Aesthetic Elements, Inc. v. Meera Enterprises, LLC

CourtCourt of Appeals of Iowa
DecidedJanuary 9, 2025
Docket23-1250
StatusPublished

This text of Aesthetic Elements, Inc. v. Meera Enterprises, LLC (Aesthetic Elements, Inc. v. Meera Enterprises, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Aesthetic Elements, Inc. v. Meera Enterprises, LLC, (iowactapp 2025).

Opinion

IN THE COURT OF APPEALS OF IOWA

No. 23-1250 Filed January 9, 2025

AESTHETIC ELEMENTS, INC., Plaintiff-Appellee,

vs.

MEERA ENTERPRISE, LLC, Defendant-Appellant. ________________________________________________________________

Appeal from the Iowa District Court for Linn County, David M. Cox, Judge.

A defendant appeals a jury verdict awarding liquidated damages to the

plaintiff on its breach-of-contract claim. AFFIRMED.

Jodie C. McDougal, Brandon R. Underwood, and Sarah B. Golwitzer of

Fredrikson & Byron, P.A., Des Moines, for appellant.

Ryan J. Coufal and Gretchen L. McGill (Pro Hac Vice) of Dvorak Law Group,

LLC, Omaha, Nebraska, for appellee.

Heard by Greer, P.J., and Schumacher and Badding, JJ. 2

BADDING, Judge.

In the aftermath of the August 2020 derecho that tore through Iowa, Meera

Enterprise, LLC hired Aesthetic Elements, Inc. to evaluate its property damage and

submit a proposed scope of work to Meera’s insurer. The parties dispute whether

they also agreed that Aesthetic Elements would perform the approved repairs.

When Meera retained a different contractor, Aesthetic Elements sued for breach.

A jury found in Aesthetic Elements’ favor and awarded the company liquidated

damages. Meera appeals, challenging (1) whether there was an enforceable

contract; (2) the enforceability of a liquidated damages provision in that contract;

(3) the admission of lost-profits testimony from the owner of Aesthetic Elements;

and (4) the court’s refusal to submit a spoliation instruction to the jury. We affirm.

I. Background Facts and Proceedings

Meera Enterprise, LLC operates a hotel in Cedar Rapids, Iowa. On August

10, 2020, a powerful windstorm carved a path of destruction through Cedar Rapids

and the surrounding area. Among the affected properties was Meera’s hotel.

Meera promptly opened a claim with its insurer, West Bend Mutual Insurance

Company. It then turned to coordinating repairs.

On August 13, Meera’s owners—Dheeraj Julka and Rajinder Singh—

arranged a meeting with Aesthetic Elements, Inc., a contractor specializing in

“insurance restoration” projects. Julka and Aesthetic Elements were working

together on a hail damage claim for another hotel owned by one of Julka’s other

entities. During that meeting, representatives for Meera and Aesthetic Elements

executed a one-page, standardized “Service Agreement” prepared by Aesthetic

Elements. 3

Under the service agreement, Meera retained Aesthetic Elements “as

general contractor of record for the purpose of inspecting, evaluating and creating

an estimate for the scope of work necessary to repair or replace the damage” to

Meera’s hotel. The service agreement also provided:

If [Meera’s] insurance company (the “Insurer”) approves a claim for the Work (the “Claim”), [Meera] acknowledges and agrees that [Meera] shall promptly enter into a Construction Agreement with [Aesthetic Elements] to set forth the terms and conditions upon which [Aesthetic Elements] shall perform the Work. The cost of the Work shall be equal to the amount of the replacement cost value authorized by the Insurer (including all overhead and profit), plus the insurance deductible which shall be paid by [Meera] to [Aesthetic Elements] (the “Agreed Price”).

If Meera failed to enter a construction agreement or authorize repairs following

approval of the claim, the service agreement required Meera to pay Aesthetic

Elements “twenty percent . . . of the replacement cost value of the Claim.”

According to Aesthetic Elements, these terms were designed to facilitate an

efficient relationship between contractor, customer, and insurer. Project manager

Cody Langan testified that preparing an estimate and negotiating the scope of work

is “50 percent” of an insurance restoration project. The scope of work, according

to Langan, sets out “what needs to be done . . . to put the property back to its pre-

loss condition while maintaining current warranties, building code, [and]

manufacturer specifications.” Langan testified that the structure of the service

agreement gave Aesthetic Elements flexibility to negotiate necessary repairs while

capping Meera’s out-of-pocket costs at the price of its deductible. Julka testified

that, based on his review of the service agreement, he understood Meera was

hiring Aesthetic Elements to “fix the roof” on its hotel. 4

Immediately after the parties signed their service agreement, Aesthetic

Elements got to work evaluating the damage to the hotel. Workers spent multiple

days inspecting the roof membrane and conducting temporary repairs. On

September 4, Aesthetic Elements submitted an eighty-three-page inspection

report to West Bend comprised of pictures that Langan took the month before.

