Boston Harbor Development Partners, LLC. v. United States

103 Fed. Cl. 499, 2012 WL 936633, 2012 U.S. Claims LEXIS 252
CourtUnited States Court of Federal Claims
DecidedMarch 5, 2012
DocketNo. 11-867C
StatusPublished
Cited by7 cases

This text of 103 Fed. Cl. 499 (Boston Harbor Development Partners, LLC. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Boston Harbor Development Partners, LLC. v. United States, 103 Fed. Cl. 499, 2012 WL 936633, 2012 U.S. Claims LEXIS 252 (uscfc 2012).

Opinion

ORDER

ALLEGRA, Judge:

In this preaward bid protest case, the General Services Administration (GSA) awarded a contract to Emerald Corporate Center, LCC (ECC or defendant-intervenor) for the construction and lease of a new campus for the Federal Bureau of Investigations (FBI) in Boston, Massachusetts. After Boston Harbor Development Partners (Boston Harbor or plaintiff) protested this award with the General Accountability Office (GAO), GSA indicated that it would take corrective action and GAO dismissed the appeal. But, that corrective action did not include terminating the lease that GSA had entered into with ECC as part of the protested procurement. Plaintiff complains that GSA’s failure to cancel the lease will bias the agency’s evaluators toward awarding ECC the contract again and, in a proposed solution to this problem, seeks a declaration that the lease is void. The United States and ECC have moved to dismiss this protest under RCFC 12(b)(1) for lack of jurisdiction, asserting, inter alia, that Boston Harbor lacks standing. For the reasons that follow, the court GRANTS these motions.2

I. Background

To meet the FBI’s need for additional space, on April 7, 2008, GSA published a [501]*501Request for Expression of Interest for the construction and lease of a new FBI campus in the Boston, Massachusetts area. Several parties responded. The FBI evaluated the security of each of the seven proposed locations and found that five met its requirements — these included sites proposed by ECC and Boston Harbor. On July 28, 2008, GSA issued Phase I Solicitation for Offers (SFO) No. 2818A to the representatives of the approved sites, seeking a “dedicated campus facility for the” FBI. Of the five offerors invited to bid, only three submitted proposals — ECC, Boston Harbor, and a third company. GSA’s Source Selection Evaluation Board (SSEB) evaluated these proposals and visited each of the offered sites to determine if they satisfied the SFO’s requirements. Following this evaluation, ECC received an overall score that was slightly higher than that given to Boston Harbor.

On January 15, 2009, GSA distributed Phase II SFO No. 2818A to the three Phase I offerors, requiring the offerors to submit price and technical proposals; only ECC and Boston Harbor submitted Phase II proposals. The Phase II SFO stated that the government would “select for award the proposal that satisfies all of the minimum requirements set forth in the SFO and, consistent with the Phase II technical evaluation factors, represents the best overall value to the Government.” The Phase II proposals were evaluated by a five person SSEB, which identified issues for clarification in both proposals. From November 2009 to April 2010, GSA conducted discussions with both offerors and received a series of proposal revisions, ultimately leading to each offeror submitting a final proposal. The SSEB reviewed the final proposals and, on November 10, 2010, concluded that ECC’s proposal represented the best value to the government based on its higher Phase I and II scores, as well as its lower price. On December 1, 2010, Boston Harbor received notice that GSA had selected ECC’s proposal.

On December 3, 2010, Boston Harbor protested the award to GAO, alleging that certain errors and illegalities had led GSA to select ECC. On December 10, 2010, Boston Harbor filed a supplemental protest. Among the allegations in this protest, plaintiff claimed that: (i) ECC’s proposal should have been scored as a capital lease (rather than as an operating lease); (ii) GSA incorrectly calculated the present value of ECC’s proposal in its price analysis; and (iii) ECC’s proposed site did not meet the minimum requirements of the solicitation and thus was ineligible for the award. On December 21, 2010, GSA notified GAO that it had identified an error in its present value calculations and intended to recalculate the present value of the proposed sites and assign revised Phase II scores. Two days later, GAO dismissed Boston Harbor’s protest as moot.

