Brunobuilt v. Strata

457 P.3d 860, 166 Idaho 208
CourtIdaho Supreme Court
DecidedFebruary 5, 2020
Docket46638
StatusPublished
Cited by14 cases

This text of 457 P.3d 860 (Brunobuilt v. Strata) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brunobuilt v. Strata, 457 P.3d 860, 166 Idaho 208 (Idaho 2020).

Opinion

IN THE SUPREME COURT OF THE STATE OF IDAHO Docket No. 46638

BRUNOBUILT, INC., an Idaho corporation, ) ) Plaintiff-Appellant, ) ) Boise, December 2019 Term v. ) ) Opinion Filed: February 5, 2020 STRATA, INC.; CHRIS M. COMSTOCK; H. ) ROBERT HOWARD; MICHAEL G. ) Karen A. Lehrman, Clerk WOODWORTH, ) ) Defendants-Respondents )

Appeal from the District Court of the Fourth Judicial District of the State of Idaho, Ada County. Steven Hippler, District Judge.

The judgment of the district court is affirmed. No attorney fees are awarded on appeal. Costs are awarded to the Strata Defendants as the prevailing party.

McConnell Wagner Sykes & Stacey, PLLC, Boise, attorneys for Appellant. Rick L. Stacey and Chad M. Nicholson argued.

Duke, Scanlan & Hall, PLLC, Boise, attorneys for Respondent. Kevin A. Griffiths argued. ___________________________________

BEVAN, Justice I. NATURE OF THE CASE BrunoBuilt, Inc., (“BrunoBuilt”) appeals a district court’s dismissal of its claims against Strata, Inc. (“Strata”), Chris M. Comstock, H. Robert Howard, and Michael G. Woodworth (collectively “the Strata Defendants”). BrunoBuilt filed a professional negligence action against the Strata Defendants alleging that when the Strata Defendants rendered engineering services for the Terra Nativa Subdivision they failed to identify a pre-existing landslide and negligently failed to recommend construction of infrastructure that would stabilize and prevent further landslides within the Subdivision. A home BrunoBuilt had contracted to build and the lot on which the dwelling was located were allegedly damaged as a result. The district court dismissed BrunoBuilt’s claims after holding that the parties had entered into an enforceable settlement 1 agreement, or alternatively, that summary judgment was warranted in favor of the Strata Defendants based on the economic loss rule. We affirm the district court judgment because the parties entered into an enforceable settlement agreement.

II. FACTUAL AND PROCEDURAL BACKGROUND In 1992, owners of land in the Boise foothills began developing a multiple phase subdivision that would ultimately become known as the Terra Nativa Subdivision (“Subdivision”). The developers retained Strata to perform geotechnical engineering services throughout the development of the Subdivision. The current matter arises from earth movement affecting property located at Lot 16, also known as 238 N. Alto Via Court (“Lot 16”) in the Subdivision. Amy and William Dempsey purchased Lot 16 in 2014 and signed a contract with BrunoBuilt to construct a home. Pursuant to the contract, the Dempseys quitclaimed Lot 16 to BrunoBuilt to construct a home, and upon completion BrunoBuilt was to re-convey the lot to the Dempseys in exchange for the contract price. Prior to commencing construction on the Dempsey home, BrunoBuilt built a residence on neighboring property down the street for Paul and Becky Rowan. Around February 2016, portions of the land in the Subdivision began to slide. In February and March 2016, final building inspections were performed in anticipation of securing a certificate of occupancy from the City. The home BrunoBuilt constructed for the Dempseys on Lot 16 passed all the final building inspections; yet, sometime between April and June of 2016, the slide became noticeable within Lot 16 with visible cracking in the front yard. The house itself was not damaged by the earth movement, but all utilities, highway district, and fire department services in the area were terminated. As a result, the City withheld issuing a certificate of occupancy for the house on Lot 16. Unable to occupy their home, the Dempseys refused to pay under the contract and BrunoBuilt retained ownership of Lot 16. 1 Predictably, the ground displacement within the Subdivision resulted in several lawsuits. On October 6, 2016, the Rowans sent BrunoBuilt a demand letter under Idaho’s Notice and Opportunity to Repair Act (“NORA”) for the damage occurring to their home on Alto Via Court. BrunoBuilt tendered the NORA notice to Strata, demanding that Strata defend and indemnify

