United Electric Light Co. v. Deliso Construction Co.

52 N.E.2d 553, 315 Mass. 313, 1943 Mass. LEXIS 956
CourtMassachusetts Supreme Judicial Court
DecidedDecember 29, 1943
StatusPublished
Cited by55 cases

This text of 52 N.E.2d 553 (United Electric Light Co. v. Deliso Construction Co.) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United Electric Light Co. v. Deliso Construction Co., 52 N.E.2d 553, 315 Mass. 313, 1943 Mass. LEXIS 956 (Mass. 1943).

Opinion

Ronan, J.

This is an action of tort to recover for damage to the plaintiff’s conduit lines and manholes, located underground in Columbus Avenue, a public way in Springfield, which it was alleged was caused by the defendant while it was engaged in performing a written contract made with the city of Springfield for the construction of a tunnel, six feet in diameter, with outside circular steel walls, for the purpose of containing a sewer line. There was evidence that steel plates were put in place as the tunnel progressed, and through holes in these plates a mixture of cement and water, known as “grout,” which was subjected to a pressure of fifty pounds per square inch, was discharged by a nozzle for the purpose of forming a cement crust on the outside top of the tunnel and of filling in the fissures in the earth which arose from the construction of the tunnel. The top of this tunnel was twenty-three and one half feet below the surface of Columbus Avenue at Pynchon Street and about twenty-three feet below the surface of this avenue at Worthington Street. The plaintiff had built a manhole near each of these points on Columbus Avenue, and a conduit consisting of a cement envelope containing tile conduits led into and from each manhole. The conduits were about two and one half feet high and their top was about three feet below the surface of Columbus Avenue. The manholes were seven [315]*315and one half to eight feet deep and had sand bottoms. There was evidence that cement was found in these manholes and conduits; and that cement appeared at two places upon the surface of this street and in the cellar of a business building located outside the limits of the way. The city had made borings along the proposed location of the tunnel, and the estimate contained in the contract as the amount of cement that would be required for these grouting operations was stated to be ten thousand bags. There was testimony that more than thirty-five thousand bags were actually used for which the defendant was paid at the rate of $2 a bag. There was testimony that the cement had hardened in the plaintiff’s underground structure; and that it was necessary to remove it from the manholes by chipping it with an air compressor, and to remove some of the conduits and to substitute new ones at a cost to the plaintiff of a little more than $4,800. The jury could find that the cement deposited in the plaintiff’s underground system came from the grouting operations of the defendant.

The plaintiff’s declaration contained four counts, the first for negligence, the second for a nuisance, the third for the escape of a dangerous instrumentality and the fourth for trespass. The judge, subject to the plaintiff’s exception, directed a verdict for the defendant on each of the last three counts. The jury returned a verdict for the defendant upon the first count. The only other exception saved by the plaintiff was to the limitation upon the admission in evidence of a provision of the contract, introduced in evidence, between the defendant and the city obligating the defendant to exercise care so as not to injure underground pipes, conduits and other structures in the street, and putting a duty upon the defendant to repair at its expense any damage that might be incurred by these structures, which the judge refused to permit the jury to consider as any evidence of the duty that the defendant owed to the plaintiff.

The plaintiff’s manholes and conduits could be found to have been lawfully laid in the public way in accordance with permits duly granted in 1900 and 1921 by the proper municipal authorities to whom that power had been granted by [316]*316R. L. c. 122, § 2, G. L. c. 166, § 22. The effect of the permits, however, was to authorize the location of these structures which would otherwise constitute a nuisance. Commonwealth v. Boston, 97 Mass. 555. Lynch v. Lowell Electric Light Corp. 263 Mass. 81. The plaintiff by virtue of the permits secured the privilege of sharing in a common right, the enjoyment of which was in the public at large, and the participation in this common right by the plaintiff by constructing and maintaining its structures for the use of the public, or that portion thereof that desired to use the facilities furnished by the plaintiff, did not impose an additional servitude upon the way for it was a use of the way that was included within the purposes for which it was taken, laid out and constructed. The rights of the owners of the lands abutting the way, although they owned the fee, were not impaired by the installation and maintenance of this underground system. Pierce v. Drew, 136 Mass. 75. Lincoln v. Commonwealth, 164 Mass. 1. Bishop v. North Adams Fire District, 167 Mass. 364. Sears v. Crocker, 184 Mass. 586. Cheney v. Barker, 198 Mass. 356. Centehar v. Selectmen of Watertown, 268 Mass. 121.

