Spokane Structures, Inc. v. Equitable Investment, LLC

226 P.3d 1263, 148 Idaho 616, 2010 Ida. LEXIS 17
CourtIdaho Supreme Court
DecidedJanuary 28, 2010
Docket35349-2008
StatusPublished
Cited by42 cases

This text of 226 P.3d 1263 (Spokane Structures, Inc. v. Equitable Investment, LLC) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Spokane Structures, Inc. v. Equitable Investment, LLC, 226 P.3d 1263, 148 Idaho 616, 2010 Ida. LEXIS 17 (Idaho 2010).

Opinion

EISMANN, Chief Justice.

This is an action to recover damages for preparing plans and specifications for a building remodel. The parties had entered into a “Design/Build Agreement,” but after the plaintiff prepared the plans for the remodel, the defendant elected not to proceed with the project. The district court granted summary judgment holding that the parties had an express contract that did not obligate the defendant to pay any money if it elected not to proceed with the project and that recovery under any equitable theory was precluded because of the existence of the express contract. Because the parties did not have a binding contract, we vacate the summary judgment and remand for further proceedings.

I. FACTS AND PROCEDURAL HISTORY

Equitable Investment, LLC, (Landowner) approached Spokane Structures, Inc., (Builder) about designing the remodel of a building into a commercial office and warehouse and then providing the labor and materials for the remodel. The parties executed a one-page document entitled “Design/Build Agreement,” which provided as follows:

This agreement between SPOKANE STRUCTURES, INC. and Systemsteehnologies [sic] sets forth the scope of the work to be performed by SPOKANE STRUCTURES, INC. in the design and construction of an office and warehouse of approximately 7950 sq. ft. located in Hayden, Idaho. Spokane Structures, Inc. agrees to design, engineer, and draft plans in preparation of all documents/drawings required to enable the owner and contractor to agree on a final design and cost of construction to be performed. As a minimum the drawings to be prepared should include:
1. Site and location plans to determine building location and elevation, set backs from property lines and utility locations.
2. Building foundations, slabs and sidewalks.
3. Building floor plans.
*618 4. Schedules of doors, windows, finishes, etc.
5. Exterior building elevation to show style, form and finish.
6. Building sections to show sufficient detail required to achieve style and to show code compliance.
7. Electrical system layout.
8. Heating, air conditioning and ventilation to show all equipment and ducting.
9. Plumbing system layout including location of all special requirements, hose bibs, etc.
A final cost for construction will be provided upon completion of the plans and approval from the City of Hayden Building Department. The cost for construction is not to exceed $605,000.00, which includes all costs associated with construction, including overhead and profit. Change orders will be handle [sic] in writing only, and billed at cost of change plus 20% for profit and overhead. Billing for construction will be monthly progress billing on the percentage of completion method. This agreement is contingent upon the owners getting financing. Should financing not be obtained Spokane Structures, Inc. will be paid $5000.00 for the plans. A $2,500.00 retainer is required at signing of this agreement.

Builder commenced working on plans for the remodel, and Landowner requested various changes including increasing the building size by 5,000 square feet. On March 16, 2007, Builder completed a final design incorporating those requested changes. It sent Landowner the remodel plans along with a proposed construction contract signed by Builder under which it agreed to complete the project for $644,092. Landowner decided not to follow through with the project.

On June 7, 2007, Builder filed a complaint alleging that the Design/Build Agreement was a binding contract and seeking either specific performance of the agreement or damages for breach of contract, unjust enrichment, quantum meruit, or promissory estoppel. Landowner filed an answer, and on February 12, 2008, it moved for summary judgment. At the hearing on the motion for summary judgment, the district court orally ruled that the Design/Build Agreement was an unambiguous, express contract; that Landowner could not have breached the contract because its terms did not obligate Landowner to do anything; and that Builder could not recover on any equitable theories because there was an express contract.

On April 15, 2008, the district court entered an order granting Landowner’s motion for summary judgment. On June 17, 2008, after briefing and argument, the court entered an order awarding Landowner court costs, including a reasonable attorney fee, in the sum of $14,446.75.

On May 23, 2008, Builder had filed a notice of appeal. The district court did not enter a final judgment until June 24, 2008, and then on July 15, 2008, it entered an amended judgment which included the award of costs.

II. ANALYSIS

A. Do We Have Jurisdiction To Hear this Appeal?

Before we address the merits of the appeal, we will consider the effect of Builder’s premature notice of appeal. Insofar as is relevant to this case, an appeal as a matter of right could only be taken from a judgment, order, or decree that was final. I.A.R. 11(a)(1). In this case, Builder filed its notice of appeal before entry of the final judgment, and it stated in the notice of appeal that it was appealing “from the Order granting summary judgment entered in the above-entitled action on the 15th day of April, 2008.” In addition, the clerk’s record on appeal was prepared and filed with this Court before the final judgment was entered, and therefore the final judgment was not in the record on appeal. After this Court raised the lack of a final judgment during oral argument, Landowner supplemented the record with copies of the final judgment and the amended judgment.

At the time Builder filed its notice of appeal, the district court had entered its order granting summary judgment. That order stated:

*619 IT IS HEREBY ORDERED, ADJUDGED AND DECREED that there exists no issue as to any material fact and that Defendant is entitled to judgment as a matter of law.
NOW, THEREFORE, IT IS ORDERED that Defendant’s Motion for Summary Judgment against Plaintiff be, and it is, granted and that judgment will be entered in favor of the Defendant Equitable Investment, LLC, and against the Plaintiff, Spokane Structures, Inc.

This order did not constitute a judgment. As we stated in In re Universe Life Insurance Co., 144 Idaho 751, 756, 171 P.3d 242, 247 (2007), “An order granting summary judgment does not constitute a judgment.”

Rule 56(e) of the Idaho Rules of Civil Procedure provides with respect to a motion for summary judgment:

The judgment sought

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re: Marc Howell
Ninth Circuit, 2026
Milton v. Valley
D. Idaho, 2025
Snap! Mobile v. Vertical Raise
544 P.3d 714 (Idaho Supreme Court, 2024)
Treasure Valley Home Solutions, LLC v. Chason
524 P.3d 1272 (Idaho Supreme Court, 2023)
Chester v. Wild Idaho Adventures RV Park, LLC
519 P.3d 1152 (Idaho Supreme Court, 2022)
Uzzle v. Estate of Eric Milo Hirning
Idaho Supreme Court, 2022
Durst v. ID Comm. for Reapportionment
505 P.3d 324 (Idaho Supreme Court, 2022)
IDJC v. Dudley
467 P.3d 420 (Idaho Supreme Court, 2020)
Ellis v. Ellis
467 P.3d 365 (Idaho Supreme Court, 2020)
Brunobuilt v. Strata
457 P.3d 860 (Idaho Supreme Court, 2020)
Taylor v. Riley
Idaho Supreme Court, 2017
RE: The Estate of Gordon Thomas Lanham
369 P.3d 307 (Idaho Court of Appeals, 2016)
Rice v. Sallaz
357 P.3d 1256 (Idaho Supreme Court, 2015)
Safaris Unlimited v. Mike Von Jones
353 P.3d 1080 (Idaho Supreme Court, 2015)
Tracfone Wireless v. State of Idaho
351 P.3d 599 (Idaho Supreme Court, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
226 P.3d 1263, 148 Idaho 616, 2010 Ida. LEXIS 17, Counsel Stack Legal Research, https://law.counselstack.com/opinion/spokane-structures-inc-v-equitable-investment-llc-idaho-2010.