1 BrunoBuilt has filed a separate cause of action against the Dempseys for breach of contract in BrunoBuilt, Inc. v. Dempsey, Ada County Case No. CV01-17-23686. 2 BrunoBuilt with respect to the Rowans’ claim; however, Strata rejected BrunoBuilt’s tender based on a contract that was executed between Strata and BrunoBuilt for the Rowan project. The Rowan damages arose from the same earth movement that damaged Lot 16, both of which were the subject of a separate action against the Strata Defendants, Sericati, et al. v. Strata, Inc., et al., Ada County Case No. CV OC 16-09068 (the “Sericati case”). On December 19, 2016, BrunoBuilt filed another action, BrunoBuilt v. Kleinfelder, et al., Ada County Case No. CV01-16-22915 (the “Kleinfelder case”). In the Kleinfelder case, Brunobuilt named several individuals and entities involved in the development of the Subdivision, including the Strata Defendants. BrunoBuilt did not serve the Strata Defendants at that time because the parties were engaged in settlement discussions. On January 3, 2017, counsel for the Strata Defendants, Kevin Scanlan, met with counsel for BrunoBuilt, Wyatt Johnson, to discuss potential dismissal of the claims against the Strata Defendants in the Kleinfelder case. Scanlan proposed that if BrunoBuilt would agree to dismiss its pending claims against the Strata Defendants in the Kleinfelder case, the Strata Defendants would negotiate with the Rowans in the Sericati case to secure a covenant not to sue, by which the Rowans would agree not to sue BrunoBuilt for any landslide damage caused to their home. In a declaration, Johnson testified that Scanlan made it clear that the Strata Defendants were not proposing any payment to BrunoBuilt for damages BrunoBuilt had sustained as a result of the 2016 landslide (which damages were sustained in connection with the agreement between the Dempseys and BrunoBuilt). Instead, the sole consideration the Strata Defendants were offering in exchange for BrunoBuilt’s agreement to dismiss its pending claims against the Strata Defendants was an agreement by the Strata Defendants to secure a covenant from the Rowans that they would not sue BrunoBuilt for the landslide damages caused to their home. Johnson told Scanlan he would discuss the Strata Defendants’ settlement offer with his client and get back to him. Between January 3, 2017, and January 10, 2017, Scanlan negotiated with counsel for the Rowans regarding including the covenant not to sue in the settlement of the Sericati case and with Johnson regarding settlement of the Kleinfelder case. On January 5, 2017, Scanlan called Johnson to ask about the status of the offer. Johnson informed Scanlan that BrunoBuilt’s principal, Robert Bruno, was still considering it. Scanlan gave Johnson until January 9 to accept. During the call, Johnson and Scanlan also discussed (1)

3 whether BrunoBuilt would be willing to provide a Pierringer 2 release to the Strata Defendants in the Kleinfelder case, through which it would only dismiss the Strata Defendants and maintain its claims against the other defendants, or (2) whether it would dismiss the entire case. Johnson advised Scanlan he would discuss the Pierringer release option with his client and get back to him on whether his client would agree to the proposal. On January 9, 2017, during a phone call, Johnson informed Scanlan that BrunoBuilt would be willing to dismiss its claims against the Strata Defendants in exchange for a release from the Rowans, but BrunoBuilt required that it have the direct and independent right to enforce any covenant not to sue that the Rowans might give to the Strata Defendants in the Sericati case.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

York v. Kemper Northwest, Inc.
Idaho Supreme Court, 2026
Streamline Builders, LLC v. Chase
Idaho Supreme Court, 2024
Evans v. Wright
554 P.3d 591 (Idaho Supreme Court, 2024)
Gomez v. Hurtado
554 P.3d 53 (Idaho Supreme Court, 2024)
Bracken v. City of Ketchum
537 P.3d 44 (Idaho Supreme Court, 2023)
Treasure Valley Home Solutions, LLC v. Chason
524 P.3d 1272 (Idaho Supreme Court, 2023)
Knudsen v. J.R. Simplot Company
Idaho Supreme Court, 2021

Cite This Page — Counsel Stack

Bluebook (online)
457 P.3d 860, 166 Idaho 208, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brunobuilt-v-strata-idaho-2020.