Carson Hybrid Energy Storage v. Turlock Irrigation District CA5

CourtCalifornia Court of Appeal
DecidedFebruary 5, 2025
DocketF087073A
StatusUnpublished

This text of Carson Hybrid Energy Storage v. Turlock Irrigation District CA5 (Carson Hybrid Energy Storage v. Turlock Irrigation District CA5) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Carson Hybrid Energy Storage v. Turlock Irrigation District CA5, (Cal. Ct. App. 2025).

Opinion

Filed 2/5/25 Carson Hybrid Energy Storage v. Turlock Irrigation District CA5 Opinion following Rehearing

NOT TO BE PUBLISHED IN THE OFFICIAL REPORTS California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication or ordered published for purposes of rule 8.1115.

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA

FIFTH APPELLATE DISTRICT

CARSON HYBRID ENERGY STORAGE, LLC., et al., F087073

Plaintiffs and Appellants, (Super. Ct. No. CV-23-001227)

v. OPINION TURLOCK IRRIGATION DISTRICT, et al.,

Defendants and Respondents.

APPEAL from an order of the Superior Court of Stanislaus County. Sonny S. Sandhu, Judge. Duran and Cedillo and Manuel Duran for Plaintiffs and Appellants. Duncan and Allen and Jon R. Stickman for Defendants and Respondents. -ooOoo- Plaintiffs Carson Hybrid Energy Storage, LLC and CMD Carson, LLC (collectively “Carson”) appeal the trial court’s order dismissing Carson’s complaint with prejudice after the court sustained defendant Turlock Irrigation District’s (“Turlock”) demurrer. The court found that Carson’s complaint was preempted due to ongoing administrative proceedings before the Federal Energy Regulatory Commission (FERC) under the Federal Power Act (FPA). (See 16 U.S.C. §§ 824 et seq.) We originally filed an opinion reversing the judgment. However, we granted Turlock’s petition for rehearing to consider the impact of new proceedings before FERC that occurred while this appeal was pending. We reaffirm our earlier decision and reverse the judgment. BACKGROUND Carson’s Complaint On March 9, 2023, Carson filed a complaint in Stanislaus County alleging, in relevant part, the following: Turlock operates as a public corporation that provides electricity services to ratepayers and other utilities. Relevant here, Turlock provides “non-discriminatory transmission access” to other utilities, meaning Turlock “awards interconnection requests and transmission services on a first come first serve equal basis, without regard to project owner.” Carson, a private company, needed to interconnect a future energy storage project with Turlock’s transmission system to sell energy to the electrical grid. On January 7, 2021, the parties entered into an Interconnection System Impact Study Agreement (ISISA). In return for Carson’s deposit and funding, Turlock would issue a report consistent with the ISISA’s parameters within six to nine months detailing the projected impact of Carson’s project on Turlock’s system, estimating Carson’s costs to upgrade any necessary equipment to secure interconnection, and projecting the time to complete interconnection. Beyond Carson’s deposit, Turlock would invoice Carson for any necessary work, provide those invoices to Carson, and reconcile any discrepancies upon the report’s completion. Turlock also placed Carson’s project in its interconnection queue. Turlock informed Carson only one project preceded Carson’s project, but Carson later came to believe that Turlock impermissibly placed its own competing energy storage project ahead of Carson’s project in the queue.

2. Over the next two years, various disputes regarding the ISISA arose forming the basis for Carson’s allegations that Turlock breached the ISISA by: (1) failing to utilize the correct modeling parameters specified in the ISISA; (2) utilizing modeling parameters not provided in the ISISA; (3) failing to provide analysis and models required by the ISISA; (4) failing to provide information required by Section 5.0 of the ISISA; (5) impermissibly delaying the interconnection study for various improper reasons; (6) refusing to provide invoices; (7) refusing to permit Carson to arrange relationships with third-party vendors pursuant to Section 7.1 of the ISISA; (8) failing to communicate with the California Independent System Operator (CAISO) as required by Attachment A to the ISISA; and (9) threatening to withdraw Carson’s interconnection request unless Carson provided an additional $150,000 within 30 days for Turlock to proceed with the next study, the Interconnection Facilities Study (IFS), where Turlock has not, according to Carson, completed the first study under the ISISA. Carson requested that the trial court award injunctive relief to prevent Turlock from (1) enforcing the deadline to fund the $150,000 for the IFS until Turlock completes the deficient ISISA report, (2) removing Carson’s project from the interconnection queue, and (3) considering its own competing project before Carson’s project. Carson also requested that the court order Turlock to specifically perform the obligations Carson contended Turlock failed to perform. FERC Proceedings On February 10, 2023, plaintiff CMD Carson, LLC (CMD) filed an application with the FERC under sections 210 and 211 (16 U.S.C. §§ 824i, 824j) of the FPA for an order directing Turlock to provide interconnection and transmission services for Carson’s project. The factual allegations in CMD’s application were substantially the same as

