Valley Gas Company v. Federal Power Commission, Tennessee Gas Pipeline Company, Intervenors

487 F.2d 1182, 159 U.S. App. D.C. 311
CourtCourt of Appeals for the D.C. Circuit
DecidedOctober 2, 1973
Docket71-1743
StatusPublished
Cited by6 cases

This text of 487 F.2d 1182 (Valley Gas Company v. Federal Power Commission, Tennessee Gas Pipeline Company, Intervenors) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Valley Gas Company v. Federal Power Commission, Tennessee Gas Pipeline Company, Intervenors, 487 F.2d 1182, 159 U.S. App. D.C. 311 (D.C. Cir. 1973).

Opinion

WILKEY, Circuit Judge:

This case arises on petition for review of an order of the Federal Power Commission 1 which permitted the Ten *1184 nessee Gas Pipeline Company, a division of Tenneco Inc. (Tennessee), to abandon certain liquified natural gas (LNG) facilities 2 for the purpose of selling them to the New England Gas and Electric Association and Air Products & Chemicals, Inc. (NEGEA). As the basis for allowing such abandonment, in accordance with Section 7(b) of the Natural Gas Act, 3 the Commission found that “the public interest will be best served by granting Tennessee’s application.” 4 Finding that conclusion to be supported by substantial evidence, and to have been based on legally appropriate criteria, we affirm the Commission’s Order.

1. Facts

On 26 July 1965 the Commission issued a certificate of public convenience and necessity authorizing construction and operation of an in-ground storage LNG facility near Hopkinton, Massachusetts. 5 This facility had been requested by Tennessee’s customers with a view that it would help to provide “peak-shaving” 6 natural gas service during the winter months, by means of evaporating gas which had been liquified during the off-peak season and stored underground. Not only would such a large centralized facility spare Tennessee’s various customers the expense and inconvenience of building their own LNG peaking facilities, it would also, it was hoped, result in a lower overall cost of gas. 7

The liquefaction of natural gas for storage in the in-ground tanks was commenced early in 1967, in anticipation that redelivery of the gas in the form of peaking service to customers who had contracted for such service could start in the fall of 1967. Unfortunately, despite continuous attempts to fill the storage tanks, an unexpectedly high “boil off” rate held the effective storage level to one-sixth of the planned capacity. 8 *1185 Commencement of peaking service was impossible in the face of that technological problem; extensive efforts to find a solution were unsuccessful.

Faced with this failure, Tennessee proposed an additional investment in above-ground tanks of equal capacity and filed an application to amend its certificate to that effect. However, since such a change would add dramatically to the cost of service, Tennessee conditioned its proposal on the willingness of its customers to purchase volumes of natural gas from the above-ground project at higher rates, sufficient to render it economically feasible. The customers were willing to purchase only one-sixth of the necessary volume. 9 Therefore, Tennessee entered into a contract to sell its facilities to NEGEA, 10 and applied for authority to abandon the original project in order to be in position to sell the facilities.

The only one of Tennessee’s customers to oppose abandonment was Valley Gas Company (Valley). Unlike many of the prior customers, Valley was not one of those prior contractors for LNG service who would be receiving peaking service, at least in some amount, from NEGEA. 11 Valley claimed that, as a condition of approval of the abandonment, Tennessee should be ordered to provide it with some sort of substitute service essentially equivalent to that which it would have received had Tennessee’s project been a success.

On 20 April 1971 the Presiding Examiner ruled that the abandonment application should be unconditionally granted. He deferred disposition of Valley’s request for substitute service until the second phase of the administrative proceedings, which would also deal with the proper accounting treatment to be given to Tennessee’s unrecovered costs. By order of 21 July 1971 the Commission affirmed and adopted the Examiner’s decision. The Commission approved the delay of decision on Valley’s claim, noting that the Phase II hearings were by then already completed and that “fairness to New England LNG users compels our prompt decision in Phase I.” 12

II. Abandonment Authorization

We find that the Commission’s order permitting abandonment was' supported by substantial evidence and premised on proper criteria. The standard to be applied by the FPC in such cases is hardly a model of clarity and detail. The Natural Gas Act provides that abandonment shall be allowed only if permitted by “the present or future public convenience or necessity.” 13 However, the key elements in the decision must obviously be the provision of the maximum supply of gas, at the lowest possible rate, consistent with the physical and economic realities of the industry. The Commission clearly applied the appropriate test in this case.

*1186 There is no question that Tennessee’s project, as originally certificated, had foundered on insurmountable physical defects encountered in the structure of the in-ground reservoirs. If the Commission had disallowed abandonment, it would in effect have been deciding to require Tennessee to press its application for amendment of the certificate, despite the fact that Tennessee’s new above-ground storage proposal lacked customer support. Given the lack of support, the Commission could not ignore the fact that Tennessee’s proposal would have involved greater cost and delay than the readily available alternative represented by an approved sale of the facilities to NEGEA. 14

Since the applicable statutory standard is the present or future public interest, the Commission quite properly refrained from recriminations and concentration on hindsight in reaching its decision. 15 The question before the Commission was not what might have or should have been done to make the in-ground LNG storage project a success, but rather what course was now best for all the customers of gas in the New England region. In that light, the advantages of the NEGEA proposal were just as important as the disadvantages of Tennessee’s new plan.

With regard to those customers who would be receiving LNG service from NEGEA (largely Worcester and New Bedford — but many others as well for a while), there was an advantage in cost. 16 By buying Tennessee’s liquefaction facilities, and building its own storage tanks, the NEGEA group was eliminating the middleman as to those functions.

*1187

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
487 F.2d 1182, 159 U.S. App. D.C. 311, Counsel Stack Legal Research, https://law.counselstack.com/opinion/valley-gas-company-v-federal-power-commission-tennessee-gas-pipeline-cadc-1973.