The permits did not give the plaintiff any title or proprietary interest in that part of the way that was occupied by its structures, and if the city acting under the power of eminent domain changed the grade of the way or even discontinued it, the plaintiff would have no claim for damages, even if it sustained a loss of these structures which could not be removed without destroying them. Natick Gas Light Co. v. Natick, 175 Mass. 246. New England Telephone & Telegraph Co. v. Boston Terminal Co. 182 Mass. 397. Boston Electric Light Co. v. Boston Terminal Co. 184 Mass. 566. Boston, Worcester & New York Street Railway v. Commonwealth, 301 Mass. 283.

The plaintiff, although without any proprietary interest in the land, and notwithstanding its allegation that the manholes and conduits constituted “the plaintiff’s close,” was the owner of the equipment which it had installed in the way. This equipment did not become a part of the realty but was the personal property of the plaintiff which re[317]*317mained in its custody and possession. Lorain Steel Co. v. Norfolk & Bristol Street Railway, 187 Mass. 500. French v. Jones, 191 Mass. 522. Hunt Drug Co. v. Hubert, 298 Mass. 195.

It is settled by the verdict returned for the defendant on the count for negligence, to which no exceptions by the plaintiff are pending, that the damage sustained by the plaintiff was not caused by any negligence of the defendant, and the question presented is whether the evidence was sufficient to maintain any of the causes of action set forth in the last three counts of the declaration.

We first consider the count in trespass. The plaintiff was not a licensee toward the defendant but was lawfully occupying a portion of the underground of the street by virtue of its permits. The defendant was also lawfully occupying another portion of this underground area by virtue of its contract with the city. Both were occupying entirely different portions of the way. There was no evidence that the construction of the sewer would necessarily result in damage to the plaintiff’s property. The plaintiff’s system had been installed years before the defendant began the construction of the sewer, and the plaintiff, so far as the defendant was concerned, was entitled to enjoy its property free from any damage caused by the negligence of the defendant and from any interference due to any trespass by the defendant. Alabama Power Co. v. Guntersville, 236 Ala. 503. New Hartford Water Co. v. Village Water Co. 87 Conn. 183. Tri-County Electric Membership Corp.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kennedy v. Osmanski, III
D. Massachusetts, 2025
Ho v. Winchester Boat Club
Massachusetts Land Court, 2021
Alleyne v. Diageo USVI, Inc.
63 V.I. 384 (Superior Court of The Virgin Islands, 2015)
Field v. Hughes-Birch (In re Hughes-Birch)
499 B.R. 134 (D. Massachusetts, 2013)
Shapiro v. City of Worcester
29 Mass. L. Rptr. 551 (Massachusetts Superior Court, 2011)
Robbins v. City of Worcester
27 Mass. L. Rptr. 470 (Massachusetts Superior Court, 2010)
Woods v. Brimm
27 Mass. L. Rptr. 389 (Massachusetts Superior Court, 2010)
Tsivitsi v. City of Worcester
26 Mass. L. Rptr. 491 (Massachusetts Superior Court, 2010)
Wynn v. Rudack
25 Mass. L. Rptr. 587 (Massachusetts Superior Court, 2009)
Drury v. Drury
25 Mass. L. Rptr. 513 (Massachusetts Superior Court, 2009)
Sprint Communications Co. v. Western Innovations, Inc.
618 F. Supp. 2d 1101 (D. Arizona, 2009)
Jupin v. Kask
447 Mass. 141 (Massachusetts Supreme Judicial Court, 2006)
Commonwealth v. Santos
792 N.E.2d 702 (Massachusetts Appeals Court, 2003)
McBarron v. Arena
10 Mass. L. Rptr. 576 (Massachusetts Superior Court, 1999)
Rubin v. Walpate Construction Management, Inc.
10 Mass. L. Rptr. 377 (Massachusetts Superior Court, 1999)
Castano v. New England Telephone
7 Mass. L. Rptr. 69 (Massachusetts Superior Court, 1997)
Ronan v. Kuvin
7 Mass. L. Rptr. 15 (Massachusetts Superior Court, 1997)
Posco Investment Corp. v. Commonwealth
5 Mass. L. Rptr. 50 (Massachusetts Superior Court, 1996)
McLaughlin v. Watts
3 Mass. L. Rptr. 275 (Massachusetts Superior Court, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
52 N.E.2d 553, 315 Mass. 313, 1943 Mass. LEXIS 956, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-electric-light-co-v-deliso-construction-co-mass-1943.