Biemann and Rowell Co. v. the Donohoe Companies, Inc.

2000 NCBC 8
CourtNorth Carolina Business Court
DecidedJune 5, 2000
Docket99-CVS-9132
StatusPublished

This text of 2000 NCBC 8 (Biemann and Rowell Co. v. the Donohoe Companies, Inc.) is published on Counsel Stack Legal Research, covering North Carolina Business Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Biemann and Rowell Co. v. the Donohoe Companies, Inc., 2000 NCBC 8 (N.C. Super. Ct. 2000).

Opinion

BIEMANN AND ROWELL CO. v. THE DONAHOE COMPANIES, INC., 2000 NCBC 8

STATE OF NORTH CAROLINA IN THE GENERAL COURT OF JUSTICE SUPERIOR COURT DIVISION COUNTY OF GUILFORD 99-CVS-9132

BIEMANN AND ROWELL COMPANY, ) ) Plaintiff, ) ) v. ) ) ORDER AND JUDGMENT THE DONOHOE COMPANIES, INC., ) D/B/A DONOHOE CONSTRUCTION ) COMPANY, ) ) Defendant. )

{1} On November 15, 1999, this matter came on for trial before the undersigned without a jury based upon the submissions of the parties. The Court, having heard the evidence, makes the Findings of Fact and Conclusions

of Law set forth below. Judgment on all claims is entered in favor of Defendant The Donohoe Companies,

Inc. (“Donohoe”). Central to the resolution of this case is the determination of the proper procedures to be

followed by co-primes under state contracts when claims arise against each other during the course of the project. Erwin and Bernhardt, P.A., by Fenton T. Erwin, Jr., for Plaintiff Biemann and Rowell Company.

Safran Law Offices, by Perry R. Safran, for Defendant The Donohoe Companies, Inc.

Findings of Fact {2} Plaintiff, Biemann and Rowell Company (“Biemann and Rowell”), is a corporation duly organized under the laws of the state of North Carolina. Defendant, Donohoe Construction Company (“Donohoe”), is a

corporation duly organized under the laws of the State of Delaware which conducts business in North Carolina. This case arises out of the construction of the University of North Carolina Neuropsychiatric Hospital in Chapel Hill, North Carolina (“Neuropsych”). The construction of Neuropsych was a multi-million

dollar project. By statute in North Carolina, when the cost of a building project is over $500,000, the State employs multiple prime contractors. Four separate contractors were employed on the Neuropsych project to

perform the heating, ventilating and air conditioning (“HVAC”) work, the plumbing and gas fitting work, the electrical wiring and installation work, and the general work relating to the erection of the building. {3} Biemann and Rowell submitted an aggressive bid to UNC Hospitals (“Owner”) in the amount of

$3,515,900 for the HVAC work on the Neuropsych project. On or about July 1, 1992, Biemann and Rowell and Donohoe entered into separate contracts with the Owner to serve as the mechanical contractor and general contractor, respectively, for the construction of Neuropsych. Wayne J. Griffin Electric, Inc. was the electrical

prime contractor and Bell BCI Company was awarded the plumbing contract. The architect on the Neuropsych project was HKS Architects, Inc. (“Architect”). {4} Donohoe, as General Contractor, was to assume the role of Project Expediter. Article 14 of the General Conditions of the contract provided that the Project Expediter had the following responsibilities: (1) schedule the work of all Contractors; (2) maintain a project progress schedule for all Contractors and revise the schedule as needed; (3) give adequate notice to all Contractors of time frames critical to the job progress to insure efficient continuity of all phases of the work; and (4) notify the Architect of any changes in the project schedule. {5} The Supplementary General Conditions to the project contract removed some of the scheduling responsibilities from the Project Expediter and instead placed them with the Schedule Coordinator. Alternate G-5 in the contract indicated that Donohoe was to employ HICAPS as a CPM Schedule Coordinator. Change order G-8, issued by the Owner and effective October 6, 1993, approved proposed change order 60 and directed that the CPM Schedule Coordinator would be employed directly by UNC and would be changed to The Milestone Group in lieu of HICAPS. {6} As project expediter, Donohoe had poorly defined responsibilities. Although Milestone relieved Donohoe

of the responsibility for developing the original CPM schedule, Donohoe remained responsible for “maintain[ing] the progress schedule, making monthly adjustments, updates, corrections, etc. that [were]

necessary, keeping all Contractors and the [Architect] fully informed.” (Pl. Ex. 1, Article 14(j).) Thus, while

