Bourassa v. Gateway Erectors, Inc.

194 N.W.2d 602, 54 Wis. 2d 176, 1972 Wisc. LEXIS 1064
CourtWisconsin Supreme Court
DecidedFebruary 29, 1972
Docket235
StatusPublished
Cited by20 cases

This text of 194 N.W.2d 602 (Bourassa v. Gateway Erectors, Inc.) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bourassa v. Gateway Erectors, Inc., 194 N.W.2d 602, 54 Wis. 2d 176, 1972 Wisc. LEXIS 1064 (Wis. 1972).

Opinion

Hallows, C. J.

Two issues are raised on this appeal: (1) Was Bourassa’s negligence at least equal to Gateway’s as a matter of law and should recovery under *179 the comparative negligence law therefore he denied; and (2) were six rulings made by the trial court erroneous and so prejudicial as to require a new trial in the interest of justice?

Contributory negligence.

The apportionment of negligence by a jury, like any other answer in the verdict will be sustained by this court if there is any credible evidence which under any reasonable view supports the jury’s findings. Fisher v. Simon (1961), 15 Wis. 2d 207, 112 N. W. 2d 705; Neider v. Spoehr (1969), 41 Wis. 2d 610, 165 N. W. 2d 171; Netzel v. State Sand & Gravel Co. (1971), 51 Wis. 2d 1, 12, 186 N. W. 2d 258.

A review of the evidence shows Gateway was to furnish the shoring or scaffolding which supported the forms used in constructing the concrete floors and the beams. The forms for the floor were furnished by the subcontractor but the general contractor had the duty to construct the forms for the beams. The scaffolding consisted of metal braces upon which were placed wooden ledger beams on which joists were laid at right angles. These joists protruded several feet beyond the edge of the building. In erecting the forms for the concrete beams, the general contractor used these protruding joists as support for a plywood plank, which served as a working platform for its employees on the outside of the building. On July 24, 1965, the date of the accident, the pouring and the hardening of the concrete for the floor and beams in this part of the hospital addition called Section A had been completed and Gateway removed its supporting scaffolding. Although the scaffold was removed, some of the joists stayed up against the underside of the floor or what would be the ceiling for the space below. These joists *180 were held to the undersurface because of braces which were nailed to the joists and to the beam forms. As a result, the work platform of the general contractor remained over the edge of the structure without any substantial support.

There is testimony, stressed by Gateway, that while the scaffolding was removed there was considerable noise from the timbers and beams falling down and, in fact, the floor in Section A vibrated during this procedure. It was also testified that a person looking at Section A from the outside could see the scaffolding was removed and some planks and parts of the wooden form for the horizontal beams were not supported. It was also testified that if Bourassa had looked down and under the edge of the newly poured floor before he stepped on the plank platform, he would have observed the absence of support for the platform. On these facts it is argued a foreman familiar with the construction knew or should have known the platform was unsafe.

The evidence, however, showed Bourassa had spent the day in Section C with his crew and did not know the scaffold had been removed in Section A and he did not hear the noise incident to the removal of the scaffolding. Bourassa further testified that while working in Section C his view of Section A was blocked by the scaffolding in Section B and when he went from Section C to Section A by climbing a ladder to the top of Section B, he did not have an occasion to notice whether the shoring was removed in Section A. He also testified it would be difficult for him to stop and peer over the edge of the building to see if the scaffolding was under the floor to support the plank and the joists extending beyond the building. Bourassa was injured when in removing some braces and wood on the outside of the building used for the beam forms he stepped on the working platform to retrieve the lumber. *181 The platform, being unsupported because Gateway had removed the scaffold, gave way and Bourassa was injured.

While it is clear Gateway had no contractual obligation to erect or provide a scaffold for work platforms on the outside of the building for use by the general contractor, the superintendent of Gateway testified the use of the protruding joists of the subcontractor as support for the general contractor’s platform for working on the forms for the horizontal concrete beams was a regular practice in the industry. There was also testimony that before the accident the construction superintendent saw several joists unsupported and told Gateway’s foreman to have his men strip the “whole works” and not leave anything hanging in the air.

