Boyer, Inc. v. Trinity River Authority of Texas

Procedural entryThis page is a short order in Boyer, Inc. v. Trinity River Authority of Texas. Read the opinion of the Court — 279 S.W.3d 354
Court of Appeals of Texas·Decided January 17, 2008·No. 02-07-00052-CV·Published

Opinion

                                      COURT OF APPEALS

                                       SECOND DISTRICT OF TEXAS

                                                   FORT WORTH

                                        NO. 2-07-052-CV

BOYER, INC.                                                                       APPELLANT

                                                   V.

TRINITY RIVER AUTHORITY

OF TEXAS                                                                            APPELLEE

                                              ------------

           FROM THE 141ST DISTRICT COURT OF TARRANT COUNTY

                                              ------------

                                             OPINION

                                              ------------


Appellant Boyer, Inc. seeks a reversal of the trial court=s summary judgment for Appellee Trinity River Authority of Texas (ATRA@) dismissing Boyer=s claim for lack of jurisdiction.  Boyer argues on appeal that the trial court erred by not finding a waiver of immunity under the Texas Local Government Code because Boyer properly pleaded and provided sufficient summary judgment evidence to support the existence of a contract and a claim for breach of that contract.  Boyer also argues that trial court erred if summary judgment was based on TRA=s position that the Texas Water Code contains no waiver of immunity for Boyer=s contract claims because the water code is irrelevant to the sovereign immunity analysis.  Because we hold that the trial court erred by granting summary judgment and dismissing Boyer=s claim, we reverse the judgment and remand the cause for further proceedings.

Facts and Procedural History

On December 1, 1999, TRA and Boyer entered into a contract for work on TRA=s Lake Livingston Dam Improvements Project.  Before completion of the work, TRA and Boyer executed a change order for additional work to be done by Boyer.

In June 2003, Boyer provided TRA with a revised estimate, adding  $1,611,848.85 to the estimate that it had previously submitted.  TRA did not take action on the revised estimate and subsequently terminated the contract. In January 2004, TRA instructed Boyer to demobilize and provide a final cost accounting.  Boyer submitted a balance due of $624,051.00.  TRA disputed Boyer=s calculations, which included actual field costs and a fifteen percent mark-up, and after the parties failed to resolve their disagreement, Boyer filed this suit.


TRA filed a plea to the jurisdiction and a summary judgment motion on its plea to the jurisdiction.  TRA asserted in its motion that Boyer had already been paid according to the terms of the change order.  According to TRA, although Boyer claimed that TRA was not immune from suit because Boyer=s cause of action was a suit on a written contract, in this case Boyer sought additional profits, which are consequential damages.  TRA argued that under the local government code, consequential damages are not recoverable by a plaintiff suing on a written contract.  Thus, TRA argued that it had immunity from suit.        TRA also asserted no-evidence grounds for summary judgment, arguing that there is no evidence that this is not a bona fide dispute, and thus the Prompt Payment Act does not apply here, and that there is no evidence that Boyer gave appropriate notice or followed the procedures required under the Prompt Payment Act.


In its response to TRA=s motion for summary judgment, Boyer maintained that the contract, as amended by the change order, provided for Boyer to be paid the fifteen percent mark-up.  Boyer asserted that the trial court had jurisdiction under Local Government Code sections 271.151 through 271.160 and claimed that these provisions authorize damages for a balance due under a contract, Aas it may have been amended, including any compensation for the increased cost to perform the work as a direct result of owner-caused delays.@  Boyer claimed that the fifteen percent mark-up included Aincreased costs to perform,@ as the mark-up included significant overhead costs, not just profits.  The trial court granted summary judgment for TRA and dismissed Boyer=s claims with prejudice for lack of subject matter jurisdiction.

Standard of Review

A defendant is entitled to summary judgment on an affirmative defense if the defendant conclusively proves all the elements of the affirmative defense.[1]  To accomplish this, the defendant-movant must present summary judgment evidence that establishes each element of the affirmative defense as a matter of law.[2]  When reviewing a summary judgment, we take as true all evidence favorable to the nonmovant, and we indulge every reasonable inference and resolve any doubts in the nonmovant=s favor.

Free access — add to your briefcase to read the full text and ask questions with AI

Boyer, Inc. v. Trinity River Authority of Texas, (Tex. Ct. App. 2008).

Boyer, Inc. v. Trinity River Authority of Texas (Boyer, Inc. v. Trinity River Authority of Texas) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Olympic Waste Services v. City of Grand Saline
204 S.W.3d 496 (Court of Appeals of Texas, 2006)
Reata Construction Corp. v. City of Dallas
197 S.W.3d 371 (Texas Supreme Court, 2006)
Tooke v. City of Mexia
197 S.W.3d 325 (Texas Supreme Court, 2006)
Continental Holdings, Ltd. v. Leahy
132 S.W.3d 471 (Court of Appeals of Texas, 2003)
Matheus v. Sasser
164 S.W.3d 453 (Court of Appeals of Texas, 2005)
Rhone-Poulenc, Inc. v. Steel
997 S.W.2d 217 (Texas Supreme Court, 1999)
Duhart v. State
610 S.W.2d 740 (Texas Supreme Court, 1980)
Ryland Group, Inc. v. Hood
924 S.W.2d 120 (Texas Supreme Court, 1996)