McKinney & Moore, Inc. v. City of Longview, Texas

CourtCourt of Appeals of Texas
DecidedDecember 8, 2009
Docket14-08-00628-CV
StatusPublished

This text of McKinney & Moore, Inc. v. City of Longview, Texas (McKinney & Moore, Inc. v. City of Longview, Texas) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McKinney & Moore, Inc. v. City of Longview, Texas, (Tex. Ct. App. 2009).

Opinion

Affirmed as Modified and Memorandum Opinion filed December 8, 2009.

In The

Fourteenth Court of Appeals

___________________

NO. 14-08-00628-CV

McKinney & Moore, Inc., Appellant

V.

City of Longview, Texas, Appellee

On Appeal from the 188th District Court

Gregg County, Texas

Trial Court Cause No. 2004-243-A

MEMORANDUM OPINION

McKinney & Moore, Inc. (AMMI@) appeals from the trial court=s grant of both a plea to the jurisdiction based on governmental immunity and a summary judgment on the merits favoring the City of Longview, Texas.  Longview had awarded MMI, a general contractor, the contract to construct the Lake O= the Pines Raw Water Intake Structure.  After MMI completed work on the project, and Longview made what it considered final payment on the contract, MMI sued for additional sums allegedly due.  In two issues, MMI attacks the trial court’s grant of the jurisdictional plea and the summary judgment on the merits.  We reverse in part the trial court’s holding on the plea to the jurisdiction, affirm the summary judgment, and affirm the judgment as modified.

I.  Background

In November 2000, Longview opened bidding for construction of the Lake O= the Pines Raw Water Intake Structure.  Prior to the bidding, Longview had hired an engineering firm who then hired a subcontractor, URS Grenier Woodward Clyde, to perform a subsurface investigation of the project site, including taking samples from four bore holes.  URS produced a geotechnical report dated May 1999, which was made available to the contract bidders.  The introductory section of the report warned that the report might “not be adequate for construction planning, cost estimating or design of temporary works.”  There is no evidence in the record that MMI performed any subsurface investigation on its own either prior to bidding or after being awarded the contract.

MMI was awarded the contract.  Among the provisions of the contract of interest in this case are the following:

C  Section SP-27 states that subsurface and soils information is furnished for “information only” and without any representation as to “accuracy or adequacy.”  It also advises prospective bidders to make their own investigations “as they deem necessary.”

C  Section SP-33 permits the contractor to rely on the “subsurface soil investigations[,] soil boring logs and test result” contained in the URS report.  It further states that “Contractor recognizes that the technical data listed reflect only the conditions for the day the data was collected and reflects [sic] only conditions existing at the exact location of Samples.”

C  Section 3.03 makes the owner “responsible for the adequacy of the design, sufficiency of the Contract Documents, the safety of the structure, and the practicability of the operations of the completed project,” provided the contractor has complied with all requirements.

C  Section 3.08, labeled “DAMAGES,” states that if the contractor is damaged during work on the project “by the act, neglect, omission, mistake or default” of the owner or other entity employed by the owner, the owner will reimburse the contractor for the loss.

C  Section 6.04 mandates that “acceptance by the CONTRACTOR of final payment shall be a bar to any claims . . . except where noted otherwise in the Contract Documents.”

During performance of the contract, MMI reportedly encountered unexpected difficulties, including:  (1) high rainfall which led to unprecedented lake levels, and (2) a layer of iron ore rock which had not been revealed in the URS report.  The contract called for a completion date of November 30, 2001.  Due to the unexpected events, MMI requested three change orders, under procedures set forth in the contract, to extend the project’s scheduled completion date.  On October 18, 2001, after the first change order was granted but prior to the granting of the other two, the president of MMI, George McKinney, wrote a letter to Longview, suggesting that his company would absorb the added expense associated with the unexpected difficulties in exchange for granting of the time extensions for completion of the work.  Such extensions allowed MMI to avoid paying liquidated damages for failure to timely complete the project.

On March 20, 2003, near completion of the project, MMI submitted a Request for Equitable Adjustment seeking the additional costs it had incurred due to the unexpected difficulties.  Longview denied the request in July 2003.  On December 12, 2003, after project completion, MMI submitted to Longview a payment request, signed by McKinney and notarized, showing that with the requested payment, the amount due on the contract would be paid in full.  This request was apparently transmitted to Longview along with a cover letter suggesting that MMI still sought an equitable adjustment for additional amounts as presented in the March 20 Request for Equitable Adjustment.  Subsequently, on January 14, 2004, MMI prepared a revised payment request, adding an additional $2,040 to the amount allegedly due under the contract.  Longview, however, ultimately paid only the amount contained in the original final payment request, a total of $4,128,668.25.  MMI accepted that payment.

MMI then sued Longview, seeking recovery of the additional expenses MMI had incurred due to the unexpected difficulties encountered during construction.  In response, Longview filed a plea to the jurisdiction based on governmental immunity.  Specifically, Longview argued that although in section 271.152 of the Local Government Code, the Texas Legislature waived immunity for municipalities for breach of contract claims, MMI’s claims (1) were based in tort principles not breach of contract, and (2) sought consequential damages, which were barred in such suits by section 271.153 of the Local Government Code.  Tex. Loc. Gov’t Code §§ 271.152, 271.153.  Longview also filed a motion for summary judgment on the merits, arguing, among other things, that as a matter of law:  (1) it did not breach the contract, (2) MMI was estopped from seeking additional sums based on statements it made in its requests for additional time to complete construction, (3) governmental immunity had not been waived for MMI’s claims, and (4) MMI’s acceptance of final payment barred it from seeking additional sums pursuant to section 6.04 of the contract.  The trial court granted both the plea to the jurisdiction and the summary judgment on the merits without stating the grounds therefor.

II.  Plea to the Jurisdiction

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Texas Department of Parks & Wildlife v. Miranda
133 S.W.3d 217 (Texas Supreme Court, 2004)
Valence Operating Co. v. Dorsett
164 S.W.3d 656 (Texas Supreme Court, 2005)
Seagull Energy E & P, Inc. v. Eland Energy, Inc.
207 S.W.3d 342 (Texas Supreme Court, 2006)
State v. Holland
221 S.W.3d 639 (Texas Supreme Court, 2007)
FM Properties Operating Co. v. City of Austin
22 S.W.3d 868 (Texas Supreme Court, 2000)
Tooke v. City of Mexia
197 S.W.3d 325 (Texas Supreme Court, 2006)
City of Carrollton v. Singer
232 S.W.3d 790 (Court of Appeals of Texas, 2007)
McConnell v. Southside Independent School District
858 S.W.2d 337 (Texas Supreme Court, 1993)
County of Cameron v. Brown
80 S.W.3d 549 (Texas Supreme Court, 2002)
Provident Life & Accident Insurance Co. v. Knott
128 S.W.3d 211 (Texas Supreme Court, 2003)
Boyer, Inc. v. Trinity River Authority of Texas
279 S.W.3d 354 (Court of Appeals of Texas, 2009)
Stuart v. Bayless
964 S.W.2d 920 (Texas Supreme Court, 1998)
Arthur Andersen & Co. v. Perry Equipment Corp.
945 S.W.2d 812 (Texas Supreme Court, 1997)
Mead v. Johnson Group, Inc.
615 S.W.2d 685 (Texas Supreme Court, 1981)
Forbau Ex Rel. Miller v. Aetna Life Insurance Co.
876 S.W.2d 132 (Texas Supreme Court, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
McKinney & Moore, Inc. v. City of Longview, Texas, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mckinney-moore-inc-v-city-of-longview-texas-texapp-2009.