American Gas Ass'n v. Federal Energy Regulatory Commission

912 F.2d 1496, 286 U.S. App. D.C. 142
CourtCourt of Appeals for the D.C. Circuit
DecidedAugust 24, 1990
DocketNo. 87-1588
StatusPublished
Cited by31 cases

This text of 912 F.2d 1496 (American Gas Ass'n v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Gas Ass'n v. Federal Energy Regulatory Commission, 912 F.2d 1496, 286 U.S. App. D.C. 142 (D.C. Cir. 1990).

Opinion

STEPHEN F. WILLIAMS, Circuit Judge:

[[Image here]]

[149]*149[[Image here]]

I. Introduction

In the Spring of 1985, as Mikhail Gorbachev was assuming the duties of General Secretary and inaugurating perestroika, the Federal Energy Regulatory Commission launched its own restructuring of the natural gas industry. See Notice of Proposed Rulemaking, Regulation of Natural Gas Pipelines After Partial Wellhead Decontrol, 50 Fed.Reg. 24,130 (June 7, 1985) (issued May 30, 1985). The cornerstone was “open access” — a process by which a pipeline would be able to avoid many of the regulatory hurdles otherwise impeding the provision of gas transportation, in exchange for committing itself to carry gas for any party, including gas that would be sold in competition with its own. Open access would thus provide a market-based incentive to pipelines to keep the costs of their own gas competitive.

As with Gorbachev, the road has not been smooth. The Commission issued its final rule, Order No. 436, in October 1985. In Associated Gas Distributors v. FERC (“AGD I”), 824 F.2d 981 (D.C.Cir.1987), we generally approved the rule but vacated it on the ground that the Commission had failed to adequately address some fundamental problems, especially the rule’s effect on pipelines’ take-or-pay liabilities. The Commission moved swiftly to promulgate a substitute rule (Order No. 500, 52 Fed.Reg. 35,334 (Aug. 14, 1987)) before our mandate issued, so that open access transportation could continue without interruption.

Innumerable parties attacked not only Order No. 500 (and later orders of the 500 series), but also many individual FERC adjudications of issues based on Order No. 500. Many of these were consolidated and argued before us in the Fall of 1989. In American Gas Ass’n v. FERC (“AGA I”), 888 F.2d 136 (D.C.Cir.1989), the court resolved several of the claims but remanded the record to the Commission to address some issues that AGD I had said it must consider, as well as some new problems posed by Order No. 500 itself. (We disposed of still other components of the case in Associated Gas Distributors v. FERC (“AGD II”), 893 F.2d 349 (D.C.Cir.1989), petitions for certiorari filed, 59 U.S.L.W. 3017 (Nos. 89-1988, -1989, -1990, -2000, -2016), and Transwestern Pipeline Co. v. FERC, 897 F.2d 570 (D.C.Cir.1990)). As a result of the remand, the Commission issued Order No. 500-H, III FERC Stats. & Regs. II 30,867 (1989), and, on applications for rehearing, Order No. 500-1, III FERC Stats. & Regs. ¶ 30,880 (1990). The contending parties were of course not satisfied, and here we review their contentions.

First, we affirm the Commission’s rejection of demands that it should have intervened under § 5 of the Natural Gas Act, 15 U.S.C. § 717d (1988), to modify uneconomic take-or-pay contracts between producers and pipelines. Second, we affirm in virtually all respects its decisions creating a “crediting” mechanism. This allows pipelines that carry gas under open access (which is likely to displace their own and [150]*150thus aggravate their take-or-pay liabilities) to obtain credit in an equal amount against their take-or-pay obligations under contracts with the gas’s producer. As to one feature, however, we remand the case to the Commission for further consideration. Third, although we cannot find any insuperable legal obstacle to the Commission’s provision for “pregranted abandonment” of transportation services provided under “blanket certificates,” we remand the case on that issue because the Commission’s explanations do not adequately justify its decision or respond to opponents’ claims. Finally, we reject a series of miscellaneous contentions as either unripe or lacking in merit.

