Diamond Waterproofing Systems, Inc. v. 55 Liberty Owners Corp.

826 N.E.2d 802, 4 N.Y.3d 247, 793 N.Y.S.2d 831, 2005 N.Y. LEXIS 446
CourtNew York Court of Appeals
DecidedMarch 24, 2005
StatusPublished
Cited by68 cases

This text of 826 N.E.2d 802 (Diamond Waterproofing Systems, Inc. v. 55 Liberty Owners Corp.) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Diamond Waterproofing Systems, Inc. v. 55 Liberty Owners Corp., 826 N.E.2d 802, 4 N.Y.3d 247, 793 N.Y.S.2d 831, 2005 N.Y. LEXIS 446 (N.Y. 2005).

Opinion

*250 OPINION OF THE COURT

Ciparick, J.

On this appeal, the issues presented are whether the Federal Arbitration Act (9 USC § 1 et seq. [FAA]) governs the parties’ contract dispute and, if so, whether the question as to the timeliness of the subject arbitration demand is an issue for the arbitrator or the courts. We conclude that the FAA is applicable here as the contract had an effect on interstate commerce. We further conclude that the timeliness question and all other related questions are for the arbitrator to determine because the contract’s choice of law provision does not provide that New York law shall govern the enforcement of the parties’ agreement.

I.

Petitioner Diamond Waterproofing Systems, Inc. (Diamond Systems) is a corporation primarily engaged in the business of waterproofing, masonry and related trades. Respondent 55 Liberty Owners Corp. is a cooperative that owns a nationally land-marked residential building located in Manhattan. On May 5, 1995, these parties entered into a contract pursuant to which Diamond Systems would repair and reconstruct the entire facade and roof of Liberty’s building. Under the contract, they agreed to submit “[a]ny controversy or Claim arising out of or related to the Contract” for arbitration. The contract further provided that “[it] shall be governed by the law of the place where the Project is located.”

By October 1996, Diamond Systems had finished its work on the project. However, following the World Trade Center attacks of September 11, 2001, an engineering inspection of the building revealed cracks on the facade that were not present when the project was completed. Consequently, on September 20, 2002, Liberty served a demand for arbitration on nonparty Diamond Waterproofing Company, Inc. (Diamond Company) for breach of contract and negligence. * The statement of claim sought damages “in an amount currently unknown but equal to . . . the cost of restoring and repairing the facade and underlying supports of the Building.” In response, Diamond Company sought to permanently stay arbitration pursuant to CPLR 7503, *251 contending that it was not a party to the subject contract and that the demand failed to advise that it had 20 days to make an objection. Supreme Court granted the stay, and subsequently denied Liberty’s motion for leave to reargue and renew Diamond Company’s application.

On February 10, 2003, Liberty commenced a new arbitration proceeding naming Diamond Systems as the proper respondent. Diamond Systems then petitioned for a permanent stay on the ground that the demand for arbitration was barred pursuant to the six-year statute of limitations set forth in CPLR 213 (2). Diamond Systems contended that because its work on the project was substantially completed on September 18, 1996 and fully completed by October 10, 1996, the February 2003 demand for arbitration was untimely. Liberty cross-moved to dismiss the petition, arguing that the FAA governed this action and that the issue of timeliness was for the arbitrator to determine. Liberty further argued that its demand against Diamond Systems was timely under the relation-back doctrine.

Supreme Court granted Diamond Systems’ petition and denied the cross motion. The court reasoned that Liberty’s reliance on the FAA was misplaced as the parties did not agree to arbitrate and no substantial nexus existed between the project and interstate commerce for purposes of applying the FAA. The Appellate Division reversed, denied Diamond Systems’ petition for a permanent stay of arbitration, granted Liberty’s cross motion and dismissed the petition. The Court held that the FAA is applicable to this dispute “since the subject project ‘affected’ interstate commerce” (6 AD3d 101,104 [2004]), and that Supreme Court erred in employing the substantial nexus test to hold otherwise. The Court concluded therefore that under the FAA the timeliness issue was one for the arbitrator, not the courts. We granted Diamond Systems’ motion for leave to appeal, and now affirm.

II.

Diamond Systems and Liberty first dispute whether a sufficient nexus with interstate commerce exists to establish FAA coverage of their contract. The courts below were split as to what test should be employed, Supreme Court applying the more stringent substantial effect on interstate commerce standard and the Appellate Division applying the more generous “affects” test. In determining which standard controls, we turn to the language of the Act and United States Supreme Court cases interpreting the statute.

