Capitol Paving of D.C., Inc. v. H&L Construction Corporation

District Court, District of Columbia·Decided April 17, 2025·No. Civil Action No. 2024-2148·Published

Opinion

UNITED STATES DISTRICT COURT FOR THE DISTRICT OF COLUMBIA

CAPITOL PAVING OF D.C., INC., Plaintiff,

v. Case No. 1:24-cv-02148 (ACR)

H&L CONSTRUCTION CORPORATION, Defendant.

MEMORANDUM OPINION

Plaintiff Capitol Paving of D.C., Inc., is a D.C. corporation in the business of asphalt paving, restoration, and repair and installation of water and sewer lines. See Dkt. 1 (Compl.) ¶ 4. On July 23, 2024, Plaintiff sued H&L Construction Corporation, a Florida corporation, alleging a violation of the District of Columbia Prompt Pay Act, breach of contract, quantum meruit, and unjust enrichment. Id. at 1. Defendant failed to answer or appear in this case, so Plaintiff filed a motion for a default judgment on October 28, 2024. See Dkt. 12. After considering the relevant evidence submitted by Plaintiff, the Court GRANTS the motion in part and DENIES it as moot without prejudice in part, awarding compensatory damages, attorney’s fees, and costs. 1 I. BACKGROUND

Plaintiff brought this civil action based on a contract it made with Defendant, dated October 11, 2021, to remove and reinstall water and sewer lines at the Embassy of Hungary. See

1 The Court, in granting judgment on Plaintiff’s claims for violation of the D.C. Prompt Pay Act and breach of contract, need not address Plaintiff’s claims for quantum meruit and unjust enrichment, which are pled in the alternative that an express contract was not made between the parties. Because the Court finds that an express contract did exist, it denies Plaintiff’s alternative arguments as moot, without prejudice.

Compl., Ex. 1 (the Contract), and two change orders, dated December 6, 2021, and March 29, 2022, see Compl., Ex. 2 (the Change Orders) (together, the Project). Plaintiff began its work on on or about November 8, 2021, as a subcontractor for the Project under the request and direction of Defendant and with approval from the Hungarian Embassy. See Compl. ¶¶ 57, 13. Plaintiff provided all labor and materials necessary to complete the Project. See id. ¶ 5. It completed the project on or about June 30, 2022. See id. ¶ 6. The Embassy of Hungary then paid Defendant for Plaintiff’s work. See id. ¶ 67. After numerous discussions between Plaintiff and Defendant, Defendant made two payments to Plaintiff: $40,000.00 on May 19, 2023, and an additional $40,000.00 on May 31, 2023. See id. ¶ 9. However, Defendant still owes Plaintiff $340,000.00 for Plaintiff’s work on the Project pursuant to their contractual agreements. See id.; see also Compl., Ex. 3 (Statement of Account).

On July 23, 2024, Plaintiff filed its Complaint in this case. Compl. at 7. On August 6, 2024, Plaintiff successfully served Defendant in accordance with the Federal Rules of Civil Procedure. Dkt. 7. After Defendant failed to appear or otherwise respond to the Complaint, Plaintiff filed an affidavit for default on October 10, 2024, Dkt. 10, and the Clerk of the Court entered default on October 10, 2024, Dkt. 11. Plaintiff then filed a motion for default judgment on October 28, 2024. Dkt. 12.

Plaintiff requests that the Court award it with “[d]amages in an amount of not less than $340,000.00, plus interest as allowed by law and/or the Contract[,]” as well as “[a]ttorneys’ fees and legal costs in an amount to be determined following entry of a final judgment” and “[a]ny other further relief this Court deems just and necessary.” See Compl. at 7. Plaintiff submitted an affidavit in support of the compensatory damages it requests, which it calculated to be

$482,800.00. See Dkt. 12-1 at 1. Plaintiff also submitted an affidavit in support of attorney’s fees and costs in the amounts of $11,150.00 and $537.04, respectively. See Dkt. 12-2 at 1.

II. STANDARD OF REVIEW The Federal Rules of Civil Procedure provide for the entry of a default judgment “[w]hen a party against whom a judgment for affirmative relief is sought has failed to plead or otherwise defend” against an action. Fed. R. Civ. P. 55(a); see also Jackson v. Beech, 636 F.2d 831, 836 (D.C. Cir. 1980) (cleaned up). Rule 55 sets forth a two-step process for a party seeking a default judgment: first, entry of a default by the clerk of the court, followed by entry of a default judgment by either the clerk or the Court. Fed. R. Civ. P. 55.

