Bay Rock Operating Co. v. St. Paul Surplus Lines Insurance Co.

298 S.W.3d 216, 2009 WL 856040
CourtCourt of Appeals of Texas
DecidedJune 24, 2009
Docket04-08-00180-CV
StatusPublished
Cited by28 cases

This text of 298 S.W.3d 216 (Bay Rock Operating Co. v. St. Paul Surplus Lines Insurance Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bay Rock Operating Co. v. St. Paul Surplus Lines Insurance Co., 298 S.W.3d 216, 2009 WL 856040 (Tex. Ct. App. 2009).

Opinion

OPINION

Opinion by

PHYLIS J. SPEEDLIN, Justice.

St. Paul Surplus Lines Insurance Company (“St. Paul”) sued Bay Rock Operating Company (“Bay Rock”) in the name of, and as subrogee of, its insured, well operator Hollimon Oil Corporation (“Hollimon”). The suit alleged that Bay Rock committed negligence, gross negligence and breach of contract in planning and supervising the drilling of the Striebeck No. 1 Well, located in Live Oak County, Texas, which resulted in a blowout and fire. Four working interest owners, Feliciana Corporation, Duncan Underwood, Everett Desha, and Seeligson Oil Co., Ltd., who together represent 35% of the working interest in the well also joined the suit in their individual capacities. The suit sought to recover from Bay Rock the damages caused by the blowout, including the costs to control the well, repair, evaluate and complete the well, redrill a nearby second well, and the value of lost gas. After a jury trial, and the resolution of post-trial motions, the trial court entered a final judgment for Hollimon and St. Paul in the amount of $1,799,012.70, plus prejudgment interest, on the negligence claim. The trial court disregarded the jury’s award of a separate $1 million in damages for lost gas to the four working interest owners. Both sides appealed. For the reasons discussed below, we affirm the portion of the trial court’s judgment finding liability against Bay Rock and awarding St. Paul its recovery in subrogation; however, we reverse the portion of the judgment concerning the other damages to be awarded, and render in part and remand in part as to those additional damages.

Factual and PROCEDURAL Background

J. Charles Hollimon, Ltd. is the manager of an oil and gas contract area in Live *221 Oak County, Texas and the generator of the lease prospect on which the Striebeck No. 1 Well was drilled. It designated Hollimon Oil Corporation to be its agent and the well operator pursuant to a Drilling and Operating Agreement, which incorporated a Joint Operating Agreement describing the rights and responsibilities of the operator and working interest owners. Charles Hollimon is the principal of both entities. As required by the Joint Operating Agreement, Hollimon obtained a blowout insurance policy with St. Paul (the “Policy”) covering the well. The Policy contains a subrogation clause.

Hollimon then hired Bay Rock to design, plan, and supervise the drilling of Strie-beck No. 1 Well. In turn, Bay Rock recommended Unison Drilling, Inc., a drilling contractor, to physically drill the well, and Hollimon hired Unison. Bay Rock’s engineer, John MacDiarmid, prepared the drilling program for the well. MacDiar-mid decided to use a drilling rig from Unison that had a 3,000 pound blowout preventer, believing that would be sufficient for this well. The blowout preventer had two main components: (i) a Reagan annular which contains a rubber bladder that closes around the drill pipe; and (ii) Shaffer pipe rams comprised of two steel plates that can seal around the pipe more tightly than the annular. Both are operated by hydraulic pressure. A device called a closing unit or accumulator is connected to the blowout preventer and controls the hydraulic fluid necessary to open and close, and maintain pressure on, the two preventer components; if the hydraulic fluid runs out, the blowout preventer will fail. In addition, MacDiarmid hired Ted Reichert to be Bay Rock’s representative, or “company man,” who would stay on-site and oversee the day-to-day drilling process. Reichert was in communication with MacDiarmid several times each day.

When the drilling reached a depth of over 7,000 feet and the crew was setting the intermediate casing, they encountered a weak zone which caused them to lose circulation as the liquid mud leaked into the surrounding formation. To counteract that, Reichert instructed the drilling crew to perform a “squeeze job” repair by pumping liquid cement into the pipe and forcing the cement into the formation to fill the cracks where the liquid mud was leaking. MacDiarmid had instructed Reic-hert to conduct a “formation integrity test,” or casing shoe test, when they set the intermediate casing to ensure the formation and casing seat could withstand the expected levels of pressure as the drilling progressed deeper. Believing he had conducted an equivalent test when he drilled through the “squeeze job,” Reichert did not think the formation integrity test was necessary, and did not conduct it. Instead, drilling was continued beyond the intermediate casing seat. When MacDiar-mid learned that Reichert had not performed the formation integrity test, he did not halt the drilling to conduct the test, but permitted the drilling to continue.