*252 The FAA provides that a written arbitration provision in “a contract evidencing a transaction involving commerce . . . shall be valid, irrevocable, and enforceable, save upon such grounds as exist at law or in equity for the revocation of any contract” (9 USC § 2 [emphasis added]). The Supreme Court has interpreted the words “involving commerce” as the functional equivalent of the phrase “affecting commerce,” which ordinarily signals Congress’ intent to exercise its Commerce Clause powers to the fullest extent (see Allied-Bruce Terminix Cos., Inc. v Dobson, 513 US 265, 273-274 [1995]). Thus, where a contract containing an arbitration provision “affects” interstate commerce, disputes arising thereunder are subject to the FAA. To be sure that the FAA is applicable to those transactions that have an effect on interstate commerce, the Supreme Court has recently reaffirmed the validity of Allied-Bruce (see Citizens Bank v Alafabco, Inc., 539 US 52, 53 [2003]; see also Wien & Malkin, LLP v Helmsley-Spear, Inc., 300 AD2d 32, 33 [1st Dept 2002], lv denied 99 NY2d 511 [2003], revd and remanded 540 US 801, 801 [2003]).

We conclude that the project here affected interstate commerce, triggering application of the FAA. Numerous out-of-state entities were involved in the transaction. The project manual and the engineer’s drawings were created in a joint effort with a structural engineering firm headquartered in Illinois. Diamond Systems’ largest supplier of materials for the project, MJM Studios, Inc., was a New Jersey company, and project meetings and visits were often scheduled at MJM’s offices. The largest supplier of equipment for the project, Dunlop Equipment, Inc., was a Massachusetts company. Further, various additional materials, equipment and services for the project were obtained from Oklahoma, Maryland and Kansas.

We turn next to the question whether the timeliness of the arbitration demand should be resolved by the arbitrators or the courts. The “presumption is that the arbitrator should decide ‘allegation's] of waiver, delay, or a like defense to arbitrability’ ” (see Howsam v Dean Witter Reynolds, Inc., 537 US 79, 84 [2002], quoting Moses H. Cone Mem. Hosp. v Mercury Constr. Corp., 460 US 1, 25 [1983]). Questions concerning “ ‘whether prerequisites such as time limits, notice, laches, estoppel, and other conditions precedent to an obligation to arbitrate have been met, are [generally] for the arbitrators to decide’ ” (id. at 85 [citation omitted]).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Judlau Contr., Inc. v. Five Star Elec. Corp.
2024 NY Slip Op 34013(U) (New York Supreme Court, New York County, 2024)
Rigano v. Uber Tech., Inc.
2024 NY Slip Op 51381(U) (New York Supreme Court, Westchester County, 2024)
Matter of Sivanesan v. YBF, LLC
2024 NY Slip Op 04327 (Appellate Division of the Supreme Court of New York, 2024)
Vitiello v. Home Buyers Resale Warranty Corp.
2022 NY Slip Op 05246 (Appellate Division of the Supreme Court of New York, 2022)
Cyprium Therapeutics, Inc. v. Curia Global, Inc.
2022 NY Slip Op 51426(U) (New York Supreme Court, Albany County, 2022)
Matter of Cardinale v. New York City Dept. of Educ.
2022 NY Slip Op 02791 (Appellate Division of the Supreme Court of New York, 2022)
Matter of Bergassi Group LLC v. Allied World Ins. Co.
2021 NY Slip Op 02265 (Appellate Division of the Supreme Court of New York, 2021)
Basile v. Riley
2020 NY Slip Op 06600 (Appellate Division of the Supreme Court of New York, 2020)
Smith v. Nobiletti Bldrs., Inc.
2019 NY Slip Op 8240 (Appellate Division of the Supreme Court of New York, 2019)
Matter of Steyn v. CRTV, LLC
2019 NY Slip Op 5341 (Appellate Division of the Supreme Court of New York, 2019)
Matter of Mahn v. Major, Lindsey, & Africa, LLC
2018 NY Slip Op 1888 (Appellate Division of the Supreme Court of New York, 2018)
Adams v. Metropolitan Transportation Authority
2017 NY Slip Op 5946 (Appellate Division of the Supreme Court of New York, 2017)
Final Sossous v. Herricks Union Free School District
142 A.D.3d 709 (Appellate Division of the Supreme Court of New York, 2016)
Rita Cusimano v. Andrew v. Schnurr Bernard v. Strianese
44 N.E.3d 212 (New York Court of Appeals, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
826 N.E.2d 802, 4 N.Y.3d 247, 793 N.Y.S.2d 831, 2005 N.Y. LEXIS 446, Counsel Stack Legal Research, https://law.counselstack.com/opinion/diamond-waterproofing-systems-inc-v-55-liberty-owners-corp-ny-2005.