III. FINDINGS OF FACT

Plaintiff Capitol Paving of D.C., Inc., is a District of Columbia corporation with its “principal office” located in Washington, D.C. See Compl. ¶ 1. Defendant H&L Construction Corporation is a Florida corporation registered to do business in the District of Columbia with a “principal office” in Jacksonville, Florida. Id. ¶ 2. “On or around October 2021, [Defendant] retained [Plaintiff] to, inter alia, remove and reinstall water and sewer lines at the Embassy of Hungary.” Id. ¶ 4; see also the Contract. “[Plaintiff] also performed work for [Defendant] pursuant to two (2) Change Orders[.]” Id.; see also the Change Orders. “[Plaintiff] began its work on the Project on or about November 8, 2021[,]” “provided and/or arranged for all labor and materials necessary to complete the Project[,]” id. ¶ 5, and “performed all work in furtherance of the Project in a professional and workmanlike manner, and pursuant to the terms and conditions of the Contract[.]” Id. ¶ 7. “[T]he services rendered by [Plaintiff] were approved and accepted by [Defendant], as well as the Hungarian Embassy.” Id. The Project achieved

“Substantial Completion” in June 2022 with “final punch list work completed in July of 2022.” Id. ¶ 6. “[Defendant] was paid for the work of [Plaintiff] by the Hungarian Embassy.” Id.

While “[Defendant] made several payments to [Plaintiff] during the term of the Project[,]” id. ¶ 8, including “payments to [Plaintiff] on May 19, 2023 in the amount of $40,000.00 and May 31, 2023 for another $40,000.00[,]” id. ¶ 9; see also id. Ex. 3, the “total value of the services, labor, and materials supplied by [Plaintiff] for which it has not been compensated is $340,000.00.” Id. ¶ 11. “[Defendant], through its Principal and Owner, Lajos Horvath, has acknowledged the outstanding debt owed to [Plaintiff], and has agreed to pay the outstanding amount owed to [Plaintiff]. Notwithstanding that fact, [Defendant] has failed and refused to pay [Plaintiff] for the services, labor, and materials supplied by [Plaintiff] in furtherance of the Project.” Id. ¶ 10.

In support of its motion for a default judgment, Plaintiff has submitted evidence including records of the executed Contractor Agreement between Plaintiff and Defendant and records of the two Change Orders. See Compl., Exs. 1, 2. Plaintiff also attached a Customer Ledger for the Project that shows that Defendant owes Plaintiff an outstanding balance of $340,000.00. See id. at Ex. 3. Plaintiff further submitted an affidavit from Randy B. Panizo, Vice President of Capitol Paving of D.C., Inc., to substantiate the amount that Defendant owes Plaintiff as shown in the Statement of Account. See Dkt. 12-1.

IV. CONCLUSIONS OF LAW Plaintiff requests that this Court enter “an Order in its favor and against Defendant”

arising out of Defendant’s alleged violation of the Prompt Pay Act, D.C. Code § 27A-104, breach of contract, quantum meruit, and unjust enrichment. See Compl. ¶ 36.

Before entering a default judgment, a court must comply with its “affirmative obligation to determine whether it has subject-matter jurisdiction over the action[,]” Friends Christian High Sch. v. Geneva Fin. Consultants, 321 F.R.D. 20, 22 (D.D.C. 2017) (internal quotation marks omitted), as well as personal jurisdiction over the Defendant, see Mwani v. bin Laden, 417 F.3d 1, 6 (D.C. Cir. 2005). After establishing jurisdiction over the action, the court must determine whether a plaintiff has sufficiently alleged facts establishing the defendant’s liability. See Boland v. Elite Terrazzo Flooring, Inc., 763 F. Supp. 2d 64, 67 (D.D.C. 2011) (noting that entry of a default “establishes the defaulting party’s liability for the well-pleaded allegations of the complaint”) (emphasis added).

Free access — add to your briefcase to read the full text and ask questions with AI

Capitol Paving of D.C., Inc. v. H&L Construction Corporation, (D.D.C. 2025).

Capitol Paving of D.C., Inc. v. H&L Construction Corporation (Capitol Paving of D.C., Inc. v. H&L Construction Corporation) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Mwani, Odilla Mutaka v. Bin Ladin, Usama
417 F.3d 1 (D.C. Circuit, 2005)
Nevius v. Africa Inland Mission International
511 F. Supp. 2d 114 (District of Columbia, 2007)
Tsintolas Realty Co. v. Mendez
984 A.2d 181 (District of Columbia Court of Appeals, 2009)
Dale Denton Real Estate, Inc. v. Fitzgerald
635 A.2d 925 (District of Columbia Court of Appeals, 1993)
Environmental Research International, Inc. v. Lockwood Greene Engineers, Inc.
355 A.2d 808 (District of Columbia Court of Appeals, 1976)
McWILLIAMS BALLARD v. BROADWAY MANAGEMENT COMPANY, INC.
636 F. Supp. 2d 1 (District of Columbia, 2009)
Schiff v. American Ass'n of Retired Persons
697 A.2d 1193 (District of Columbia Court of Appeals, 1997)
Boland v. ELITE TERRAZZO FLOORING, INC.
763 F. Supp. 2d 64 (District of Columbia, 2011)
Plesha v. Ferguson
725 F. Supp. 2d 106 (District of Columbia, 2010)
Boland v. Providence Construction Corp.
304 F.R.D. 31 (District of Columbia, 2014)
McLaughlin v. Hartford Life & Annuity Ins. Co.
299 F. Supp. 3d 115 (D.C. Circuit, 2017)
Candido v. District of Columbia
242 F.R.D. 151 (District of Columbia, 2007)