United States of America Ex Rel. Modern Electric, Inc., Appellant/cross-Appellee v. Ideal Electronic Security Co., Inc., Appellee/cross-Appellant

81 F.3d 240, 40 Cont. Cas. Fed. 76,918, 317 U.S. App. D.C. 145, 34 Fed. R. Serv. 3d 118, 1996 U.S. App. LEXIS 8474
CourtCourt of Appeals for the D.C. Circuit
DecidedApril 19, 1996
Docket95-7119, 95-7121
StatusPublished
Cited by42 cases

This text of 81 F.3d 240 (United States of America Ex Rel. Modern Electric, Inc., Appellant/cross-Appellee v. Ideal Electronic Security Co., Inc., Appellee/cross-Appellant) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States of America Ex Rel. Modern Electric, Inc., Appellant/cross-Appellee v. Ideal Electronic Security Co., Inc., Appellee/cross-Appellant, 81 F.3d 240, 40 Cont. Cas. Fed. 76,918, 317 U.S. App. D.C. 145, 34 Fed. R. Serv. 3d 118, 1996 U.S. App. LEXIS 8474 (D.C. Cir. 1996).

Opinion

Opinion for the Court filed by Circuit Judge TATEL.

TATEL, Circuit Judge:

In this dispute between a government contractor and its subcontractor, we review the district court’s determination that fifty-two purchase orders and three oral requests for services were not contracts. Because the district court apparently assumed, contrary to District of Columbia law, that purchase orders cannot be contracts, we reverse and remand for reconsideration. We also set aside the district court’s award to the subcontractor on an unjust enrichment claim added to the subcontractor’s complaint after trial.

I.

Pursuant to Section 8(a) of the Small Business Act, 15 U.S.C. § 687(a) (1994), Ideal Electronic Security Co., Inc. — the defendant, appellee, and cross-appellant — obtained a three-year contract to replace PCB-laced electrical transformers at the Walter Reed Medical Centers in Washington, D.C. and Forest Glen, Maryland. In preparing its bid for the Walter Reed contract, Ideal cooperated with Modern Electric, Inc. — the plaintiff, appellant, and cross-appellee — which had expertise working with PCB-laced transformers. With the understanding that Modem would perform much of the work under the contract if Ideal won the bid, Ideal based its bid on Modem’s price estimates for contract line items.

After Ideal won the contract in July 1991, Modern performed several tasks under the contract, apparently expecting that the two companies would enter into a written subcontract. They finally signed a 'written subcontract on November 26, 1991. The subcontract included a termination date of April 2, 1992 — only four months later — even though both parties expected that the Walter Reed project would take much longer to finish. The written subcontract required Ideal to “use standard purchase order forms for all orders” and provided that Ideal would pay Modern for each invoiced amount after Ideal received payment from the Government. The subcontract also provided that Ideal would supply 25% of the labor for the entire project and that during any given period Ideal would provide at least 20% of the labor. Accordingly, the subcontract required Modem to deduct from all its invoices wages incurred by Ideal personnel, with the wages determined by the wage rates set in the prime contract between the Government and Ideal. Modern was also to deduct from the invoices a 20.7% labor tax on these wages.

The typical course of dealings between Ideal and Modem pursuant to the subcontract was as follows. Ideal sent Modern purchase orders identifying specific tasks that needed to be done pursuant to delivery orders that the Government sent to Ideal under the prime contract. Ideal’s purchase orders, usually signed by an Ideal representative, included quantity and price terms. Ideal based its prices on the line item prices in the prime contract. After receiving a purchase order, Modem performed the work, sending Ideal an invoice or a series of invoices; the charges on Modern’s invoices typically corresponded to the prices Ideal had listed in its purchase orders. Pursuant to the terms of the subcontract, Ideal was entitled to a labor credit representing wages for its personnel working on each project. Ideal was thus usually not liable for the full amounts listed in Modem’s invoices, and Modern apparently granted Ideal labor credits as a matter of course.

