Office of the Consumers' Counsel, State of Ohio v. Federal Energy Regulatory Commission, Columbia Gas of Ohio, Inc., Columbia Gas Transmission Corp., Washington Gas Light Co., Intervenors. State of Ohio v. Federal Energy Regulatory Commission, Columbia Gas of Ohio, Inc., Columbia Gas Transmission Corp., Washington Gas Light Co., Intervenors

808 F.2d 125
CourtCourt of Appeals for the D.C. Circuit
DecidedJanuary 6, 1987
Docket85-1585
StatusPublished
Cited by4 cases

This text of 808 F.2d 125 (Office of the Consumers' Counsel, State of Ohio v. Federal Energy Regulatory Commission, Columbia Gas of Ohio, Inc., Columbia Gas Transmission Corp., Washington Gas Light Co., Intervenors. State of Ohio v. Federal Energy Regulatory Commission, Columbia Gas of Ohio, Inc., Columbia Gas Transmission Corp., Washington Gas Light Co., Intervenors) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Office of the Consumers' Counsel, State of Ohio v. Federal Energy Regulatory Commission, Columbia Gas of Ohio, Inc., Columbia Gas Transmission Corp., Washington Gas Light Co., Intervenors. State of Ohio v. Federal Energy Regulatory Commission, Columbia Gas of Ohio, Inc., Columbia Gas Transmission Corp., Washington Gas Light Co., Intervenors, 808 F.2d 125 (D.C. Cir. 1987).

Opinion

808 F.2d 125

257 U.S.App.D.C. 230

OFFICE OF THE CONSUMERS' COUNSEL, STATE OF OHIO, Petitioner,
v.
FEDERAL ENERGY REGULATORY COMMISSION, Respondent,
Columbia Gas of Ohio, Inc., Columbia Gas Transmission Corp.,
Washington Gas Light Co., et al., Intervenors.
STATE OF OHIO, et al., Petitioners,
v.
FEDERAL ENERGY REGULATORY COMMISSION, Respondent,
Columbia Gas of Ohio, Inc., Columbia Gas Transmission Corp.,
Washington Gas Light Co., et al., Intervenors.

Nos. 85-1585, 85-1586.

United States Court of Appeals,
District of Columbia Circuit.

Argued Sept. 29, 1986.
Decided Jan. 6, 1987.
As Amended Jan. 6, 1987.

M. Howard Petricoff, Sp. Asst. Atty. Gen., State of Ohio, with whom Robert S. Tongren, Asst. Atty. Gen., State of Ohio, Columbus, Ohio, was on the brief for petitioners, State of Ohio, et al., in No. 85-1586.

Margaret Ann Samuels, Columbus, Ohio, with whom David C. Bergmann, Sandusky, Ohio, was on the brief for petitioners, Office of the Consumers' Counsel, State of Ohio, in No. 85-1585.

John Harris Conway, Atty., F.E.R.C., with whom Jerome M. Feit, Sol., F.E.R.C., Washington, D.C., was on the brief for respondent. Barbara J. Weller and Andrea Wolfman, Attys., F.E.R.C., Washington, D.C., also entered appearances for respondent.

Fredric J. George, with whom Stephen J. Small and H.L. Snyder, Charleston, W. Va., were on the brief for intervenor, Columbia Gas Transmission Corp., in Nos. 85-1585 and 85-1586.

Karen B. Pancost and Gordon M. Grant, Washington, D.C., were on the brief for intervenors, Washington Gas Light Co., et al., in Nos. 85-1585 and 85-1586.

Roger C. Post, Columbus, Ohio, was on the brief for intervenor, Columbia Gas of Ohio, Inc., in Nos. 85-1585 and 85-1586.

Before SILBERMAN and WILLIAMS, Circuit Judges, and JAMESON,* Senior District Judge.

Opinion for the Court filed by Circuit Judge WILLIAMS.