Milestone assumed the role of coordinator in assimilating information obtained from the co-primes, Donohoe had a more active responsibility for communication on the project between co-primes and for the proposal of

any necessary adjustments to the schedule. Donohoe had no power or leverage as expediter. Under the

contract, the leverage remained with the Owner. Donohoe’s real impact on the job was the result of its

position as general contractor. {7} According to Article 18, the Architect was charged with the responsibility of interpreting the contract

documents. Thus, the Architect had the authority to find Donohoe in violation of the contract. On several

occasions, the Architect reminded Donohoe of its obligations as project expediter. In fact, on at least one occasion the Architect warned Donohoe that it was ignoring its contract responsibilities by failing to make

needed adjustments and updates to the schedule.

{8} Milestone, as Schedule Coordinator, was responsible for developing a Critical Path Method progress schedule. The Critical Path Method (CPM) of scheduling construction work utilizes a flow chart showing the

sequence of the work to be performed. Milestone developed the CPM schedule based on information provided

by the co-primes. The original project CPM schedule was approved by all parties on December 18, 1992, and provided for completion of the project within 1004 days of the Notice to Proceed which was issued on August

17, 1992.

{9} Scheduling on the Neuropsych project was largely a mechanical function. Each prime contractor was responsible for scheduling its work activities in accordance with the critical path. Milestone received

information from the primes on their progress and updated the project schedule accordingly. If a prime

contractor was causing the project to fall behind the critical path, Milestone sent the contractor written notification of actual or potential delays.

{10} In addition to preparing the critical path for the project, Milestone was responsible for monitoring work and

for updating the schedule every two weeks. Article 57 of the Supplementary Conditions required Milestone to monitor the work on the project through weekly coordination meetings with “appropriate representatives of

Contractor(s), the Owner, the Architect and designed [sic] subcontractors.” In addition, weekly meetings with

the project foremen were held, providing an opportunity for the prime contractors to discuss the progress of the project and to raise concerns about delays. {11} The project documents outlined the duties of co-prime contractors. Specifically, the co-prime contractors were required to cooperate and consult with each other during construction. Each contractor was to execute his work so as to cause the least amount of delay to the other contractors. Each contractor was to be responsible for any damage to the other contractors’ work and each contractor was to be financially responsible to the other contractors for undue delay caused by him. {12} The contract also provided that if any part of the contractor’s work depended upon the work of another contractor, defects which might affect that work should be reported to the Architect in order that prompt inspection might be made and the defects corrected. Commencement of work by a contractor where such condition existed was to constitute acceptance of the other contractor’s work as being satisfactory in all respects, except as to defects which might later develop. The Architect was designated the judge of the quality of work and was responsible for settling all disputes between contractors on the project.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

New Pueblo Constructors, Inc. v. State
696 P.2d 185 (Arizona Supreme Court, 1985)
Southern Box and Lumber Co. v. Home Chair Co.
108 S.E.2d 70 (Supreme Court of North Carolina, 1959)
Bolton Corp. v. T. A. Loving Co.
380 S.E.2d 796 (Court of Appeals of North Carolina, 1989)
Rose v. Vulcan Materials Company
194 S.E.2d 521 (Supreme Court of North Carolina, 1973)
Roger J. Au & Son, Inc. v. Northeast Ohio Regional Sewer District
504 N.E.2d 1209 (Ohio Court of Appeals, 1986)
Youngdale & Sons Construction Co. v. United States
38 Cont. Cas. Fed. 76,467 (Federal Claims, 1993)
Mega Construction Co. v. United States
39 Cont. Cas. Fed. 76,564 (Federal Claims, 1993)
Neal & Co. v. United States
41 Cont. Cas. Fed. 77,003 (Federal Claims, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
2000 NCBC 8, Counsel Stack Legal Research, https://law.counselstack.com/opinion/biemann-and-rowell-co-v-the-donohoe-companies-inc-ncbizct-2000.