Although the terms of the written subcontract expired on April 2, 1992, Modern continued performing work pursuant to purchase orders for approximately another year. Their course of dealings, at least for a while, followed the same pattern as under the written subcontract. At a certain point, however, disagreements arose about the timing of Ideal’s payments. Modern charged that the *243 payments were late, but Ideal took the position that it did not have to pay Modern until the Government paid Ideal, as the expired subcontract had provided. In January 1993, Ideal agreed to make payment on invoices within forty-five days. In exchange, Modern made concessions regarding wage rates and labor credits. The January agreement also required Ideal to notify Modern of any dispute as to the amount charged in an invoice within three days of receiving that invoice.

According to Modern, Ideal continued to malee late payments. On March 26, 1993, Modern charged that Ideal was in breach of the January agreement regarding the timing of payments. In April, after discussions with Ideal, Modem agreed that Ideal could have five days upon receipt of each invoice to give notice of disputed charges. From April to June of 1993, the companies exchanged angry letters and faxes concerning late payments and damage that Ideal alleged Modern had caused to sidewalks at the Walter Reed Medical Center. In September 1993, Modem declared that it would perform no more work for Ideal.

Modern filed suit for breach of contract in the United States District Court for the District of Maryland. The suit was transferred to the United States District Court for the District of Columbia. The complaint alleged that after the expiration of the written subcontract, Modem and Ideal had an oral contract requiring payment on invoices within forty-five days. At trial, Modern modified its theory, arguing that each purchase order was itself a contract and also that the companies had entered into three oral agreements for Modern to perform certain services without purchase orders. Modern claimed damages totaling $227,722.27. Modern also amended its complaint to add a quantum meruit claim.

In response to Modern’s claims, Ideal argued that the parties had intended that the written subcontract, providing that Ideal would pay Modem when the Government paid Ideal, would remain in effect for the full period of the prime contract, despite the subcontract’s stated termination date of April 2, 1992. Ideal further argued that, were Modern to prevail on any of its claims, Ideal would be entitled to numerous setoffs against those claims. According to Ideal, these set-offs, totaling $272,603.15, were to compensate for labor credits; for remediation; for overcharges; for work not performed; for work not authorized by purchase order; for invoices paid in full; and for work by Modern that the Government refused to accept.

Ruling from the bench following trial without a jury, the district court concluded that the written subcontract expired as its terms provided on April 2, 1992 and that the individual purchase orders issued by Ideal and Ideal’s oral requests for work were not contracts and thus created no contractual liability. See Trial Tr. at 647-49, United States ex rel. Modern Elec., Inc. v. Ideal Elec. Sec. Co. (D.D.C. Mar. 9, 1995) (No. 94-385). The district court also ruled that, because there was no contract between the companies, their January 1993 letter agreement about payment terms, wage rates, and labor credits was neither a new contract nor a modification of an existing contract. See id. at 649-50. The district court next rejected Modem’s quantum meruit claim. Acknowledging that Modern had shown that it had rendered valuable services for and bestowed a substantial benefit on Ideal, that Ideal had accepted the services, and that Modern had expected payment, see id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Remus v. Wcp Fund I LLC.
District of Columbia, 2025
Ratchford v. Cafe Dupont, LLC
District of Columbia, 2025
Sampedro v. Anyado Group, LLC
District of Columbia, 2023
Khalil v. El Rafaei
E.D. Virginia, 2022
Alemayehu v. Abere
199 F. Supp. 3d 74 (District of Columbia, 2016)
Intelect Corporation v. Cellco Partnership Gp
160 F. Supp. 3d 157 (District of Columbia, 2016)
D.W. v. J.W.B.
230 So. 3d 763 (Court of Civil Appeals of Alabama, 2015)
Diamond v. Jones Day LLP (In re Howrey LLP)
515 B.R. 624 (N.D. California, 2014)
Eastern Savings Bank, Fsb v. Papageorge
31 F. Supp. 3d 1 (District of Columbia, 2014)
Boyd v. Farrin
958 F. Supp. 2d 232 (District of Columbia, 2013)
CVS/Caremark Corp. v. Washington
121 So. 3d 391 (Court of Civil Appeals of Alabama, 2013)
Univ. Am-Can v. CSI-Concrete Sys.
2012 DNH 047 (D. New Hampshire, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
81 F.3d 240, 40 Cont. Cas. Fed. 76,918, 317 U.S. App. D.C. 145, 34 Fed. R. Serv. 3d 118, 1996 U.S. App. LEXIS 8474, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-of-america-ex-rel-modern-electric-inc-cadc-1996.