Bechtel Do Brasil Construções Ltda. v. UEG Araucária Ltda.

638 F.3d 150, 2011 WL 982330
CourtCourt of Appeals for the Second Circuit
DecidedMarch 22, 2011
Docket10-341
StatusPublished
Cited by17 cases

This text of 638 F.3d 150 (Bechtel Do Brasil Construções Ltda. v. UEG Araucária Ltda.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bechtel Do Brasil Construções Ltda. v. UEG Araucária Ltda., 638 F.3d 150, 2011 WL 982330 (2d Cir. 2011).

Opinion

GERARD E. LYNCH, Circuit Judge:

Plaintiffs Bechtel do Brasil, Bechtel Canada, and Bechtel International filed this action seeking to stay arbitration in connection with defendant UEG Araucária’s claims of breach of contract, negligence and fraud. Plaintiffs contended that defendant’s claims were barred by the applicable statute of limitations. Defendant responded that matters of timeliness were for the arbitrator to decide and that, in any event, its claims were timely. The United States District Court for the Southern District of New York (Barbara S. Jones, Judge) concluded that plaintiffs’ statute of limitations claims were not governed by the parties’ arbitration agreement, that the applicable limitations period had run, and that a permanent stay of arbitration was therefore warranted.

We hold that the district court erred in concluding that the parties’ contracts left the power to determine the timeliness issue to the courts. Accordingly, we reverse the judgment of the district court and remand the case for proceedings consistent with this opinion.

BACKGROUND

In 2000, UEG Araucária Ltda. (“UEGA”), a Brazilian entity, entered into *152 a series of contracts with Bechtel Do Brasil Construgóes Ltda., Bechtel Canada Co., and Bechtel International, Inc. (collectively, “Bechtel”) for services associated with the construction of a power plant in Araucaria, Brazil. The total agreement, worth approximately $210 million, required Bechtel to engineer and construct a 469-mega-watt, gas-turbine generating station as well as to conduct the required performance testing, so that the facility would be ready for operation on the day that UEGA took delivery.

The agreement was memorialized in four documents — the “Site Construction Contract,” the “Equipment Supply Contract,” the “Services Contract,” and the “Umbrella Agreement.” Each of the three “contracts” contained an identical Arbitration provision. 1 That provision states:

37.2 Arbitration
Any dispute, controversy, or claim arising out of or relating to the Contract, or the breach, termination or validity thereof ... shall be finally settled by arbitration in accordance with the Rules of Conciliation and Arbitration of the International Chamber of Commerce (the “ICC”) then in effect (the “Rules”), except as these rules my be modified herein....
37.2.2
Any arbitration proceeding or award rendered hereunder and the validity, effect and interpretation of this agreement to arbitrate shall be governed by the laws of the state of New York.

Each contract also included an identical “Law and Procedure” section, which provides, in relevant part:

39.1.1 Governing Law
The law which is to apply to the Contract and under which the Contract is to be construed is the law of the state of New York without regard to the jurisdiction’s conflicts of laws rules____
39.1.2 Procedural Law
The law governing the procedure and administration of any arbitration instituted pursuant to Clause 37 is the law of the State of New York.

On September 16, 2002, Bechtel informed UEGA by letter that it had completed mechanical work on the plant and would begin the performance testing that was contractually required before formal delivery could occur. This testing began on September 18, 2002 and was completed on September 26, 2002. The next day, UEGA certified its acceptance of the plant.

For reasons unrelated to this lawsuit, UEGA did not begin operating the plant until December 2006, more than four years after it accepted delivery from Bechtel. Just over a year later, on January 13, 2008, the plant’s steam-turbine generator failed. UEGA asserts that this failure was due to “deficiencies in the structural integrity of the lug welds” that Bechtel or its subcontractors should have discovered during the construction and testing of the plant in 2002.

On September 29, 2008, UEGA filed a Request for Arbitration before the International Chamber of Commerce (“ICC”) claiming breach of contract, negligence, and fraud in connection with alleged defects in the steam plant. UEGA later amended this request to add a claim for negligent misrepresentation.

Bechtel responded by filing this action in the Supreme Court for the State of New York seeking a permanent stay of arbitration on the grounds that UEGA’s claims were time-barred under both New York and Brazilian law. Notwithstanding the parties’ agreement to arbitrate, Bechtel *153 invoked the jurisdiction of the Supreme Court pursuant to section 7502(b) of the New York Civil Practice Law and Rules, which states:

If, at the time that a demand for arbitration was made or notice of intention to arbitrate was served, the claim sought to be arbitrated would have been barred by limitation of time had it been asserted in a court of the state, a party may assert the limitation as a bar to the arbitration on an application to the court....

On Bechtel’s view, the statute of limitations governing UEGA’s contract claims began to run from the date of mechanical completion. As such, even under the most generous of the potentially applicable limitations periods — six years for common law breach of contract in New York — the window for claims would have closed on September 16, 2008.

UEGA removed the case to federal district court and filed a counter-application to compel arbitration. Responding to Bechtel’s assertion that any claims under the contract were time-barred, UEGA asserted that the relevant date from which to calculate the limitations period was September 27, 2002, the date upon which it formally accepted delivery of the facility. Because September 27, 2008 fell on a Saturday, UEGA’s request for arbitration, filed on September 29, would therefore be timely under New York law. UEGA further argued that its claims were not time-barred, even if New York’s borrowing statute would apply Brazil’s three-year statute of limitations. See N.Y. C.P.L.R. 202 (limiting the limitations period for causes of action accruing outside of New York where the foreign jurisdiction imposes a shorter statute of limitations than the state does). Under UEGA’s interpretation of Brazilian law, that country’s limitations period began to run only upon discovery of the defects in the steam plant. UEGA had therefore brought its claims with time to spare. Finally, UEGA maintained that any issue as to the timeliness of its claims was a matter for the arbitrator to decide.

In a written order granting a temporary stay of arbitration, the district court rejected UEGA’s assertion that the issue of timeliness was reserved for the arbitrator. The court acknowledged that “[t]he federal policy in favor of arbitration requires that any doubts concerning the scope of arbitrable issues be resolved in favor of arbitration.” Bechtel Do Brasil Construções Ltda., et al. v. UEG Araucária Ltda., No. 09-cv-6417, at 3 (S.D.N.Y. Nov. 16, 2009).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ibrahim v. Nassau County
E.D. New York, 2025
Vasell v. SeatGeek, Inc.
E.D. New York, 2025
In Re: Celsius Network LLC
S.D. New York, 2024
Hermes v. Swain
Second Circuit, 2021
Nicosia v. Amazon.com, Inc.
384 F. Supp. 3d 254 (E.D. New York, 2019)
Harris v. TD Ameritrade Inc.
338 F. Supp. 3d 170 (S.D. Illinois, 2018)
Conte v. Blossom Homes, L.L.C.
2016 Ohio 7480 (Ohio Court of Appeals, 2016)
Ameriprise Financial Services, Inc. v. Beland
672 F.3d 113 (Second Circuit, 2011)
Pallares v. Kohn
650 F.3d 276 (Third Circuit, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
638 F.3d 150, 2011 WL 982330, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bechtel-do-brasil-construcoes-ltda-v-ueg-araucaria-ltda-ca2-2011.