Asic II Ltd. v. Stonhard, Inc.

63 F. Supp. 2d 85, 1999 U.S. Dist. LEXIS 14567, 1999 WL 728278
CourtDistrict Court, D. Maine
DecidedSeptember 6, 1999
DocketCiv. 97-204-P-C
StatusPublished
Cited by23 cases

This text of 63 F. Supp. 2d 85 (Asic II Ltd. v. Stonhard, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Asic II Ltd. v. Stonhard, Inc., 63 F. Supp. 2d 85, 1999 U.S. Dist. LEXIS 14567, 1999 WL 728278 (D. Me. 1999).

Opinion

MEMORANDUM OF DECISION AND ORDER

GENE CARTER, District Judge.

Plaintiff ASIC II Limited (“ASIC II”) and Defendant Stonhard, Inc. (“Stonhard”) have submitted this case to the Court for decision on a Stipulated Record (“SR”). 1 See Docket No. 49. National Semiconductor Corporation (“NSC”) is a manufacturer of “semiconductor wafers” which owns and operates a manufacturing facility located at 333 Warren Avenue in South Portland, Maine. SR ¶2. In May of 1993, NSC entered into a Construction Management Contract with CMPA, Inc., (“CMPA”) to have it serve as the construction manager for the building of NSC’s three-story addition to its manufacturing facility in South Portland. 2 SR ¶¶ 9-10; Ex. 36. This new addition will be referred to as “Building 17.” SR ¶ 8. NSC later entered into a contract with Stonhard pursuant to which *87 Stonhard agreed to furnish and install a chemical-resistant floor coating system in Building 17, then under construction. SR ¶11.

On the morning of February 5, 1994, a fire occurred on the construction site of Building 17 in the location of a temporary platform where Stonhard had placed boxes of chemical sealant materials. SR ¶ 18. The fire caused damage to the Building 17 construction project, predominantly in the form of heavy smoke damage. SR ¶ 19. The fire and smoke damage to Building 17 in the amount of $500,911 proximately resulted from Stonhard’s conduct in handling and storing its floor coating chemicals, which conduct constitutes negligence and breach of contract as alleged in Counts I and II of Plaintiffs Complaint. 3 SR ¶ 1.

For the period from April 1, 1992, through April 1, 1995, Industrial Risk Insurers (“IRI”) was NSC’s direct casualty insurer under Policy No. 31-3-57327, captioned “Worldwide Property Insurance Policy.” 4 SR ¶ 3; Exhibit 76. ASIC II is the successor corporation to ASIC Limited Reinsurance Corporation, which was the reinsurer of the risks described in the IRI policy covering the NSC location in issue. 5 SR ¶ 5. The damages of $500,911 were covered by the IRI policy, subject to a $100,000 deductible which was the responsibility of NSC. SR ¶ 23; Ex. 76. For the purposes of this action, ASIC II stands in the shoes of NSC, with respect to NSC’s rights to initiate legal action against the party or parties responsible for the loss. 6 SR ¶ 7.

Because Stonhard has admitted liability on Count I for negligence and Count II for breach of contract, the only issue before the Court for decision is the applicability of Stonhard’s affirmative defense that the action is barred by the doctrine of waiver of subrogation. See Amended Answer (Docket No. 36). The Court concludes that the waiver provision in the General Conditions of the contract between Ston-hard and NSC is applicable and bars this action.

I. FACTS

From the stipulated record, the events which led up to the formation of a contract to supply and install a floor coating in Building 17 are as follows. On November 23, 1993, CMP A, sent Michael Bisson, project engineer at Stonhard, a document entitled “Invitation to Bid” for the installation of floor coating. Affidavit of Michael Bisson (Docket No. 50) at ¶ 3. The Invitation to Bid included the designation “Bid Package No. 707-1.11-09705-Floor Coating” (“bid package”) and included the following materials: a cover letter dated *88 November 23, 1993, from John Burrus at CMPA to Michael Bisson at Stonhard, a “Proposal Form,” a “Lump Sum Contract — Short Form,” 20 pages of “Job Procedures,” and 29 pages of “General Conditions.” Ex. 1. In the section entitled General Conditions, ¶ 6.5(B) provides for waiver between the owner and the contractor for damages caused by fire. Ex. 1, General Conditions ¶ 6.5(B). Mr. Bis-son discussed the bid package with several people at Stonhard in the course of preparing to bid on the job. Bisson Aff. ¶ 4. Mr. Bisson specifically discussed with Don Sampson, a District Manager at Stonhard, some of the General Conditions of the bid proposal, including section 6.7, referencing the contractor’s obligation to insure against “fire and other risks included in its standard extended coverage endorsement.” Bisson Aff. ¶ 4. Mr. Bisson asserts that Stonhard does not provide such coverage and, accordingly, in its proposal Stonhard did not include property insurance as part of the bid. Bisson Aff. ¶ 4.

