Boyer, Inc. v. Trinity River Authority of Texas

279 S.W.3d 354, 2008 WL 163560
CourtCourt of Appeals of Texas
DecidedMarch 26, 2009
Docket2-07-052-CV
StatusPublished
Cited by21 cases

This text of 279 S.W.3d 354 (Boyer, Inc. v. Trinity River Authority of Texas) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Boyer, Inc. v. Trinity River Authority of Texas, 279 S.W.3d 354, 2008 WL 163560 (Tex. Ct. App. 2009).

Opinion

OPINION

LEE ANN DAUPHINOT, Justice.

Appellant Boyer, Inc. seeks a reversal of the trial court’s summary judgment for Appellee Trinity River Authority of Texas (“TRA”) dismissing Boyer’s claim for lack of jurisdiction. Boyer argues on appeal that the trial court erred by not finding a waiver of immunity under the Texas Local Government Code because Boyer properly pleaded and provided sufficient summary judgment evidence to support the existence of a contract and a claim for breach of that contract. Boyer also argues that trial court erred if summary judgment was based on TRA’s position that the Texas Water Code contains no waiver of immunity for Boyer's contract claims because the water code is irrelevant to the sovereign immunity analysis. Because we hold that the trial court erred by granting summary judgment and dismissing Boyer’s claim, we reverse the judgment and remand the cause for further proceedings.

Facts and PRocedural History

On December 1, 1999, TRA and Boyer entered into a contract for work on TRA’s Lake Livingston Dam Improvements Project. Before completion of the work, TRA and Boyer executed a change order for additional work to be done by Boyer.

In June 2003, Boyer provided TRA with a revised estimate, adding $1,611,848.85 to the estimate that it had previously submitted. TRA did not take action on the revised estimate and subsequently terminated the contract. In January 2004, TRA instructed Boyer to demobilize and provide a final cost accounting. Boyer submitted a balance due of $624,051.00. TRA disputed Boyer’s calculations, which included actual field costs and a fifteen percent mark-up, and after the parties failed to resolve their disagreement, Boyer filed this suit.

TRA filed a plea to the jurisdiction and a summary judgment motion on its plea to the jurisdiction. TRA asserted in its motion that Boyer had already been paid according to the terms of the change order. According to TRA, although Boyer claimed that TRA was not immune from suit because Boyer’s cause of action was a suit on a written contract, in this case Boyer sought additional profits, which are consequential damages. TRA argued that under the local government code, consequential damages are not recoverable by a plaintiff suing on a written contract. Thus, TRA argued that it had immunity from suit.

TRA also asserted no-evidence grounds for summary judgment, arguing that there is no evidence that this is not a bona fide dispute, and thus the Prompt Payment Act does not apply here, and that there is no evidence that Boyer gave appropriate notice or followed the procedures required under the Prompt Payment Act.

In its response to TRA’s motion for summary judgment, Boyer maintained that the contract, as amended by the change order, provided for Boyer to be paid the fifteen percent mark-up. Boyer asserted that the trial court had jurisdiction under Local Government Code sections 271.151 through 271.160 and claimed that these provisions authorize damages for a balance due under a contract, “as it may have been amended, including any compensation for the increased cost to perform the work as a direct result of owner-caused delays.” Boyer claimed that the fifteen percent mark-up included “in *357 creased costs to perform,” as the mark-up included significant overhead costs, not just profits. The trial court granted summary judgment for TRA and dismissed Boyer’s claims with prejudice for lack of subject matter jurisdiction.

STANDARD OF REVIEW

A defendant is entitled to summary judgment on an affirmative defense if the defendant conclusively proves all the elements of the affirmative defense. 1 To accomplish this, the defendant-movant must present summary judgment evidence that establishes each element of the affirmative defense as a matter of law. 2 When reviewing a summary judgment, we take as true all evidence favorable to the non-movant, and we indulge every reasonable inference and resolve any doubts in the nonmovant’s favor. 3

Analysis

Sovereign immunity protects the state from suits for money damages, and the state’s political subdivisions “are entitled to such immunity — referred to as governmental immunity — unless it has been waived.” 4 We will refer to both sovereign immunity and governmental immunity as “sovereign immunity.”

In its first issue, Boyer argues that it properly pleaded and provided sufficient summary judgment evidence to support the existence of a contract and a claim for breach of that contract, and, therefore, under Texas Local Government Code sections 271.151 through 271.160, TRA does not have sovereign immunity.

Sovereign immunity is waived only by clear and unambiguous language. 5 Texas Local Government Code section 271.152 states;

A local governmental entity that is authorized by statute or the constitution to enter into a contract and that enters into a contract subject to this subchap-ter waives sovereign immunity to suit for the purpose of adjudicating a claim for breach of the contract, subject to the terms and conditions of this subchapter. 6

Section 271.153 limits the availability of damages in a suit under this subchapter:

(a) The total amount of money awarded in an adjudication brought against a local governmental entity for breach of a contract subject to this subchapter is limited to the following:
(1) the balance due and owed by the local governmental entity under the contract as it may have been amended, including any amount owed as compensation for the increased cost to perform the work as a direct result of owner-caused delays or acceleration;
(2) the amount owed for change orders or additional work the contractor is directed to perform by a local governmental entity in connection with the contract; and
(3) interest as allowed by law. 7

*358 This section goes on to state that “[d]am-ages awarded in an adjudication brought against a local governmental entity arising under a contract subject to this subchapter may not include ... consequential damages, except as expressly allowed under Subsection (a)(1) [or] ... damages for unabsorbed home office overhead.” 8

Section 271.151 defines “[(Contract subject to this subchapter” as “a written contract stating the essential terms of the agreement for providing goods or services to the local governmental entity that is properly executed on behalf of the local governmental entity.” 9 River authorities are included in the definition of “local governmental entity.” 10

The statutory provisions at issue contain the following historical note:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Powell Electrical Systems, Inc. v. Hewlett Packard Co.
356 S.W.3d 113 (Court of Appeals of Texas, 2011)
City of North Richland Hills v. Home Town Urban Partners, Ltd.
340 S.W.3d 900 (Court of Appeals of Texas, 2011)
Kirby Lake Development, Ltd. v. Clear Lake City Water Authority
320 S.W.3d 829 (Texas Supreme Court, 2010)
Jones v. City of Dallas
310 S.W.3d 523 (Court of Appeals of Texas, 2010)
Kansas City Southern v. Port of Corpus Christi Authority
305 S.W.3d 296 (Court of Appeals of Texas, 2009)
City of Corinth v. NUROCK DEVELOPMENT, INC.
293 S.W.3d 360 (Court of Appeals of Texas, 2009)
Clear Lake City Water Auth. v. FRIENDSWOOD DEVELOPMENT COMPANY, LTD.
256 S.W.3d 735 (Court of Appeals of Texas, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
279 S.W.3d 354, 2008 WL 163560, Counsel Stack Legal Research, https://law.counselstack.com/opinion/boyer-inc-v-trinity-river-authority-of-texas-texapp-2009.