Then, on the evening of August 5, 2003, a gas kick occurred in which gas began flowing into the hole, pushing the drilling mud out into the formation and increasing the pressure in the hole and ultimately at the surface. Reichert ordered the annular component of the blowout preventer to be closed, but it began leaking and shortly thereafter its rubber bladder burst, causing hydraulic fluid to leak out. At that point, the pipe rams were closed, but there was not enough hydraulic pressure to hold them shut and they eventually failed. The rig was evacuated at that time, and within one to two hours a blowout occurred at the surface, causing the rig to burn. The reason for this sequence of events was the crux of the dispute at trial.

*222 Hollimon filed a claim under the Policy with St. Paul for the loss sustained at the well due to the blowout and fire. St. Paul issued a reservation of rights letter, contending the claim was not covered under the Policy. Subsequently, St. Paul settled with Hollimon, advancing $2 million to cover the payment of third party vendors and later paying it an additional $857,788. As subrogee, St. Paul then filed suit against Bay Rock in the name of Hollimon, its insured. As noted, four of the working interest owners also joined the suit against Bay Rock seeking their uninsured damages for lost gas. Bay Rock answered and filed a third party contribution claim against Unison Drilling. Summary judgment was granted in favor of Unison on the contribution claim and Bay Rock non-suited Unison. Bay Rock then designated Unison as a responsible third party pursuant to section 33.004 of the Texas Civil Practice & Remedies Code. Tex. Civ. Prac. & Rem. Code Ann. § 33.004 (Vernon 2008).

After a seven-day trial, a jury found Bay Rock liable for negligence and breach of contract. The jury found Bay Rock 51% negligent, and Unison 49% negligent. Hollimon was found 0% negligent. Total damages of $4,527,476 resulting from the “occurrence,” ie., the blowout, were awarded to Hollimon as follows: $1,527,476 as the cost to control the well; $2 million as the cost to repair, complete and evaluate the well; and $1 million as the value of the lost gas from the well. The jury awarded $0 as the cost to redrill a nearby well.

The plaintiffs elected negligence as their remedy and moved for entry of judgment on the jury verdict. Bay Rock filed motions for judgment notwithstanding the verdict and for a new trial. After post-trial briefing, the trial court granted Bay Rock’s motion for judgment notwithstanding the verdict in part, and disregarded the jury’s award of $1 million in lost gas damages to the four working interest owners.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gator Gone Safety Pilots v. Garry W. Holt
Court of Appeals of Texas, 2021
Garcia v. Pruski
563 S.W.3d 333 (Court of Appeals of Texas, 2018)
Harris v. Kellogg, Brown & Root Services, Inc.
151 F. Supp. 3d 600 (W.D. Pennsylvania, 2015)
Daniel E. Arnold v. Gerardo Gonzalez
Court of Appeals of Texas, 2015
City of San Antonio v. Maria Elena Rodriguez
Court of Appeals of Texas, 2013
in Re Guardianship of Robert S. Litoff
Court of Appeals of Texas, 2013
DeGroot v. DeGroot
369 S.W.3d 918 (Court of Appeals of Texas, 2012)
Ladd Vien v. Mark Del Buono and Mary Del Buono
Court of Appeals of Texas, 2010
Total Clean, LLC v. Cox Smith Matthews Inc.
330 S.W.3d 657 (Court of Appeals of Texas, 2010)
Elzie Bell v. State
Court of Appeals of Texas, 2010
Total Clean, LLC v. Cox Smith
Court of Appeals of Texas, 2010
Cressman Tubular Products Corp. v. Kurt Wiseman Oil & Gas, Ltd.
322 S.W.3d 453 (Court of Appeals of Texas, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
298 S.W.3d 216, 2009 WL 856040, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bay-rock-operating-co-v-st-paul-surplus-lines-insurance-co-texapp-2009.