Wasserman v. Town of Bellingham

7 Mass. L. Rptr. 40
CourtMassachusetts Superior Court
DecidedMay 27, 1997
DocketNo. 9401070C
StatusPublished
Cited by1 cases

This text of 7 Mass. L. Rptr. 40 (Wasserman v. Town of Bellingham) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wasserman v. Town of Bellingham, 7 Mass. L. Rptr. 40 (Mass. Ct. App. 1997).

Opinion

Sikora, J.

The plaintiffs, Bernard Wasserman and B. Wasserman and Associates (collectively “Wasserman”), brought this action against the defendants, Town of Bellingham (“Bellingham”), Town of Blackstone (“Blackstone"), and Massachusetts Electric Company (“Mass. Electric”), for damages sustained to their property resulting from flooding allegedly caused by the defendants’ negligence. Bellingham moves for summary judgment, asserting that judgment on Wasserman’s claim against it for negligently issuing a building permit is precluded under G.L.c. 258, §10(e). Blackstone also moves for summary judgment under G.L.c. 258, §§10(f) and (j) asserting that Wasserman’s claim is essentially one of negligent inspection or supervision which would not subject a municipality to liability. Mass. Electric moves for partial summary judgment seeking this court to limit its liability, if any, to the period prior to and subsequent to the installation of the utility pole which may have contributed to the flooding.

Upon consideration of the memoranda and arguments of counsel, Bellingham’s motion for summary judgment is ALLOWED, Blackstone’s motion for summary judgment is DENIED, and Mass. Electric’s motion for summary judgment is ALLOWED in part and DENIED in part in accordance with this decision.

BACKGROUND

Wasserman owns a commercial shopping center known as Alouette Plaza (“the Plaza”), which is located partially in the Town of Bellingham and partially in the Town of Blackstone. During the relevant time periods, tenants of the Plaza included Ames Department Store (“Ames”), a bank, and convenience stores. The property adjacent to the Plaza is owned by both Blackstone and Bellingham, with a particular parcel known as Turbesi Park owned entirely by Blackstone.

Beginning in late 1990, Wasserman became aware of water problems in the Plaza which occurred after heavy rainstorms. According to Wasserman, the water problems were “minor," although they required pumping on a periodic basis after heavy rains. According to Wasserman’s deposition testimony, the Plaza had to be pumped numerous times during 1991. During this period, however, the water problems consisted only of minor flooding and did not include any septic problems.

On November 12, 1992, the defendant Mass. Electric installed a utility pole on Diana Street in Blackstone which severed and blocked a drainage pipe near the Plaza that drains water from Turbesi Park. Mass. Electric removed the utility pole on February 1, 1993 and repaired the damaged drainage pipe. Wasserman alleges that the damage to the drainage pipe during this time period contributed to the severe flooding problems. Wasserman further contends that the drainage pipe remained clogged after the pole was removed, thus contributing to the continued flooding. In April of 1993, Mass. Electric asserts that the drainage pipe was unclosed. The plaintiff alleges, however, that the pipe was not fixed for several months after April of 1993.

Beginningin December of 1992, the water problems experienced at the Plaza intensified. Wasserman became aware of sewage backup in the Plaza, particularly on the side of the parking lot where Ames was located. The plaintiffs allege that because the surface water could not drain properly, the water came into the septic system and filled up the chambers, causing effluence to come back out into the parking lot. The improper surface water drainage, they contend, was due to the fact that Turbesi Park, a wetland area, was being illegally filled by Blackstone and by the fact that the severed Diana Street drainage pipe had clogged proper flow from the wetlands. The plaintiffs base this allegation in part on a letter from Frederick DeSimone (“DeSimone”) of Grove Hall Contracting, Inc. (“Grove Hall”), the company which performed some of the pumpingin late 1992 through early 1993. When the intensified flooding occurred, Ames hired Grove Hall to pump the parking lot and to assess why the flooding had begun to [41]*41occur. According to DeSimone, whom the plaintiffs intend to call as a witness at trial, although the dumping in the wetlands was a contributing factor to the flooding, it was not the root cause of the problem. After further investigation, DeSimone concluded that the flooding was directly related to the problems with the severed drainage pipe. At some time between April and December of 1993, once the drainage pipe was repaired and subsequently unclogged, the wetlands began to drain. DeSimone expressed an opinion, however, that the fill in the wetlands had compromised its ability to drain and suggested that the fill be removed in order to resolve the flooding problems.

From December of 1992 until sometime in late 1993, the plaintiffs experienced repeated problems of effluence back-up in the Plaza, requiring frequent pumping at considerable expense. In February of 1993, the Corps of Engineers of the New England Division of the Department of the Army (the “Corps”) sent a letter to Blackstone concerning the illegal dumping of fill in Turbesi Park. The letter indicated that the Corps was conducting an investigation into the dumping as it appeared from the Corps’ records that Blackstone had- not applied for the necessary permit for placing fill in wetland areas.1 In a letter to the Corps dated June 8, 1993, Blackstone acknowledged responsibility for the removal of the fill which had been placed in Turbesi Park. The plaintiffs contend that this acknowledgment is an admission by. Blackstone that it had done the illegal dumping. Blackstone did, in fact, remove fill from part or all of Turbesi Park. Subsequently, the Corps indicated that “[d]ue to the amount of fill in the case and to priorities, the Corps is not pursuing the ease at this time.”

Wasserman filed this action seeking damages against Bellingham, Blackstone, and Mass. Electric, alleging that the negligence of each contributed to the serious flooding problems experienced at the Plaza.2

DISCUSSION

This Court grants summary judgment where there are no genuine issues of material fact and where the moving party is entitled to judgment as a matter of law based upon review of the summary judgment record. Cassesso v. Commissioner of Correction, 390 Mass. 419, 422 (1983); Community Nat’l Bank v. Dawes, 369 Mass. 550, 553 (1976); Mass.R.Civ.P. 56(c). Hie moving party bears the burden of affirmatively demonstrating the absence of a triable issue, and “that the summary judgment record entitles the moving party to judgment as a matter of law.” Pederson v. Time, Inc., 404 Mass. 14, 16-17 (1989). A party moving for summary judgment who does not bear the burden of proof at trial may demonstrate the absence of a triable issue either by submitting affirmative evidence negating an essential element of the nonmoving party’s case or by showing that the nonmoving party is unlikely to submit proof of that element at trial. Flesner v. Technical Communications Corp., 410 Mass. 805, 809 (1991); Kourouvacilis v. General Motors Corp., 410 Mass. 706, 716 (1991). The nonmoving party cannot defeat the motion for summary judgment by resting on its “pleadings and mere assertions of disputed facts ...” LaLonde v. Eissner, 405 Mass. 207, 209 (1989). If a case only involves a question of law, a court will grant summary judgment to the party entitled to judgment as a matter of law. Cassesso v. Commissioner of Correction, 390 Mass. 419, 422 (1983).

I. Bellingham’s Motion for Summary Judgment

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Melanson v. Commonwealth
15 Mass. L. Rptr. 387 (Massachusetts Superior Court, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
7 Mass. L. Rptr. 40, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wasserman-v-town-of-bellingham-masssuperct-1997.