Capitol Indemnity Corporation v. United States

United States Court of Federal Claims·Decided October 4, 2022·No. 18-916·Published

Opinion

In the United States Court of Federal Claims No. 18-916 C (Filed: October 04, 2022)

* * * * * * * * * * * * * * * * ** * * CAPITOL INDEMNITY CORP., * * Plaintiff, * * v. * * THE UNITED STATES, * * Defendant. * * * * * * * * * * * * * * * * * * ** *

Ian M. McLin, Langley & Banack, Inc., of San Antonio, TX, for Plaintiff.

Matthew J. Carhart, Trial Attorney, Commercial Litigation Branch, Civil Division, U.S. Department of Justice, with whom were Deborah A. Bynum, Assistant Director, Martin F. Hockey, Jr., Acting Director, and Brian M. Boynton, Acting Assistant Attorney General, all of Washington, D.C., for Defendant, and Major Tarik Downie, General Litigation Branch, U.S. Army Legal Services Agency, Department of the Army, of Fort Belvoir, VA, of counsel.

OPINION AND ORDER

SOMERS, Judge.

This case concerns Plaintiff Capitol Indemnity Corporation’s (“Capitol”) claims for damages it allegedly incurred as surety for a contractor, Redstick, Inc. (“Redstick”), that was hired by the U.S. Army (“Army”) to renovate a fitness facility at Fort Hood in Texas. Following Redstick’s termination for default by the Army, Plaintiff completed the remaining work on the contract, paid Redstick’s subcontractors, and subsequently filed claims against the Army for payment—including for allegedly improper progress payments the Army issued to Redstick; for certain allegedly unpaid additional work undertaken by Redstick; and for subsequent costs Plaintiff incurred for having to correct Redstick’s work on the gym floor—all of which the Army denied. Plaintiff thereafter filed suit in this Court seeking damages under the theories of equitable subrogation and equitable adjustment, and under the Contract Disputes Act (“CDA”).

In February 2020, the previously assigned judge in this matter granted in part and denied in part the government’s motion to dismiss. See Capitol Indem. Corp. v. United States, 147 Fed. Cl. 371 (2020). This opinion concerns Plaintiff’s claims that survived dismissal, which are now before the Court on cross-motions for summary judgment. For the reasons that follow, the Court denies Plaintiff’s motion for partial summary judgment and grants the government’s motion for summary judgment on all counts.

BACKGROUND AND PROCEDURAL HISTORY

A. Contract Award, Bond Agreements, and Progress Payments to Redstick

On September 27, 2014, the Army awarded a contract (W91151-14-C-0061) to Redstick for the renovation of the Iron Horse Gym at Fort Hood, which, after amendments, had a total contract price of over $2.3 million. ECF No. 63 ¶ 11 (“Pl.’s Partial Summ. J. Mot.”); ECF No. 68 at 2 (“Gov.’s Cross-Mot. Summ. J.”). The contract period-of-performance (“POP”) had an end-date of September 30, 2015. Pl.’s Partial Summ. J. Mot. ¶ 12; Gov.’s Cross-Mot. Summ. J. at 2. The purpose of the contract was

to repair building 37017, Iron Horse Gym, and renovate it to better meet the needs of the users as a “functional fitness” facility. This includes, but is not limited to, repairing any damage left by the current occupants, replacing/repairing finishes throughout the facility, fully replacing existing ceilings, insulating the entire envelope, furring out walls, reconfiguring of latrines to accommodate ABA guidelines, various other aesthetic alterations, full replacement of windows throughout the facility, complete replacement of HVAC systems, and electrical work to support the new layout. Also included are various repairs and reconfigurations of the site to include sidewalks and parking lot.

Gov.’s Cross-Mot. Summ. J. at 2 (citing ECF 68-2 at 8 (government’s “A86”)).

The contract, bonded pursuant to the Miller Act, 40 U.S.C. § 3131, required Redstick to provide performance and payment bonds. Pl.’s Partial Summ. J. Mot. ¶ 13; Gov.’s Cross-Mot. Summ. J. at 2–3. Accordingly, Redstick sought—and on October 2, 2014, Plaintiff issued— performance and payment bonds, requiring Plaintiff as the surety “to either perform any contract work that Redstick does not complete, or pay for that uncompleted work . . . and a payment bond, requiring it to pay subcontractors for labor and materials if Redstick fails to do so.” Gov.’s Cross-Mot. Summ. J. at 2–3 (record citations omitted); see also Pl.’s Partial Summ. J. Mot. ¶ 13. Plaintiff “executed and issued the Bonds based upon the terms and conditions set forth in the Contract and the General Indemnity Agreement.” Id. ¶ 13. The “General Indemnity Agreement,” an agreement between Redstick and Plaintiff executed approximately two weeks before Plaintiff was awarded the contract, purported to “assign[] to Capitol all rights in Redstick’s property, including all contracts,” id. ¶ 9, in the event of Redstick’s default on a contract for which Plaintiff had issued a bond, ECF No. 23 ¶ 6 (“Amend. Compl.”). See also Pl.’s Partial Summ. J. Mot. ¶ 10.

