Baltimore Gas & Electric Co. v. Federal Energy Regulatory Commission

252 F.3d 456, 346 U.S. App. D.C. 265, 2001 U.S. App. LEXIS 13387
Court of Appeals for the D.C. Circuit·Decided June 15, 2001·No. 19-1179·Published·Cited by 31 cases

Opinion

Opinion for the Court filed by Circuit Judge SENTELLE.

SENTELLE, Circuit Judge:

Baltimore Gas & Electric and several other petitioners (collectively “BG&E”) challenge the Federal Energy Regulatory Commission’s (“FERC”) agreement to settle an enforcement action against Columbia Gas Transmission and Columbia Gulf Transmission (collectively “Columbia”), two natural-gas vendors. The Commission initially had alleged that Columbia violated the Natural Gas Act, (“NGA”), 15 U.S.C. § 717 et seq., by engaging in unauthorized service abandonment. Because FERC’s decision to settle is committed to the agency’s nonreviewable discretion under Heckler v. Chaney, 470 U.S. 821, 105 S.Ct. 1649, 84 L.Ed.2d 714 (1985), we conclude that we lack jurisdiction to hear petitioners’ claim.

I. BACKGROUND

The NGA requires all vendors of natural gas in interstate commerce to obtain from FERC a certificate authorizing service at specified “certificated” levels. 15 U.S.C. § 717f(c). Having obtained such authority, a natural-gas vendor must obtain Commission approval before abandoning a portion, or all, of its certificated service. Id. § 717f(b).

In 1992, FERC discovered that the available capacity on one of Columbia’s pipelines was lower than the level at which it had been certificated. FERC suspected that the decline in the pipeline’s capacity was due to Columbia’s failure to replace deteriorated compressor units. The Commission therefore ordered Columbia to show cause why it had not abandoned capacity without prior authorization. It also directed its General Counsel to begin a formal, non-public investigation into whether Columbia had unlawfully abandoned service without first obtaining FERC approval. See Columbia Gas Transmission Corp., 64 FERC ¶ 61,365, 1993 WL 385590'(1993).

After a four-year investigation, FERC in August 1997 approved a settlement between Columbia and the Commission’s Enforcement section. The settlement expressly declined to resolve whether Columbia had violated the Natural Gas Act. Instead Columbia, “without admitting or denying that any violation of the NGA or the Commission’s regulations occurred, agree[d] to the remedies” the settlement contained. Columbia Gas Transmission Corp., 80 FERC ¶ 61,220, 61,867, 1997 WL 451411- (1997). The centerpiece remedy was the requirement that Columbia conduct a 30-day “open season” to determine whether there was any demand for additional capacity on its pipeline, and to make that capacity available (up to its certificated level) to customers that desired it. Id. The settlement stopped short of requiring Columbia to pay money damages to customers that may have incurred higher costs as a result of the decline in its pipeline’s capacity.

In September 1997, BG&E, one of Columbia’s customers, moved to intervene in the administrative proceedings, and also petitioned for rehearing. BG&E arg-ued both that FERC should not have settled with Columbia without submitting the agreement’s terms to public notice and comment, and that the 30-day open season was inadequate to remedy the damages it had suffered from Columbia’s capacity decline.

*458 In December 1998, FERC permitted BG&E to intervene but denied its request for rehearing. See Columbia Gas Transmission Corp., 85 FERC ¶ 61,437, 1998 WL 894921 (1998). The Commission explained that it was entitled to settle without notice and comment because the settlement was reached in the course of an agency investigation, and third parties have no right to participate in investigations. Because the investigation had now concluded, and because of BG&E’s interests, FERC granted its motion to intervene. However, the Commission declined BG&E’s invitation to reconsider its decision on rehearing. FERC cited its broad discretion to impose sanctions, which “includes the discretion not to order remedies for past violations in appropriate circumstances.” Id. at 62,642. In particular, FERC explained that monetary relief was unwarranted because the magnitude of BG&E’s asserted injuries was speculative, and because of Columbia’s poor financial condition (it had been in bankruptcy from 1991 to 1995). Id. at 62,642-48.

