The Palace at Washington Square v. Mechanics Bank CA1/3

CourtCalifornia Court of Appeal
DecidedMarch 17, 2023
DocketA164195
StatusUnpublished

This text of The Palace at Washington Square v. Mechanics Bank CA1/3 (The Palace at Washington Square v. Mechanics Bank CA1/3) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The Palace at Washington Square v. Mechanics Bank CA1/3, (Cal. Ct. App. 2023).

Opinion

Filed 3/17/23 The Palace at Washington Square v. Mechanics Bank CA1/3

NOT TO BE PUBLISHED IN OFFICIAL REPORTS California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication or ordered published for purposes of rule 8.1115.

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA

FIRST APPELLATE DISTRICT

DIVISION THREE

THE PALACE AT WASHINGTON SQUARE, LLC, Plaintiff and Appellant, A164195, A164799

v. (City & County of San Francisco MECHANICS BANK, Super. Ct. No. CGC-19-578060) Defendant and Respondent.

The Palace at Washington Square (Palace), plaintiff in this action, entered into a loan agreement with defendant Mechanics Bank (Bank) to fund construction of a residential and commercial building. As the maturity date of the construction promissory note approached and passed, the parties engaged unsuccessfully in negotiations to extend it. Bank eventually demanded payment of the loan balance as well as attorney fees incurred in efforts to enforce its rights, and subsequently filed an action for appointment of a receiver. Palace paid the amount Bank demanded, which included attorney fees already incurred and a reserve for future legal expenses. In this action, Palace alleges that Bank did not negotiate in good faith in violation of the implied covenant of good faith and fair dealing and that its actions amounted to economic duress. After trial, a referee ruled against

1 Palace on the causes of action before him, and awarded Bank contractual attorney fees. Palace appeals the judgment and fee award. We affirm. FACTUAL AND PROCEDURAL BACKGROUND I. The Construction Loan Documents Palace and Bank entered into a construction loan agreement on February 22, 2016, under which Bank agreed to lend an amount not to exceed $18,500,000 to finance construction of a five-story condominium project in San Francisco. The loan agreement required Palace to complete construction no later than December 1, 2017. The loan proceeds were to be advanced to Palace in disbursements, with all principal, interest, and other amounts “due and payable in full” on the loan’s maturity date, defined as two years from the date of the agreement unless an event of default occurred. Disbursements were to be paid only if there was no default, defined in Paragraph 19.1 of the loan agreement to include Palace’s failure “to make any principal, interest, or other payment when due and payable,” Palace’s failure to perform non-monetary covenants or conditions if certain notice requirements were met, or a construction delay rendering it unlikely the project would be completed by the completion date. Palace was prohibited from “suffer[ing] or permit[ing] any mechanics’ lien to be filed or otherwise asserted,” and was required to pay all amounts due to anyone that might result in a mechanic’s lien if unpaid. The loan agreement provided that no modification would be valid if not in writing and signed by the party against whom modification was sought, and it contained an “Entire Agreement” clause. Palace also executed a construction promissory note, with a loan maturity date of February 22, 2018. The promissory note provided that Palace would pay the costs of collecting or attempting to collect sums due

2 under the note and loan document, including reasonable attorney fees in the event of a default. It also provided for a higher rate of interest (the default rate) to be charged if Palace did not make any payments on time. Also among the loan documents was a deed of trust, which contained attorney fee and indemnity clauses that we discuss in further detail below. II. Project Delays and Request for Extension The project was not finished by the scheduled completion date of December 1, 2017, and Bank extended the completion date to February 1, 2018 to allow Palace to continue to receive disbursements and finish the project, without defaulting on the loan. On December 11, 2017, Marc Thompson, a senior vice president of Bank, wrote a letter to Palace’s owner, Joel Campos, telling him that the construction loan would mature on February 22, 2018, and that Bank would need updated financial information in order to begin the credit process to extend the loan. Campos provided the requested documents, and Thompson told Campos he was working on the extension. Campos received advice to seek replacement financing from other lenders, and there was evidence it would have been “very easy” for him to do so. Campos declined to do so, saying that he intended to continue to work with Bank. It appears that subcontractors for the construction project were not being paid by February 2018, and the contractor, West Builders, Inc. (West Builders) informed Palace that it and the subcontractors would file liens on the project as of February 18. Thompson did not have authority to approve a loan extension; rather, Bank’s chief credit officer, Scott Givens, had final approval authority. Because of the uncertainty caused by the conflict between Campos and the