The contract awarded to Redstick incorporated by reference several provisions within the Federal Acquisition Regulation (“FAR”), two of which in particular concern the contracting officer’s authority to make progress payments throughout the term of the contract to the contractor. See generally id. ¶¶ 14–20; Gov.’s Cross-Mot. Summ. J. at 7–8. First, the contract incorporated by reference FAR 52.232-5, see ECF No. 68-2 at 12 (government’s “A90”),

2 concerning “Payments under Fixed-Price Construction Contracts,” which provides in relevant part that “[t]he Government shall make progress payments monthly as the work proceeds, or at more frequent intervals as determined by the Contracting Officer, on estimates of work accomplished which meets the standards of quality established under the contract, as approved by the Contracting Officer.” FAR 52.232-5(b). Furthermore, the section provides that “if satisfactory progress has not been made, the Contracting Officer may retain a maximum of 10 percent of the amount of the payment until satisfactory progress is achieved.” FAR 52.232-5(e). Second, the contract incorporated FAR 52.232-16, see ECF No. 68-2 at 25–26 (government’s “A103–A104”), concerning “Progress Payments,” which provides in relevant part that “[t]he total amount of progress payments shall not exceed 80 percent of the total contract price.” FAR 52.232-16(a)(6). The contract also contained a provision titled “Eligibility for Payment/Construction Contract Progress Payment Requests,” which provides that “[n]o progress payments are authorized above 80% of the contract value.” ECF No. 23-2 at 48–49 (Plaintiff’s “Exhibit ‘B’”).

It is undisputed that, over the course of the project, Redstick experienced difficulties with contract performance. See, e.g., Gov.’s Cross-Mot. Summ. J. at 3; Pl.’s Partial Summ. J. Mot. ¶ 21. Redstick did not complete performance by the POP end-date of September 30, 2015. Pl.’s Partial Summ. J. Mot. ¶ 26. Nor, allegedly, did Redstick fulfill obligations to pay its subcontractors. Id. ¶ 25; Gov.’s Cross-Mot. Summ. J. at 4. Nonetheless, the government continued making progress payments to Redstick through January 29, 2016, when it issued the ninth and final progress payment that Redstick would receive. Gov.’s Cross-Mot. Summ. J. at 10; Pl.’s Partial Summ. J. Mot. ¶ 78. Ultimately, on March 28, 2016, the government declared Redstick to be in default and terminated the original contract after Redstick abandoned performance. Pl.’s Partial Summ. J. Mot. ¶ 55; Gov.’s Cross-Mot. Summ. J. at 14.

The briefing, as well as an opinion in this matter issued by Judge Firestone on the government’s motion to dismiss, contain a multitude of factual allegations and competing narratives—dating back to September 2015—regarding who-knew-what (and when) about Redstick’s difficulties. See, e.g., Capitol Indem. Corp., 147 Fed. Cl. at 375–76; Pl.’s Partial Summ. J. Mot.

Free access — add to your briefcase to read the full text and ask questions with AI

Capitol Indemnity Corporation v. United States, (uscfc 2022).

Capitol Indemnity Corporation v. United States (Capitol Indemnity Corporation v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

First Nat. Bank of Ariz. v. Cities Service Co.
391 U.S. 253 (Supreme Court, 1968)
Adickes v. S. H. Kress & Co.
398 U.S. 144 (Supreme Court, 1970)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Marriott International Resorts, L.P. v. United States
586 F.3d 962 (Federal Circuit, 2009)
Delmarva Power & Light Co. v. United States
542 F.3d 889 (Federal Circuit, 2008)
National American Insurance v. United States
498 F.3d 1301 (Federal Circuit, 2007)
Lumbermens Mutual Casualty Co. v. United States
654 F.3d 1305 (Federal Circuit, 2011)
Balboa Insurance Company v. The United States
775 F.2d 1158 (Federal Circuit, 1985)
Mingus Constructors, Inc. v. The United States
812 F.2d 1387 (Federal Circuit, 1987)
Fireman's Fund Insurance Company v. The United States
909 F.2d 495 (Federal Circuit, 1990)
Transamerica Insurance Company v. The United States
989 F.2d 1188 (Federal Circuit, 1993)
Anchor Savings Bank, FSB v. United States
121 Fed. Cl. 296 (Federal Claims, 2015)