WILLIAMS, Circuit Judge:

Petitioners seek review of a decision of the Federal Energy Regulatory Commission ("FERC" or the "Commission") authorizing abandonment of a 4.7-mile stretch of natural gas pipeline in Ohio known as D-75W. Bowman v. Columbia Gas Transmission Corp., 31 F.E.R.C. (CCH) p 61,185, reh'g denied, 32 F.E.R.C. (CCH) p 61,075 (1985). The proceedings before FERC consisted of a consolidation of two actions. In the first, Steve Bowman and 13 other consumers (the "consumers"), all of whom received gas delivered through D-75W, sought an order compelling Columbia Gas Transmission Corporation ("Columbia") to cease all efforts to terminate service through that line. In the second, Columbia sought FERC's permission under section 7(b) of the Natural Gas Act of 1938 (the "NGA"), 15 U.S.C. Sec. 717f(b) (1982),1 to abandon D-75W. FERC rejected the consumers' claims that abandonment would be contrary to the public convenience or necessity2 and granted Columbia's request. It also rejected a separate challenge by the Ohio Department of Development (Energy Division) and the Public Utilities Commission of Ohio (collectively referred to here as "Ohio" or the "state") to aspects of the abandonment order that relate to Ohio's jurisdiction. The consumers and Ohio petition for relief under section 19(b) of the NGA, 15 U.S.C. Sec. 717r(b) (1982). We find no grounds to set aside the order.

Background

The disputed stretch of pipeline consists of the 4.3-mile segment of Line D-75 to the west of Harpster, Ohio.3 D-75 was constructed between 1909 and 1911 by Ohio Fuel Gas Company ("Ohio Fuel"), the predecessor of Columbia, and originally carried gas from Line T-50 eastward to several Ohio towns. Construction of Line D-75 was facilitated by right-of-way agreements with rural consumers, predecessors of the petitioners, who lived between Line T-50 and Harpster. These consumers exchanged easements across their property for the right to receive service directly from the line through what are known as farm taps "[w]hile gas is conveyed through said premises in said pipe line...."4

The eastern end of D-75 was connected to a new Ohio Fuel line, Line D, around 1929. Joint Appendix ("J.A.") at 802. For the next four decades D-75 was used to move gas from Line T-50 to Line D, as well as to provide gas to the towns along its path and to the rural consumers. By 1970, Line T-50 had deteriorated, and Ohio Fuel applied for and was granted authorization to abandon it. Ohio Fuel Gas Co., 45 F.P.C. 25 (1971). After the demise of T-50, the company reversed the flow in D-75, feeding gas in at D-75's eastern end and moving it westward. Thus the consumers residing along the 4.3-mile stretch of D-75W west of Harpster were no longer tapping into the vital first stage of D-75, but instead found themselves at the end of the line.

Over time D-75W began to develop excessive leaks. Between 1960 and 1967 Columbia repaired over 400 leaks with magnesium anodes designed to slow deterioration. In the following years it detected fewer leaks, but in the spring of 1983 it discovered 28. J.A. at 787. Columbia determined that the line could no longer be used safely, id. at 703-05, and the consumers were informed in June 1983 of its intention to abandon the line, id. at 668-77. The consumers started an action in state court, seeking an injunction against abandonment on grounds of the right-of-way agreements. Brief of Petitioner at 15-16. In January 1984, however, the Department of Transportation issued an order requiring Columbia to cease its use of the line because of the safety hazard. See J.A. at 666-67. Columbia complied and since February 1, 1984, has not used the line. See id. at 621. Of course the Department of Transportation order left in place Columbia's service obligation under the NGA, stemming from the original certification of service. For relief from that obligation, FERC consent is required. See, e.g., United Gas Pipe Line Co. v. McCombs, 442 U.S. 529, 99 S.Ct. 2461, 61 L.Ed.2d 54 (1979).

Meanwhile, the consumers' state court action culminated in a settlement. According to its terms, Columbia, at its expense, supplied the consumers with $39,226.16 worth of equipment enabling them to use propane as an alternative fuel. (One consumer incurred expenses of $21,000 to convert a grain dryer, which Columbia apparently will pay for under the order here reviewed.) Columbia also agreed to pay the difference between the higher cost of propane and the cost of gas until the status of D-75W was resolved. J.A. at 614. The parties stipulated that repair of D-75W west of Harpster would be prohibitively expensive and that replacement of the pipeline with a four-inch plastic pipe would cost $173,000.

Ohio's Standing

As a preliminary matter, we must determine whether Ohio has standing. Its challenge relates to four points of the Commission's order.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
808 F.2d 125, Counsel Stack Legal Research, https://law.counselstack.com/opinion/office-of-the-consumers-counsel-state-of-ohio-v-federal-energy-cadc-1987.