Boise Cascade Corp. v. Reliance National Indemnity Co.

129 F. Supp. 2d 41, 2001 U.S. Dist. LEXIS 4054, 2001 WL 92378
CourtDistrict Court, D. Maine
DecidedFebruary 2, 2001
DocketCivil 98-258-PC
StatusPublished
Cited by1 cases

This text of 129 F. Supp. 2d 41 (Boise Cascade Corp. v. Reliance National Indemnity Co.) is published on Counsel Stack Legal Research, covering District Court, D. Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Boise Cascade Corp. v. Reliance National Indemnity Co., 129 F. Supp. 2d 41, 2001 U.S. Dist. LEXIS 4054, 2001 WL 92378 (D. Me. 2001).

Opinion

MEMORANDUM OF DECISION AND ORDER

GENE CARTER, District Judge.

This case arises out of a prior lawsuit brought against Boise Cascade Corporation (“Boise”) by four Koch-Glitsch, Inc. (f/k/a Koch Engineering Company, Inc. and hereinafter “Koch”) 1 employees who were injured at Boise’s paper mill in Rum-ford, Maine while performing work under *43 a contract between Boise and Koch. That personal injury case was settled before trial. In the present action, Boise has sued Koch and Reliance National Insurance Company (“Reliance”), claiming that both entities breached their contracts with Boise by declining to defend Boise and by refusing to reimburse Boise for the defense costs and settlement amounts in the lawsuits brought by the injured Koch employees. The Court previously granted summary judgment for Koch on Boise’s claims against Koch. See Memorandum of Decision and Order (Docket No. 56). After the Court’s summary judgment ruling, two claims were left to be resolved at trial: Boise’s claim against Reliance and a counterclaim filed by Koch against Boise. The remaining claim from Boise’s Complaint asserts that Reliance breached its contractual obligations under the insurance policy and that, as a result, Boise is entitled to recover from Reliance its defense costs and the settlement payments made in connection with the injured Koch employees’ suits. Rebanee responds that it had no duty to defend or reimburse Boise. Koch’s counterclaim against Boise asserts entitlement to recover attorneys’ fees and costs incurred in connection with this action by Boise. 2 After a nonjury trial, the Court makes the following findings of fact and conclusions of law.

FACTS

There was bttle dispute about the facts presented at the one-day trial. The evidence established that on June 28, 1995, Stephen Clarke, a Koch representative, provided Boise with a quote for the annual inspection and repair of some tile-lined tanks at the Boise mib. Trial Ex. 27. Koch’s written estimate was for $263,700, with additional line items for work on the “E/O Washer” and the “Blend Chest” at an estimated cost of $8,750 and $19,200, respectively. Since the quote was based on estimated time and materials, Koch also included a price schedule for time, materials, and equipment necessary to complete the work in excess of the quotation. Id. The written quote stated: “The attached Field Service Group Standard Terms and Conditions are made part of this proposal” (“the Koch standard terms”). Id. Koch’s standard terms were included with the quote as a separate document. In addition to the quote, Clarke completed and signed a Boise “Contractor Bid Form.” Id.

In response to Koch’s quote, on August 1,1995, Anthony Koris, a purchasing agent for Boise, completed, signed, and sent a purchase order to Koch for the inspection and repair of the tanks. Trial Ex. 101. The purchase order referenced the “pricing in [Koch’s] proposal” and included Boise’s standard terms and conditions (“the Boise standard terms”) on the back side of the purchase order. Id. On August 7, 1995, Clarke signed the acknowledgment copy of Boise’s purchase order. Next to Clarke’s signature on the purchase order was the language “I (WE) _ hereby accept this PURCHASE ORDER solely on the Terms & Conditions set forth herein.” Id. In addition to signing his name on the acknowledgment purchase order, Clarke wrote the words “Knight/Ballard KECI [Koch Engineering Company, Incorporated]” in the blank space provided. Id. Along with the signed acknowledgment purchase order, Clarke sent Boise a cover letter which stated that “THE ACCEPTANCE OF THIS PURCHASE ORDER IS BASED ON THE ATTACHED TERMS AND CONDITIONS” of Koch. Trial Ex. 11. 3 The testimony at trial established that the representatives of Boise and Koch never *44 discussed whose terms would control the contract.

DISCUSSION

Both Boise’s remaining claim against Rebanee and Koch’s counterclaim against Boise turn, in part, on the question as to whether Boise’s terms or Koch’s terms control the contract between Boise and Koch. The Court wib first resolve this issue. The Court will then be able to address Boise’s breach of contract claim against Reliance. Finally, the Court will consider whether Koch is entitled to recover attorneys’ fees under its counterclaim.

A. Terms of the Contract

It is agreed that the Koch employees were to inspect and repair some tanks at the Boise mill pursuant to a contract. The parties, however, hold differing views on whose terms control the contract. It is asserted by Koch and Reliance that Koch’s standard terms control the contract and, thus, that Reliance did not have a duty to name Boise as an additional insured. On the other hand, Boise asserts that its standard terms control and, thus, that Reliance did have a duty to defend and indemnify Boise in the suit brought by the injured Koch employees.

Koch and Reliance proffer two circumstances whereby Koch’s standard terms apply. Both theories depend upon Koch’s June 28th proposal being a valid offer. First, Koch argues that Boise orally accepted its offer. Second, Koch asserts that its offer was accepted when Boise sent its purchase order that expressly referenced Koch’s price quotation to Koch. Therefore, Koch and Reliance argue that Koch’s standard terms control the contract and Koch had no duty to name Boise as an additional insured. Boise asserts that its standard terms apply because Koch signed its purchase order and thereby explicitly agreed to be bound by Boise’s standard terms.

Koch’s June 28th proposal was a price quotation and the Court finds that it did not constitute an offer. As the Court previously stated in its summary judgment decision, estimates are typically not treated as offers, but, instead, they are usually understood to be an invitation to offer or the initiation of negotiation. See 17A Am. Jur.2d Contracts § 45. Under some circumstances, however, an estimate can serve as an offer, creating in the recipient the power of acceptance. Id. But to treat an estimate as an offer, the language of the estimate, and the context of the estimate in the negotiations between the parties, “must be so definite as to constitute a clear meeting of the minds.” Taft-Peirce Mfg. Co. v. Seagate Technology, Inc., 789 F.Supp. 1220, 1223 (D.R.I.1992). “[Wjhether a price quote may be considered an offer in any given case is a question of fact dependent on the nature of the particular acts or conduct and the circumstances surrounding the transaction.” Maurice Elec. Supply Co., Inc. v. Anderson Safeway Guard Rail Corp., 632 F.Supp. 1082, 1087 (D.D.C.1986). Based on the testimony at trial and its review of the June 28th proposal, the Court finds that the language and context of the proposal did not render it an offer.

Koch argues that its price quotation was the offer and relies on a number of cases for support of its argument that its price quote was an offer. All of those cases are distinguishable because none of the cases involve a situation in which both contracting parties sign a singular document.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
129 F. Supp. 2d 41, 2001 U.S. Dist. LEXIS 4054, 2001 WL 92378, Counsel Stack Legal Research, https://law.counselstack.com/opinion/boise-cascade-corp-v-reliance-national-indemnity-co-med-2001.