, namely, that the statutory language itself is the principal source of insight into the legislative purpose.”
Hoffman
v.
Howmedica, Inc.,
373 Mass. 32, 37 (1977). “[Statutory language, when clear and unambiguous, must be given its ordinary meaning.”
Bronstein
v.
Prudential Ins. Co.,
390 Mass. 701, 704 (1984).
Hashimi
v.
Kalil,
388 Mass. 607, 610 (1983).
It is clear that the ordinary, lexical meaning of the term “wire”
does not include support structures used in the transmission or distribution of electricity.
Free access — add to your briefcase to read the full text and ask questions with AI
Abrams, J.
The plaintiff, William J. Casey, sought a judgment declaring that, pursuant to G. L. c. 166, § 39,
the defend
ant, Massachusetts Electric Company (company), is obliged to assume certain costs, including the cost of temporary removal of its poles, to permit the plaintiff to relocate his home within the city of Lynn. G. L. c. 231A, § 2. A judge of the Superior Court reported four questions to the Appeals Court on a statement of agreed facts. See G. L. c. 231, § 111, third par.; Mass. R. Civ. P. 64, 365 Mass. 831 (1974). We transferred this case to this court on our own motion. We conclude that the company must bear the expenses of the cutting or removal of its “wires” but not the additional expenses incurred in the temporary removal of its poles in order to permit the plaintiff’s home to be moved. We also determine that the principles of primary jurisdiction do not require a reference to the Department of Public Utilities (D.P.U.) in order to obtain a construction of the statute. A declaration of the rights of the parties consistent with this opinion should be entered in the Superior Court. See
Attorney Gen.
v.
Kenco Optics, Inc.,
369 Mass. 412, 418 (1976).
The plaintiff is the owner of several parcels of real estate located in the city of Lynn. This controversy arose out of his recent efforts to transport a single family house from one of those lots to another.
The plaintiff’s plan for the house relocation contemplated that it be moved over Lynn public ways a distance of approximately one and one-half miles. In order for the house to pass unobstructed through the streets, it is necessary that certain overhead electric transmission and distribution lines be temporarily removed. Thus, wires and cables would have to be disconnected. Utility poles also would have to be removed and replaced with temporary structures during the move.
The plaintiff asked the company, which provides electric service to Lynn residents, to perform the necessary work on its lines. The company responded that it would bear the cost of cutting and removal of the wires, but that the plaintiff would have to pay a $15,000 fee before it would move the poles. The plaintiff then served the company with formal notice under G. L. c. 166, § 39, demanding that the company assume all costs related to the temporary removal of its lines.
The company estimated the total cost of the work necessary to permit the house relocation to be approximately $35,000. Of this amount, $20,000 is attributed to expenses directly related to the cutting and removal of wires. The company does not dispute liability for the $20,000 amount. The remaining $15,000, for which the company seeks reimbursement, is ascribed to the projected cost of engineering work to survey the proposed route, temporary construction of pole replacement and associated labor costs.
The judge reported four issues.
1.
Primary jurisdiction.
The company disputes the appropriateness of declaratory relief. It asserts that the doctrine of primary jurisdiction requires that this matter be referred to the D.P.U. for an advisory ruling. See G. L. c. 30A, § 8. The company argues that “matters pertaining to electric utilities are uniquely the province of the DPU,” contending that “the DPU is uniquely able to understand the issue of allocation of house moving costs . . . and ... the larger regulatory structure.” Thus, the company concludes “[this matter should be] considdered by the DPU . . . even if the DPU is unable to provide relief.” We do not agree.
In this case, “[n]o exclusive statutory remedy precludes declaratory relief concerning this controversy.”
Metropolitan Dist. Police Relief Ass’n
v.
Commissioner of Ins.,
347 Mass. 686, 689 (1964). See
New England Power Co.
v.
Selectmen of Amesbury,
389 Mass. 69, 70 n.4 (1983);
School Comm, of Greenfields. Greenfield Educ. Ass’n,
385Mass. 70,76 (1982). The issue is one of statutory construction. Well established is the principle that “[t]he duty of statutory interpretation is for the
courts.”Cleary v. Cardullo’s Inc.,
347Mass. 337,344(1964).
We add that the doctrine of primary jurisdiction requires prior resort to an administrative agency “where that procedure would secure ‘[u]niformity and consistency in the regulation of business entrusted to a particular agency,’ ” or “when the issue involves technical questions of fact uniquely within the expertise and experience of an agency.”
Nader v. Allegheny Airlines,
426 U.S. 290, 303-304 (1976), quoting
Far East Conference v. United States,
342 U.S. 570, 574-575 (1952). See
Murphy v. Administrator of the Div. of Personnel Admin.,
377 Mass. 217, 221 (1979). The doctrine “does not apply, however, when the issue in controversy turns on ques
tians of law which have not been committed to agency discretion.”
Id.
at 221-222.
2.
Construction of § 39.