II. Inaction under Section 5

In AGD I, this court vacated Order No. 436 and remanded for the Commission to reassess both its reasoning and its factual premises for refusing to modify “uneconomical pipeline-producer contracts” under § 5 of the Natural Gas Act. 824 F.2d at 1030. The Commission then collected extensive data from the pipelines, including figures on the relation between high prices and take-or-pay provisions, and on the proportion of contracts that were within or without its jurisdiction. On issuing its requests to the pipelines for data, it promised to aggregate and analyze the results promptly. Order No. 500, 52 Fed.Reg. at 30,341.

Despite that promise, the Commission did virtually nothing after collecting the data, and its “half-explained cunctation [convinced the AG A I court] that it delayfed] in order to avoid having to do the analysis that we required in AGD until after the take-or-pay problem ... disappeared.” AGA I, 888 F.2d at 148. Accordingly we remanded for FERC to explain in a final rule whether it planned to take § 5 action, and if not, why not. Id. The Commission has now done so in Order Nos. 500-H and 500-1, and we find its explanation sufficient.

A. Scope of Review.

Certain petitioners attempt to cast the Commission’s duty to act under § 5 in mandatory terms. Drawing on the language of § 5 saying that the Commission “shall determine the just and reasonable rate ... to be thereafter observed and in force,” 15 U.S.C. § 717d (1988) (emphasis added), they argue that the Commission must undertake a § 5 investigation whenever requested to do so. But the directive to impose a just and reasonable rate or provision is triggered only by the Commission’s finding that the existing one is “unjust, unreasonable, unduly discriminatory, or preferential.” Nothing in § 5 requires the Commission to embark on the inquiry in the first place.1

Nor did our decision in AGD I impose any such burden. We simply concluded that the Commission had not considered all the factors relevant to pursuit of such an inquiry. Most particularly, the Commission appeared virtually to deny the tendency of its restructuring program — open access transportation and a grant to customers of authority to convert purchase arrangements into transportation — to aggravate the pipelines’ take-or-pay liabilities and thus, arguably, to generate a need for action under § 5. AGD I, 824 F.2d at 1021-28, 1044; see also San Diego Gas & Elec. Co. v. FERC, 904 F.2d 727, 730-31 (D.C.Cir.1990) (summarizing material passages of AGD I). Thus our remand insisted that the Commission reassess whether § 5 should play a role in the solution.

Our review of the Commission’s decision not to take action is therefore quite limited in scope. The Commission correctly invokes General Motors Corp. v. FERC, 613 F.2d 939 (D.C.Cir.1979), stating that we review a no-investigation decision under [151]*151§ 5 only to ensure that the Commission has “consider[ed] all the relevant factors.” Id. at 944; see also Southern Union Gas Co. v. FERC, 840 F.2d 964, 968-70 (D.C.Cir.1988). As neither the Commission nor any petitioners have invoked Heckler v. Chaney, 470 U.S. 821

Free access — add to your briefcase to read the full text and ask questions with AI

Related

International Transmission Company v. FERC
988 F.3d 471 (D.C. Circuit, 2021)
Maine v. Federal Energy Regulatory Commission
854 F.3d 9 (D.C. Circuit, 2017)
Federal Trade Commission v. Wyndham Worldwide Corp.
10 F. Supp. 3d 602 (D. New Jersey, 2014)
E. & J. GALLO WINERY v. EnCana Corp.
503 F.3d 1027 (Ninth Circuit, 2007)
Shays v. Federal Election Commission
511 F. Supp. 2d 19 (District of Columbia, 2007)
Inter Nat Gas Assn v. FERC
D.C. Circuit, 2002
Aviators for Safe v. FAA
221 F.3d 222 (First Circuit, 2000)
GA Indust Grp v. FERC
D.C. Circuit, 1998

Cite This Page — Counsel Stack

Bluebook (online)
912 F.2d 1496, 286 U.S. App. D.C. 142, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-gas-assn-v-federal-energy-regulatory-commission-cadc-1990.