Although Langan began preparing a scope of work around the same time, he did

not complete it until October 15.

Meanwhile, Meera was talking to another contractor—North-West Roofing.

A lead generator from North-West had contacted Meera after the derecho and

arranged a meeting between Meera and one of North-West’s project managers.

On September 5, North-West started a scope of work for Meera, which it

completed five days later. The scope of work was revised later in September as

North-West communicated with Meera’s claims representative at West Bend.

During this same time, Langan was also communicating with the claims

representative, emailing him on September 14 “to see where we are at with this

claim?” The representative responded, “Cody[,] I know we . . . emailed back and

forth before and I know you’re a contractor. What company are you with?” Langan

answered, “I am with Aesthetic Elements, Inc. [W]e have been contracted by the

insured to complete their repairs. I will also re[-]attach a copy of our contract.”

On October 6, Meera signed an agreement with North-West to begin repairs

on the hotel. Aesthetic Elements was unaware. It proceeded to submit its

completed scope of work to a public adjuster identified by Julka the day before the

contract with North-West was signed. Langan testified that once a public adjuster

is involved, the insurance company and contractor cannot communicate: “all 5

correspondence from a contractor goes through that public adjuster.” Langan

testified that he did not learn about North-West’s involvement until sometime in

November, when his brother and owner of Aesthetics Elements, Steven Langan,

saw people at work on the roof of the hotel.

West Bend ultimately approved a claim for $461,645 in wind damage to

Meera’s property. Repairs were completed by North-West.1 Meera never signed

a construction agreement with Aesthetic Elements, and Aesthetic Elements was

never paid. In November 2021, Aesthetic Elements sued for liquidated damages,

alleging Meera violated the terms of the service agreement by “failing to allow

Aesthetic Elements to perform any and all work to the [p]roperty as approved and

agreed to by West Bend.” Aesthetic Elements also asserted a claim for unjust

enrichment.

Meera sought summary judgment, arguing, among other things, that the

service agreement was not supported by consideration and was an unenforceable

“agreement to agree.” Meera also challenged the liquidated damages provision

as an invalid penalty. The district court denied the motion. Following a four-day

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Spokane Structures, Inc. v. Equitable Investment, LLC
226 P.3d 1263 (Idaho Supreme Court, 2010)
Margeson v. Artis
776 N.W.2d 652 (Supreme Court of Iowa, 2009)
Tim O'Neill Chevrolet, Inc. v. Forristall
551 N.W.2d 611 (Supreme Court of Iowa, 1996)
Van Sickle Construction Co. v. Wachovia Commercial Mortgage, Inc.
783 N.W.2d 684 (Supreme Court of Iowa, 2010)
Rohlin Construction Co. v. City of Hinton
476 N.W.2d 78 (Supreme Court of Iowa, 1991)
Royal Indemnity Co. v. Factory Mutual Insurance Co.
786 N.W.2d 839 (Supreme Court of Iowa, 2010)
Palmer v. Albert
310 N.W.2d 169 (Supreme Court of Iowa, 1981)
Lynch v. Saddler
656 N.W.2d 104 (Supreme Court of Iowa, 2003)
McCarter v. Uban
166 N.W.2d 910 (Supreme Court of Iowa, 1969)
Whalen v. Connelly
545 N.W.2d 284 (Supreme Court of Iowa, 1996)
Air Host Cedar Rapids, Inc. v. Cedar Rapids Airport Commission
464 N.W.2d 450 (Supreme Court of Iowa, 1990)
Schaer v. Webster County
644 N.W.2d 327 (Supreme Court of Iowa, 2002)
Fausel v. JRJ Enterprises, Inc.
603 N.W.2d 612 (Supreme Court of Iowa, 1999)
Simon Estes v. Progressive Classic Insurance Company
809 N.W.2d 111 (Supreme Court of Iowa, 2012)
Francisco Villa Magana v. State of Iowa
908 N.W.2d 255 (Supreme Court of Iowa, 2018)
Kunz v. Kunz
895 N.W.2d 487 (Court of Appeals of Iowa, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
Aesthetic Elements, Inc. v. Meera Enterprises, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/aesthetic-elements-inc-v-meera-enterprises-llc-iowactapp-2025.