General Laws c. 166, § 39, as amended by St. 1958, c. 130, provides that if a person seeking to move a building over public ways needs the “wires” of a utility company “cut, disconnected or removed, the company shall forthwith cut, disconnect or remove the same” if such person has first served the company with timely notice of the location of the wires and the time at which the person wants the wires removed. Section 39 further provides that if the company neglects or refuses to cut or remove its wires after a proper request has been made, “the inspector of wires, or the selectmen of a town having no such inspector” may remove the wires and recover of the company the cost of so doing.
The plaintiff asserts that the word “wires” in § 39 is generic and embraces all equipment used to transmit electricity along or across the public ways. “The difficulty with this argument is that it overlooks a salient principle of statutory construction, namely, that the statutory language itself is the principal source of insight into the legislative purpose.”
Hoffman
v.
Howmedica, Inc.,
373 Mass. 32, 37 (1977). “[Statutory language, when clear and unambiguous, must be given its ordinary meaning.”
Bronstein
v.
Prudential Ins. Co.,
390 Mass. 701, 704 (1984).
Hashimi
v.
Kalil,
388 Mass. 607, 610 (1983).
It is clear that the ordinary, lexical meaning of the term “wire”
does not include support structures used in the transmission or distribution of electricity. In other words, “wire” ordinarily does not mean “pole.” Unless legislative usage of the word “wire” indicates that it has “acquired a peculiar and appropriate meaning in law,” we ascribe to the Legislature an intent to use the term in its ordinary sense. See G. L. c. 4, § 6, Third. See also
Corcoran
v.
S.S. Kresge Co.,
313 Mass. 299, 303 (1943).
We also look to the entire statutory scheme to determine the meaning of the word “wires” since “statutes in the same field are to be construed together, if possible, so as to form an harmonious whole.”
Mercy Hosp.
v.
Rate Setting Comm’n,
381 Mass. 34, 40 (1980).
See Negron
v.
Gordon,
373 Mass. 199, 201 (1977). General Laws c. 166, § 21F, inserted by St. 1969, c. 882, in defining terms states that “temporary relocation” shall mean “removing” or “elevating” electrical conductors from poles.
General Laws c. 166, § 38, provides penalties for the unlawful injury or destruction of “any line, wire, pole, pier or abutment, or any of the materials or property of’ a utility company.
Thus, the term “wire” is used to indicate only one type of utility company equipment, rather than as a generic term throughout G. L. c. 166.
The plaintiff’s contention that such a reading “result[s] in a tortured non-sensical interpretation of the statute” is without merit. The Legislature well could have believed that the company should bear the cost of cutting the wires but need not bear the cost of moving lawfully located poles, which could become very costly for the company and its customers.
We also note that an earlier version of § 39, St. 1869, c. 141, § 1, permitted persons desiring to move a building to “cut or otherwise disconnect the wires of any telegraph company, or to remove them
from the poles or fixtures to which they are attached’
(emphasis supplied).
Nothing in the sub
sequent version of this provision suggests that it should now be construed differently from the earlier enactment. We conclude that the defendant need not bear the costs associated with the temporary removal of its poles or other support structures.
3.
Common law.
The plaintiff argues that the company is under a common law duty to bear the entire cost of removing its equipment from a public way whenever necessary to allow passage of a building along that route.
Relying on
Norfolk Redevelopment & Hous. Auth.
v.
Chesapeake & Potomac Tel. Co.,
464 U.S. 30 (1983), the plaintiff contends that the common law has not been repealed, and that regardless of G. L. c. 166, § 39, the company must bear the entire cost of his house move. We do not agree.
In the
Norfolk
case, a telephone company sought compensation from the local government agency responsible for an urban renewal plan which required the telephone company to relocate some of its transmission facilities.
Id.
at 31-32. In considering whether a Federal statute entitled the telephone company to such compensation, the Court noted that “[u]nder the traditional common law rule, utilities have been required to bear the entire cost of relocating from a public right-of-way whenever requested to do so
by state or local
authorities” (emphasis supplied).
Id.
at 35. See generally 4A Nichols, Eminent Domain § 15.22 (rev. 3d ed. 1981) (grant to utility of permit to use public way is subservient to public travel and to paramount police power). See
United Elec. Light Co.
v.
Deliso Constr. Co.,
315 Mass. 313, 316
(1943); Natick Gas Light Co.
v.
Natick,
175 Mass. 246, 248-249 (1900). The short answer to the plaintiff’s argument is that no public authority has
requested that the company move its facilities. Contrast
Natick Gas, supra
at 247-249 (utility company must bear cost of removing pipes when required to do so by city acting under statutory authority). The principles on which the plaintiff relies are therefore inapplicable to the present case.
Moving a privately owned house is an extraordinary use of the public ways for a purely private purpose. See, e.g.
Tandy
v.
Wichita,
126 Kan. 103, 105 (1928);
Kibbie Tel. Co.
v.
Landphere,
151 Mich. 309, 313-314 (1908);
Collar
v.
Bingham Lake Rural Tel. Co.,
132 Minn. 110,113 (1916);
CentralDist. & Printing Co.
v.
Davis,
17 Pa. D. 1036, 1042 (1908).
Our answers to two of the reported questions are that the company is not under any obligation to assume the costs associated with the temporary removal of its poles to facilitate the plaintiff’s house move, and that because the sole issue is one of statutory construction, the doctrine of primary jurisdiction is not applicable.