Capital Safety, Inc. v. State

848 A.2d 863, 369 N.J. Super. 295, 2004 N.J. Super. LEXIS 181
CourtNew Jersey Superior Court Appellate Division
DecidedMay 24, 2004
StatusPublished
Cited by6 cases

This text of 848 A.2d 863 (Capital Safety, Inc. v. State) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Capital Safety, Inc. v. State, 848 A.2d 863, 369 N.J. Super. 295, 2004 N.J. Super. LEXIS 181 (N.J. Ct. App. 2004).

Opinion

The opinion of the court was delivered by

SKILLMAN, P.J.A.D.

This appeal requires us to construe a “termination for convenience” provision in a State contract.

After competitive bidding, the Division of Building and Construction (DBC)1 entered into a contract with plaintiff in May [297]*2971996 for removal of asbestos on the first through fourth floors of the Labor Building in Trenton. The amount of the contract was $1.6 million, and the project was required to be completed in 460 days.

Due to safety concerns, the Department of Labor was required to evacuate all personnel and equipment from the entire floor from which asbestos was to be removed before plaintiff could begin work. To enable the Department to continue its operations while the work was performed, the parties agreed that plaintiff would perform the asbestos removal work one floor at a time.

In accordance with this plan, plaintiff started work on the first floor in June 1996 and completed all work on the first and second floors sometime in the second half of 1997. However, the Department encountered difficulty relocating its employees on the other floors to enable plaintiff to complete its work. As a result, the DBC issued an order in October 1997 which directed plaintiff to suspend all work until the Department was able to devise a suitable plan for relocating its employees.

Plaintiff submitted a claim for the damages it had allegedly incurred as a result of the suspension of its work. The parties subsequently engaged in lengthy negotiations concerning plaintiffs claim as well as completion of its performance under the contract.

These negotiations resulted in a supplemental agreement between the DBC and plaintiff, which was executed in January 1999. Under section A of this agreement, the DBC agreed to pay plaintiff $150,000 as “full and complete compensation for all of the Contractor’s expenses, losses, claims and/or damages incurred as a result of the Order of Suspension.” Section B of the supplemental agreement states in relevant part:

[298]*2981. In the event the State moves forward with the Project, the State will issue a Dissolution of Order of Suspension simultaneously with a Notice to Proceed____
2. Within 10 days of the Dissolution of Order of Suspension and issuance of the Notice to Proceed, the Contractor shall return to the jobsite and complete the work on the Project, or any portion of work thereof, as determined by the State____

Section C of the supplemental agreement, the section directly implicated in this appeal, which is entitled “Termination for Convenience,” states in relevant part:

1. The State may, at any time, by written order terminate the Contract or any portion thereof for convenience after determining that for reasons beyond the Contractor’s control, the Contractor is or will be unable to proceed with or complete the Project as contracted for, or that termination is otherwise in the public interest.
2. Notwithstanding the above paragraph, the State expects to proceed with the Project and to issue the Contractor a Dissolution of Order of Suspension and Notice to Proceed. The Parties acknowledge that should the State exercise its right to terminate the contract for convenience and should such termination constitute an act of bad faith, the Contractor has not waived its right to pursue a breach of contract action against the State.
9. If the Director orders termination of the Contract for convenience, the State will pay for all completed items of work as of the date of the Order of Termination, at the Contract price or pursuant to any agreed apon change order. The State shall not pay for specific items or portions of the Project that have been eliminated by the Order for Termination.
(Emphasis added.)

Pursuant to this supplemental agreement, the DBC issued a notice on April 6, 1999, vacating the suspension order and directing plaintiff to proceed with asbestos removal on the fourth floor of the Labor Building. At that time, the parties anticipated that plaintiffs work on the fourth floor would be completed by November 1999 and that work on the third floor would proceed immediately thereafter. However, the Department of Labor advised the DBC in August 1999 that it was still experiencing difficulty relocating its employees and equipment on the third floor and therefore would be unable to make that floor available when plaintiff completed work on the fourth floor.

After the DBC notified plaintiff of this anticipated further delay, plaintiff submitted a claim for an additional $85,000 in delay damages. The Department subsequently notified the DBC that it [299]*299would not be able to make the third floor available for asbestos removal until July 2000 at the earliest. After unsuccessfully attempting to negotiate an agreement limiting plaintiffs claim for additional delay damages, the DBC notified plaintiff on January 6, 2000 that it was exercising its right under the supplemental agreement to terminate the contract “in the public interest, due to the impossibility of performance on the 3rd floor of the Labor Building, arising from the current occupancy of that space.”

More than a year later, the DBC entered into a new contract with another contractor for removal of asbestos on the third floor of the Labor Building.

After the DBC terminated the contract, plaintiff brought this breach of contract action. Plaintiffs complaint asserted that the Department’s inability to relocate the workers on the third floor and plaintiffs failure to accept the DBC’s proposals for additional compensation for the Department’s delay in making the third floor available for asbestos removal was not a valid basis for the DBC to invoke the termination for convenience provision of the contract.

After completion of discovery, the case was brought before the trial court by cross-motions for summary judgment. The court concluded that the DBC had not acted in bad faith in exercising its right under the supplemental agreement to terminate the contract for convenience.

You can talk about bad faith____What does it mean? Is [it] ineptitude, is [it] poor administration, is [it] generally screwing things up[?]
The State was in a situation where things were not running as they wanted it to. Things were not running as ... anyone would hope they would under the circumstances and [the] decisions [that] were made.... I specifically do not find were made to injure your client, or were made in bad faith to get some form of advantage over your client in order to obviate the need to continue on with this particular contact.
And I’m satisfied too that that was one of the things that was anticipated by the parties given the track record up until the point of the execution of the supplemental agreement.

Accordingly, the trial court entered summary judgment dismissing plaintiffs complaint.

[300]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

A.L. Prime Energy Consultant, Inc. v. Massachusetts Bay Transportation Authority
34 Mass. L. Rptr. 164 (Massachusetts Superior Court, Suffolk County, 2017)
Handi-Van, Inc. v. Broward County
116 So. 3d 530 (District Court of Appeal of Florida, 2013)
Hassler v. Sovereign Bank
644 F. Supp. 2d 509 (D. New Jersey, 2009)
In Re Appeal by Earle Asphalt Co.
950 A.2d 918 (New Jersey Superior Court App Division, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
848 A.2d 863, 369 N.J. Super. 295, 2004 N.J. Super. LEXIS 181, Counsel Stack Legal Research, https://law.counselstack.com/opinion/capital-safety-inc-v-state-njsuperctappdiv-2004.