Carr Business Enterprises, Inc. v. City of Chowchilla

166 Cal. App. 4th 14, 82 Cal. Rptr. 3d 128, 2008 Cal. App. LEXIS 1333
California Court of Appeal·Decided August 20, 2008·No. F051999·Published·Cited by 28 cases

Opinion

Opinion

WISEMAN, J.

In the published portion of this opinion, we affirm the denial of a request for contractual attorney fees, concluding that the provision relied upon to authorize fees is a standard indemnity clause. We conclude these types of provisions do not create a reciprocal right to fees, despite a reference to performance of work under the contract.

In the unpublished portion of the opinion, we affirm an award of prejudgment interest payable on retention damages from the date the contract work was completed, despite the existence of offset claims and a dispute regarding liability.

*17 PROCEDURAL AND FACTUAL HISTORIES

In 1996, the City of Chowchilla (Chowchilla) contracted, in two separate agreements, with Carr Business Enterprises, Inc. (Carr), to do some improvement work on city streets and at the municipal airport. Insurance Company of the West (West) supplied the performance bond for Carr on the construction projects. A series of problems arose delaying the work, which was not finished within the contractual timeframe. Both projects ultimately were completed by July 1997. Additional costs were incurred by Carr, which Chowchilla refused to pay, and litigation followed, with Carr suing Chowchilla. In a cross-complaint, Chowchilla named Carr and West as cross-defendants.

By stipulation, the case was submitted to a referee. (Code Civ. Proc., § 638.) The referee was asked to try all issues of fact and law raised by the pleadings. After a lengthy trial, the referee issued a detailed statement of decision, finding for the most part in favor of Carr and West. 1 The referee awarded a total amount of $613,427.07 in damages, including $92,051.55 in retention damages; $126,017.31 in interest on the retention damages pursuant to Public Contracts Code section 7107; $34,129.62 for extra work performed but not compensated; and $361,228.59 in delay damages, including $32,838.96 for lost profits.

Chowchilla moved for a new trial. The trial court granted the motion and Carr appealed. In an opinion filed on March 14, 2006 (Carr Business Enterprises, Inc. v. City of Chowchilla, supra, F044630), we reversed the order granting a new trial, but held that the interest awarded by the referee pursuant to Public Contracts Code section 7107 was improper. We remanded for the trial court to determine whether Carr was entitled to prejudgment interest under some other authority and, if so, the amount. The trial court was advised to enter a new judgment in favor of Carr in the amount of $454,570.80, plus any prejudgment interest on retention damages found.

Upon remand, Carr and West filed their memorandum of costs and moved to fix attorney fees, including fees incurred on the first appeal, as an element of costs pursuant to a provision found in both the street-improvement contract *18 and the airport-improvement contract. Chowchilla opposed the motion to fix attorney fees as costs, argued against prejudgment interest, and filed a motion to tax costs. The matters were all heard on the same date.

After further proceedings, the trial court found that the retention damages were liquidated pursuant to Civil Code 2 section 3287, subdivision (a), and awarded Carr $81,686.28 as prejudgment interest on the retention damages. The trial court denied the request for fees, finding that the provision relied upon was a standard indemnity clause and therefore not a reciprocal-fee provision. The rulings on the motion to tax costs, the motion to fix attorney fees, and the motion to determine recoverability of prejudgment interest were incorporated into the final judgment, which was entered on October 17, 2006.

Chowchilla appealed, challenging the award of prejudgment interest. Carr and West filed cross-appeals contesting the denial of attorney fees.

DISCUSSION

I. Prejudgment interest *

II. Attorney fees

A., B. *

C. Contract provisions

Carr and West contend that the trial court erred in denying their request for attorney fees by improperly interpreting section 10 of the street-improvement contract and section 11 of the airport-improvement contract as standard indemnity provisions, applicable only to third party claims. Both argue that the provisions contemplate not only third party claims, but also claims on the contract itself.

*19 “Where a contract provides for attorney fees in an action to enforce the contract, the attorney fees provision is made applicable to the entire contract by operation of Civil Code section 1717. [Citations.]” 4 (Myers Building Industries, Ltd. v. Interface Technology, Inc. (1993) 13 Cal.App.4th 949, 968 [17 Cal.Rptr.2d 242] (Myers).) Attorney fees authorized by contract are recoverable as costs pursuant to Code of Civil Procedure section 1033.5, subdivision (a)(10)(A). (Bankes v. Lucas (1992) 9 Cal.App.4th 365, 370-371 [11 Cal.Rptr.2d 723].) Under the American rule, attorney fees are not recoverable as costs unless expressly authorized by statute or contract. (Selma Auto Mall II v. Appellate Department (1996) 44 Cal.App.4th 1672, 1682 [52 Cal.Rptr.2d 599].)

Carr and West contend that section 10 of the street-improvement contract, found under the section title “Insurance Requirements for Contractors,” and the provision heading, “Hold Harmless and Indemnification Agreement,” authorizes an attorney fees award because its language includes within its scope actions arising out of the performance of the work provided for in the contract. The provision reads: “[Carr] shall indemnify and hold harmless [Chowchilla] . . . and its officers, officials, employees, agents of the above from and against all claims, damages, losses and expenses including attorney fees arising out of the performance of the work described herein, caused in whole or in part by any negligent act or omission of [Carr], any subcontractor, anyone directly or indirectly employed by any of them or anyone for whose acts any of them may be liable, except where caused by the active negligence, sole negligence, or willful misconduct of [Chowchilla].” (Italics added.) 5

In contrast to the “Hold Harmless and Indemnification Agreement” section, the street-improvement contract contains section 9, a provision under the section title of “Indemnity Agreement,” which reads: “[Carr] agrees to indemnify and save harmless [Chowchilla], Giersch & Olson, Inc., their *20 agents and emjployees, for and against all loss' or expense (including costs and attorney fees) on account of injury or death of persons employed by [Carr], or .

Free access — add to your briefcase to read the full text and ask questions with AI

Carr Business Enterprises, Inc. v. City of Chowchilla, 166 Cal. App. 4th 14, 82 Cal. Rptr. 3d 128, 2008 Cal. App. LEXIS 1333 (Cal. Ct. App. 2008).

166 Cal. App. 4th 14 (Carr Business Enterprises, Inc. v. City of Chowchilla) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Ams-Osram USA Inc. v. Renesas Electronics America, Inc.
133 F.4th 1337 (Federal Circuit, 2025)
Agk Sierra De Montserrat, L.P. v. Comerica Bank
109 F.4th 1132 (Ninth Circuit, 2024)
Alivecor, Inc. v. Apple, Inc.
N.D. California, 2022
Gonzalez v. Mathis
California Court of Appeal, 2018
Taburaza v. Zarate (In re Zarate)
567 B.R. 176 (N.D. California, 2017)
Alki Partners, LP v. DB Fund Services, LLC
4 Cal. App. 5th 574 (California Court of Appeal, 2016)
Judicial Council of Cal. v. Jacobs Facilities
California Court of Appeal, 2015
Spanish Inn v. Goodell CA4/1
California Court of Appeal, 2015
Rideau v. Stewart Title of California
California Court of Appeal, 2015
Rideau v. Stewart Title of California CA4/1
235 Cal. App. 4th 1286 (California Court of Appeal, 2015)
Mechanics Bank v. Methven CA1/5
California Court of Appeal, 2014
Voyager Assocs. v. Superior Court CA4/1
California Court of Appeal, 2014