We are of the opinion that although the evidence would sustain a greater allocation of causal negligence to Bourassa, his negligence was not at least equal or greater to Gateway’s negligence as a matter of law. 1 While the evidence may not support the exact apportionment of negligence as found by the jury, neither is the apportionment so unsupported that the case should be retried in the interest of justice. 2

*182 New trial in the interest of justice.

Gateway claims it was error to allow Bourassa to amend his complaint on the last day of trial. During the trial it became clear the general contractor, the employer of Bourassa, and not Gateway, owned the platform plank on which Bourassa stepped. Bourassa moved to amend his complaint to allege Gateway was negligent because it “failed to remove unsupported scaffolding planks and shoring from the second floor of the addition. . .” On the record it does not appear that Gateway was misled as to the nature of the negligence alleged in the complaint. Who owned the plywood plank would seem to be immaterial. The negligence was not in ownership but in the removal of the steel shoring and lumber which supported the plank which constituted the work place for employees of the general contractor. Amendments to pleadings are permitted by sec. 269.44, Stats., which is to be liberally construed. Wipfli v. Martin (1967), 34 Wis. 2d 169, 148 N. W. 2d 674; Siedenburg v. Severson (1971), 50 Wis. 2d 40, 183 N. W. 2d 35. There is no error in the court allowing the amendment. Turner Mfg. Co. v. Gmeinder (1924), 183 Wis. 664, 198 N. W. 611; McCraw v. Witynski (1969), 43 Wis. 2d 313, 168 N. W. 2d 537.

In instructing the jury, the court, over the objection of Gateway, stated the momentary diversion or preoccupation of a workman in the discharge of his duties minimized the degree of care required by him in the absence of such diversion or such preoccupation. This instruction was based on Wis J I — Civil 1051. 3 The *183 question is whether the facts warranted the giving- of such an instruction. Here, Bourassa had to reach down to remove the braces and some wood siding of the form for the beam and when the braces were loosened, he stepped down to the unsupported platform to remove and to retrieve them.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rosh v. Cave Imaging Systems, Inc.
26 Cal. App. 4th 1225 (California Court of Appeal, 1994)
Williamson v. City of Springfield
465 N.E.2d 1035 (Appellate Court of Illinois, 1984)
Thompson v. City of Philadelphia
466 A.2d 1349 (Supreme Court of Pennsylvania, 1983)
Precopio v. City of Detroit
330 N.W.2d 802 (Michigan Supreme Court, 1982)
Peair v. Home Ass'n of Enola Legion No. 751
430 A.2d 665 (Superior Court of Pennsylvania, 1981)
Ladwig v. Ermanco Inc.
504 F. Supp. 1229 (E.D. Wisconsin, 1981)
Gross v. Midwest Speedways, Inc.
260 N.W.2d 36 (Wisconsin Supreme Court, 1977)
Walsh v. Wild Masonry Co., Inc.
241 N.W.2d 416 (Wisconsin Supreme Court, 1976)
DeGroff v. Schmude
238 N.W.2d 730 (Wisconsin Supreme Court, 1976)
Smith v. Plankinton De Pulaski
238 N.W.2d 94 (Wisconsin Supreme Court, 1976)
Sampson v. Laskin
224 N.W.2d 594 (Wisconsin Supreme Court, 1975)
Britton v. Hoyt
218 N.W.2d 274 (Wisconsin Supreme Court, 1974)
Theuerkauf v. Schnellbaecher
218 N.W.2d 295 (Wisconsin Supreme Court, 1974)
Bohlman v. American Family Mutual Insurance
214 N.W.2d 52 (Wisconsin Supreme Court, 1974)
Gross v. Denow
212 N.W.2d 2 (Wisconsin Supreme Court, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
194 N.W.2d 602, 54 Wis. 2d 176, 1972 Wisc. LEXIS 1064, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bourassa-v-gateway-erectors-inc-wis-1972.