On December 3, 1993, Mr. Bisson delivered to Bobby Adams, Project Manager at CMPA, a letter proposal with Stonhard’s product recommendation dated December 2 and NSC’s bid package Proposal Form signed and dated December 3. Bisson Aff. at ¶5; Exs. 3 and 4. Included in Ston-hard’s letter proposal were provisions delineating the scope of work, a price quotation of $79,850, a warranty, the contractual terms and conditions it was proposing, and a customer satisfaction commitment. Ex. 3. The terms and conditions section states, in part, “[t]he enclosed General Terms and Conditions are a part of this proposal and shall apply to a resulting purchase order or contract.” Ex. 3 at 2. The next page attached to the letter proposal laid out the “General, Terms and Conditions” providing that “[u]pon request by the Customer, Stonhard will furnish certificates of Workman’s Compensation Insurance and Liability Insurance.” Ex. 3, General Terms and Conditions ¶ lc. The General Terms and Conditions from Stonhard’s letter proposal do not include a provision waiving rights to recover for damage due to fire and it affirmatively provides that “[t]his Agreement shall constitute the entire Agreement between the parties and the parties acknowledge that there are no other verbal or written Agreements, understandings or customs affecting the Agreement.” Ex. 3, General Terms and Conditions ¶ 7.

The bid “Proposal Form” submitted by Stonhard included only some of the pages from the original bid package Proposal Form sent to Stonhard from CMPA. Compare Exs. 1 and 4. Notably missing are portions of the bid package “Proposal Form” including the promise on page 7 to provide certificates of insurance for all the coverages required by the proposed General Conditions. 7 Compare Exs. 1 and 4. Stonhard filled out the Proposal Form with the total contract price being $79,850, the same price quote Stonhard submitted in its letter proposal. The Proposal Form, however, included a provision that Ston-hard “proposes to ... [t]he General Conditions ... will become part of the Contract Agreement with NSC Corporation.” Ex. 4. The “Proposal Form” was signed by Mr. Bisson as representative of Stonhard. Ex. 4. Many of the terms of the General Conditions from NSC’s bid package “Proposal Form” are at variance with the General Terms and Conditions found in Stonhard’s letter proposal.

On or about December 7, 1993, Mr. Bis-son met with Ken Baker of NSC, Bobby Adams, Project Manager at CMPA, and Eric Breiner, Product Engineer at Ston-hard, at CMPA’s office to discuss the floor coating aspect of the project. Bisson Aff. ¶ 6. Messrs.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Empress Casino Joliet Corp v. W. E. O'Neil Construction Co.
2016 IL App (1st) 151166 (Appellate Court of Illinois, 2016)
Empress Casino Joliet Corporation v. W.E. O'n Neil Construction Co.
2016 IL App (1st) 151166 (Appellate Court of Illinois, 2016)
Board of Commissioners v. Teton Corp.
30 N.E.3d 711 (Indiana Supreme Court, 2015)
Hemingway v. Construction By Design Corporation
2015 UT App 10 (Court of Appeals of Utah, 2015)
Board of Commissioners v. Teton Corp.
3 N.E.3d 556 (Indiana Court of Appeals, 2014)
Westfield Ins. Group v. Affinia Dev., L.L.C.
2012 Ohio 5348 (Ohio Court of Appeals, 2012)
Copper Mountain, Inc. v. Industrial Systems, Inc.
209 P.3d 1103 (Colorado Court of Appeals, 2009)
Copper Mountain, Inc. v. Industrial Systems, Inc.
208 P.3d 692 (Supreme Court of Colorado, 2009)
LEXINGTON INSURANCE COMPANY v. Entrex Communication Services, Inc.
749 N.W.2d 124 (Nebraska Supreme Court, 2008)
Walker Engineering, Inc. v. Bracebridge Corp.
102 S.W.3d 837 (Court of Appeals of Texas, 2003)
Trinity Universal Insurance Co. v. Bill Cox Construction, Inc.
75 S.W.3d 6 (Court of Appeals of Texas, 2002)
Eslon Thermoplastics v. Dynamic Systems, Inc.
49 S.W.3d 891 (Court of Appeals of Texas, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
63 F. Supp. 2d 85, 1999 U.S. Dist. LEXIS 14567, 1999 WL 728278, Counsel Stack Legal Research, https://law.counselstack.com/opinion/asic-ii-ltd-v-stonhard-inc-med-1999.