Later that month BG&E filed another motion for rehearing. BG&E again complained that FERC had unlawfully excluded it from the investigation of Columbia, and that FERC was required to award it monetary relief for the losses it suffered. In December 1999, the Commission again denied rehearing. FERC explained that BG&E had no right to participate in its investigation of Columbia. FERC further claimed that its decision to proceed against Columbia through a settlement was “well within [its] discretion.” And money damages against Columbia were unwarranted because calculating them would require “an undetermined expenditure of Commission ... resources” that FERC preferred to devote to “its current regulatory programs and initiatives.” Columbia Gas Transmission Corp., 89 FERC ¶ 61,325, 61,992, 1999 WL 1247077 (1999).

BG&E then filed a petition for review with this Court. It maintains that FERC abused its discretion by approving the Columbia settlement without first giving BG&E an opportunity to participate in the proceedings. BG&E further argues that the Commission abused its discretion by remedying Columbia’s assertedly unlawful conduct with a prospective open season, and not with money damages. 1 Intervenor Columbia moved to dismiss BG&E’s petition. FERC and Columbia claim that this Court lacks jurisdiction to consider FERC’s decision to settle, which is committed to the agency’s nonreviewable discretion pursuant to Heckler v. Chaney, 470 U.S. 821, 105 S.Ct. 1649, 84 L.Ed.2d 714 (1985). In a similar vein, they argue that, since this Court has no power to issue an order that could redress BG&E’s claimed injury, BG&E lacks standing.

II. DISCUSSION

The Administrative Procedure Act (“APA”) both authorizes and limits judicial scrutiny of the actions of administrative agencies. While there is a strong presumption of reviewability under the APA, Abbott Labs. v. Gardner, 387 U.S. 136, 140, 87 S.Ct. 1507, 18 L.Ed.2d 681 (1967), that statute expressly provides that no judicial review is available of an “agency action [that] is committed to agency discretion by law.” 5 U.S.C. § 701(a)(2). The ban on judicial review of actions “committed to agency discretion by law” is jurisdictional. See, e.g., Fort Sumter Tours, Inc. v. Babbitt, 202 F.3d 349

Free access — add to your briefcase to read the full text and ask questions with AI

Baltimore Gas & Electric Co. v. Federal Energy Regulatory Commission, 252 F.3d 456, 346 U.S. App. D.C. 265, 2001 U.S. App. LEXIS 13387 (D.C. Cir. 2001).

252 F.3d 456 (Baltimore Gas & Electric Co. v. Federal Energy Regulatory Commission) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Ruhumuriza v. Jaddou
District of Columbia, 2026
Lesly Miot v. Trump
District of Columbia, 2026
United States v. Simmons
District of Columbia, 2022
Public Citizen, Inc. v. FERC
7 F.4th 1177 (D.C. Circuit, 2021)
Rollerson v. Brazos River
6 F.4th 633 (Fifth Circuit, 2021)
Citizens for Responsibility v. FEC
993 F.3d 880 (D.C. Circuit, 2021)
Campbell v. Schmidt
District of Columbia, 2020
Weingarten v. Devos
District of Columbia, 2020
United States v. Facebook, Inc.
District of Columbia, 2020
Swecker v. Midland Power Cooperative
253 F. Supp. 3d 274 (District of Columbia, 2017)
Maria Garcia v. Gina McCarthy
649 F. App'x 589 (Ninth Circuit, 2016)
Board of Commissioners of Cherokee County, Kansas v. Kempthorne
956 F. Supp. 2d 116 (District of Columbia, 2013)
Brown v. Holder
770 F. Supp. 2d 363 (District of Columbia, 2011)
Beshir v. Holder
853 F. Supp. 2d 1 (District of Columbia, 2011)
Building & Construction Trades Department, AFL-CIO v. Solis
600 F. Supp. 2d 25 (District of Columbia, 2009)
Tucci v. District of Columbia
956 A.2d 684 (District of Columbia Court of Appeals, 2008)