Tennessee Gas Pipeline Company, a Division of Tenneco Inc. v. Federal Power Commission, Berkshire Gas Company, Intervenor. Valley Gas Company v. Federal Power Commission, Tennessee Gas Pipeline Company, Intervenors

487 F.2d 1189
CourtCourt of Appeals for the D.C. Circuit
DecidedOctober 2, 1973
Docket72-2101
StatusPublished

This text of 487 F.2d 1189 (Tennessee Gas Pipeline Company, a Division of Tenneco Inc. v. Federal Power Commission, Berkshire Gas Company, Intervenor. Valley Gas Company v. Federal Power Commission, Tennessee Gas Pipeline Company, Intervenors) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tennessee Gas Pipeline Company, a Division of Tenneco Inc. v. Federal Power Commission, Berkshire Gas Company, Intervenor. Valley Gas Company v. Federal Power Commission, Tennessee Gas Pipeline Company, Intervenors, 487 F.2d 1189 (D.C. Cir. 1973).

Opinion

487 F.2d 1189

159 U.S.App.D.C. 318, 2 P.U.R.4th 278

TENNESSEE GAS PIPELINE COMPANY, a Division of Tenneco Inc., Petitioner,
v.
FEDERAL POWER COMMISSION, Respondent, Berkshire Gas Company,
et al., Intervenor.
VALLEY GAS COMPANY, Petitioner,
v.
FEDERAL POWER COMMISSION, Respondent, Tennessee Gas Pipeline
Company et al., Intervenors.

Nos. 72-2101, 72-2106.

United States Court of Appeals,
District of Columbia Circuit.

Argued June 6, 1973.
Decided Oct. 2, 1973.

Harold L. Talisman, Washington, D. C., with whom Harry S. Welch, Houston, Tex., and Harry S. Littman, Washington, D. C., were on the brief, for petitioner in No. 72-2101 and intervenor Tennessee Gas Pipeline Co. in No. 72-2106.

Morton L. Simons, Washington, D. C., with whom Barbara M. Simons, Washington, D. C., was on the brief for petitioner in No. 72-2106.

Michael J. Manning, Atty., F. P. C., with whom Leo E. Forquer, Gen. Counsel, and George W. McHenry, Jr., Acting Sol., F. P. C., were on the brief, for respondent.

John W. Glendening, Jr., New York City, was on the brief for intervenors, the Berkshire Gas Co. and others.

Francis H. Caskin, Washington, D. C., entered an appearance for intervenors, New England Gas and Electric Assn. and Air Products and Chemicals, Inc., in No. 72-2106.

Before BAZELON, Chief Judge, and ROBINSON and WILKEY, Circuit Judges.

WILKEY, Circuit Judge:

This case arises on petitions for review of an Order of the Federal Power Commission which resolved the second phase of the proceedings discussed in Valley Gas Company v. FPC, No. 71-1743, 159 U.S.App.D.C. ____, 487 F.2d 1182, which we decide today.1 On review of the first phase, this court affirmed a Commission Order which (1) authorized abandonment of a liquified natural gas (LNG) project, and (2) allowed withdrawal of a petition to amend the original certificate for that project. The Order under review here (1) denied the claim of Valley Gas Company (Valley) for reinstatement of alleged losses in level of service, and (2) refused the request of Tennessee Gas Pipeline Company (Tennessee) that its unrecovered losses be amortized (and thereby included in its rate base) as either Research and Development Costs or as Extraordinary Property Losses. Supported by substantial evidence and based on legally appropriate criteria, as it was, the Commission's Order under review here is affirmed.

I. Facts

On 5 May 1965 Tennessee filed an application in Docket No. CP 65-352 for authority to construct and operate an in-ground storage LNG facility designed to render peaking service to eighteen New England customers. On 26 July 1965 the Commission issued a certificate of public convenience and necessity authorizing the construction and operation of the facilities to provide the proposed service.2 One basis for that approval was the existence of contracts with proposed customers to take such peaking service, at prearranged rates, when the project was completed.

Tennessee's customers had requested construction of these facilities,3 with a central purpose of relieving themselves of the expense involved in building separate and individual storage facilities to provide "peak-shaving" service. Since the construction of such a large facility would take some time, Tennessee undertook to provide an "Interim General" service (IG) to serve peaking needs, renewable at one year intervals until the LNG facility was completed.4 When the originally planned and certified facility failed for technological reasons, and Tennessee's proposed alternative met with only lukewarm customer support at necessarily increased proposed rates,5 Tennessee sought approval to abandon the in-ground LNG project, asked to withdraw its application for amendment of the certificate to allow above-ground storage, and allowed its current one-year interim service to expire.6 Protesting these actions, which resulted in termination of a supply of 6,900 Mcf of IG gas annually to itself,7 Valley claims that Tennessee is under a duty to continue supplying some form of substitute service to replace these lost supplies. The Commission disagreed.

With respect to the proper accounting treatment to be given Tennessee's losses, the Commission reversed the Administrative Law Judge's decision, which allowed Tennessee to amortize its net loss of $8,841,744 over a ten year period as a miscellaneous deferred debit. The Commission found that under applicable regulations the loss could not be properly classified as either a Research and Development Cost or an Extraordinary Property Loss. Further, the Commission held that the original certificate conditions agreed to by Tennessee precluded amortization of costs, no matter how characterized, to the extent that the project proved unsuccessful.8

II. Valley's Claim

As to whether Tennessee was legally obligated to complete (or replace with an adequate substitute) the LNG project which had foundered on technological and economic shoals, we agree with the Commission's conclusion that there was no such obligation, either to Valley individually or to the customer group as a whole.

A. Interim General Service

Valley attempted to focus the argument on the cancellation, or more accurately, refusal to further extend, Interim General service. This position conveniently overlooks the fact that IG service was specifically intended as merely an interim measure "pending the completion of [the] . . . liquified natural gas facilities."9 It was designed, for that interim period, "to avoid the expense of constructing peak shaving facilities by the New England customers who expected [LNG] . . . service."10 IG was quite obviously a necessary incentive for the customers to await completion of the larger centralized project, rather than proceeding with construction of decentralized plants. It also helped to insure the availability of adequate market support (at the originally proposed rates) to justify the central LNG project when it was to be completed.

The IG service was carefully tailored to this temporary purpose. Since the exact completion date of the in-ground project was uncertain, the related IG contracts were explicitly limited to a one year term; the Commission's certificates only "authorized [the IG] as a short-term temporary service on a year-to-year basis."11

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
487 F.2d 1189, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tennessee-gas-pipeline-company-a-division-of-tenneco-inc-v-federal-power-cadc-1973.