Subsequently, GSA’s head of contracting activity appointed a new SSEB to conduct a de novo evaluation of the Phase II offers, and also replaced the contracting officer and source selection authority (SSA) that were to make the new award decision. After the Phase II reevaluation, both offerors’ technical scores were lower, but Boston Harbor’s score fell dramatically, leaving a much greater gap between its technical score and that of ECC. While the recalculated present values resulted in a much smaller gap between the price of the two proposals, ECC’s proposal remained the less expensive option. The new SSEB recommended that ECC’s proposal be accepted, and the new SSA agreed that ECC’s proposal represented the best value to the government. Based on this determination, on September 23, 2011, GSA executed a formal lease with ECC; that lease did not contain a termination for convenience clause.

On September 26, 2011, GSA notified plaintiff that ECC had been selected again for the award. On October 6, 2011, plaintiff protested the second award to GAO, raising allegations nearly identical to those presented in its first protest. On November 18, 2011, GSA filed a notice of corrective action, stating that it “will re-evaluate the Phase I offers and Phase II as necessary as a result of the Phase I evaluations” and “scrutinize its price evaluations.” On November 21, 2011, plaintiff opposed dismissal of its second protest due to fears the outstanding lease with ECC would bias GSA’s reevaluation. But, that same day, GSA assured GAO that [502]*502“the agency will abide by the outcome of the new evaluation, notwithstanding any implications for the agency of doing so.” On November 22, 2011, GAO dismissed plaintiffs second protest as “academic” in light of GSA’s proposed corrective action.

On December 9, 2011, plaintiff filed a complaint in this court asking that, prior to GSA’s reevaluation of the two proposals, the lease be declared illegal and void ab initio. On December 15, the court granted ECC’s motion to intervene. On January 18, 2012, plaintiff filed its motion for judgment on the administrative record. On January 31, 2012, defendant and defendant-intervenor filed motions to dismiss plaintiffs complaint under RCFC 12(b)(1) and, alternatively, cross-motions for judgment on the administrative record. Briefing of these motions was completed on February 14, 2012, and oral argument was held February 21, 2012.

II. DISCUSSION

In its motion for judgment on the administrative record, plaintiff contends that the existing lease between GSA and ECC creates strong financial incentives for GSA to award the contract to ECC a third time, depriving plaintiff of the opportunity to compete on a level playing field. For their part, defendant and defendant-intervenor argue that this court lacks jurisdiction over plaintiffs complaint, for a variety of reasons, among them that plaintiff lacks standing. In that regard, defendant and defendant-intervenor argue that plaintiff is merely speculating as to how the agency will approach the reprocurement here and has not alleged an injury that can be addressed through judicial relief.

Deciding a motion to dismiss “starts with the complaint, which must be well-pleaded in that it must state the necessary elements of the plaintiffs claim, independent of any defense that may be interposed.” Holley v. United States, 124 F.3d 1462, 1465 (Fed.Cir.1997);

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Progressive Industries, Inc. v. United States
129 Fed. Cl. 457 (Federal Claims, 2016)
Omran Holding Group v. United States
128 Fed. Cl. 273 (Federal Claims, 2016)
Square One Armoring Service, Inc. v. United States
123 Fed. Cl. 309 (Federal Claims, 2015)
Reema Consulting Services, Inc. v. United States
107 Fed. Cl. 519 (Federal Claims, 2012)
International Genomics Consortium v. United States
104 Fed. Cl. 669 (Federal Claims, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
103 Fed. Cl. 499, 2012 WL 936633, 2012 U.S. Claims LEXIS 252, Counsel Stack Legal Research, https://law.counselstack.com/opinion/boston-harbor-development-partners-llc-v-united-states-uscfc-2012.