3. those in its complaint.1 However, CMD did not request that FERC issue the relief requested in Carson’s complaint. Turlock filed, in relevant part, a protest and motion to hold the FERC proceedings in abeyance pending the completion of the study process, upgrades, and new facilities. Turlock argued that ordering interconnection prior to the completion of the above would not meet the “requirements of sections 210, 211, 212, and 213 of the FPA and section 2.20 of the Commission’s Regulations.” Turlock further argued a premature order would “jeopardize [the] reliability of Turlock’s system and compel ratepayers to subsidize provision of service to [CMD] because Turlock would have to pay for upgrades to avoid exposing its system to reliability risks.” Finally, Turlock contended that, absent the agreements required for the full study and interconnection process, Turlock could not ensure the project would conform to Turlock’s operating criteria, and, without an IRS Private Letter Ruling, “would jeopardize the tax-exempt status of the bonds that Turlock used to finance its transmission system.” With respect to Turlock’s request for abeyance, CMD argued that all issues need not be resolved prior to a preliminary order requiring interconnection. CMD admitted it was “willing to agree to and pay for further studies, but Carson would like those agreements to be made under the Commission’s oversight.” Otherwise, Carson opposed Turlock’s protest and request for abeyance. On May 22, 2023, FERC granted Turlock’s request to hold the proceedings in abeyance “pending the necessary interconnection and transmission studies.” Specifically, it found “that an abeyance is warranted because Turlock has stated that it is ready and willing to provide service and that it will require a section 211 order to protect the tax- exempt status of its bonds. An abeyance will provide the parties time to continue moving

1 Absent from our record, among other things, is CMD’s application and Turlock’s protest and motion. However, FERC’s May 22, 2023, order summarizes both.

4. through Turlock’s procedures by completing the necessary studies and identifying needed upgrades. Turlock has indicated that an [IFS], a Transmission System Impact Study, and a Transmission Facilities Study still need to be completed.” (Fn. omitted.) FERC indicated that it “require[d] additional information” to issue a final order.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nantahala Power & Light Co. v. Thornburg
476 U.S. 953 (Supreme Court, 1986)
Reiter v. Cooper
507 U.S. 258 (Supreme Court, 1993)
Crosby v. National Foreign Trade Council
530 U.S. 363 (Supreme Court, 2000)
Farmers Insurance Exchange v. Superior Court
826 P.2d 730 (California Supreme Court, 1992)
Walker v. Superior Court
807 P.2d 418 (California Supreme Court, 1991)
Wholesale Electricity Antitrust Cases I & II
55 Cal. Rptr. 3d 253 (California Court of Appeal, 2007)
Brehm v. 21st Century Insurance
166 Cal. App. 4th 1225 (California Court of Appeal, 2008)
Schmidlin v. City of Palo Alto
69 Cal. Rptr. 3d 365 (California Court of Appeal, 2008)
In Re Electric Refund Cases
184 Cal. App. 4th 1490 (California Court of Appeal, 2010)
Southern California Edison Co. v. Public Utilities Commission
18 Cal. Rptr. 3d 435 (California Court of Appeal, 2004)
McKenney v. Purepac Pharmaceutical Co.
167 Cal. App. 4th 72 (California Court of Appeal, 2008)
Gallivan v. AT & T CORP.
21 Cal. Rptr. 3d 898 (California Court of Appeal, 2004)
Forsyth v. Jones
57 Cal. App. 4th 776 (California Court of Appeal, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
Carson Hybrid Energy Storage v. Turlock Irrigation District CA5, Counsel Stack Legal Research, https://law.counselstack.com/opinion/carson-hybrid-energy-storage-v-turlock-irrigation-district-ca5-calctapp-2025.