3 contractor, the six-month extension request was not submitted to Givens. Bank did not affirm an extension of the loan in writing before it matured on February 22, 2018. III. Further Negotiations and Mechanic’s Liens At a meeting with Thompson and other Bank representatives on March 1, 2018, Campos asked for the loan to be extended for six months, and for an increase in the loan amount. Bank told Campos it needed additional information about the cost to complete the project, the status of the tasks that remained, and additional items. Palace provided additional information, but Bank concluded the information was still incomplete. Bank sent Palace and Campos a notice of default on March 1, 2018, stating that the construction note had matured and the outstanding balance was due, and that as a result “events of default” had occurred. The notice continued that, although Bank as willing to engage in discussions with Palace about “forbearance or other accommodation,” Bank could terminate those discussions for any reason, except as provided in written agreements, and that Bank was not waiving its rights with respect to the maturity default or any other default. The notice of default did not list the outstanding balance on the loan. West Builders sent Bank a stop-payment notice1 on February 28, 2018, and filed a mechanic’s lien on March 1, 2018 asserting it was owed more than $3,000,000 for work it had performed. Over the next three months, multiple subcontractors also filed liens. Palace’s attorney wrote to the contractor on

1 This was a legal notice to withhold construction funds equal to the value of labor and materials furnished but not paid for, pursuant to Civil Code sections 8520, 8530, and 9350.

4 March 8, 2018, telling it the loan could not be extended unless the lien was released. Thompson sent an email to Palace on March 14, 2018, extending to March 20 the time for Palace to reach a settlement agreement with West Builders to clear the mechanic’s liens and stop-payment notice, one of a number of conditions required before Bank could consider extending the loan maturity date. Palace’s attorney, Jonathan Rodriguez, sent an email to Bank’s counsel on March 23, 2018, telling him Palace and West Builders had agreed to terms to “close out payments” and attaching a draft agreement for review and comment. The draft agreement included a number of blanks to be filled in, and it was not signed. Bank replied that its counsel would review the draft agreement and that Bank would then discuss an extension of the loan. It appears that Bank did not provide any further response regarding the draft agreement. Despite the draft settlement agreement, it appears the disputes between Palace and West Builders continued.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shadoan v. World Savings & Loan Assn.
219 Cal. App. 3d 97 (California Court of Appeal, 1990)
Rich & Whillock, Inc. v. Ashton Development, Inc.
157 Cal. App. 3d 1154 (California Court of Appeal, 1984)
Careau & Co. v. Security Pacific Business Credit, Inc.
222 Cal. App. 3d 1371 (California Court of Appeal, 1990)
Price v. Wells Fargo Bank
213 Cal. App. 3d 465 (California Court of Appeal, 1989)
Beverly Hills National Bank v. Glynn
267 Cal. App. 2d 859 (California Court of Appeal, 1968)
Carr Business Enterprises, Inc. v. City of Chowchilla
166 Cal. App. 4th 14 (California Court of Appeal, 2008)
Baldwin Builders v. Coast Plastering Corp.
24 Cal. Rptr. 3d 9 (California Court of Appeal, 2005)
Crosstalk Productions, Inc. v. Jacobson
76 Cal. Rptr. 2d 615 (California Court of Appeal, 1998)
Haight Ashbury Free Clinics, Inc. v. Happening House Ventures
184 Cal. App. 4th 1539 (California Court of Appeal, 2010)
Storek & Storek, Inc. v. Citicorp Real Estate, Inc.
122 Cal. Rptr. 2d 267 (California Court of Appeal, 2002)
Bell v. Vista Unified School District
98 Cal. Rptr. 2d 263 (California Court of Appeal, 2000)
Children's Hospital & Medical Center v. Bonta
118 Cal. Rptr. 2d 629 (California Court of Appeal, 2002)
Racine & Laramie, Ltd. v. Department of Parks & Recreation
11 Cal. App. 4th 1026 (California Court of Appeal, 1992)
Continental Heller v. AMTECH MECHANICAL SERV.
53 Cal. App. 4th 500 (California Court of Appeal, 1997)
Myers Building Industries, Ltd. v. Interface Technology, Inc.
13 Cal. App. 4th 949 (California Court of Appeal, 1993)
Banning v. Newdow
14 Cal. Rptr. 3d 447 (California Court of Appeal, 2004)
Howard v. Owens Corning
85 Cal. Rptr. 2d 386 (California Court of Appeal, 1999)
Guz v. Bechtel National, Inc.
8 P.3d 1089 (California Supreme Court, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
The Palace at Washington Square v. Mechanics Bank CA1/3, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-palace-at-washington-square-v-mechanics-bank-ca13-calctapp-2023.