Bales v. Delhi-Taylor Oil Corporation

362 S.W.2d 388, 17 Oil & Gas Rep. 811, 1962 Tex. App. LEXIS 1977
CourtCourt of Appeals of Texas
DecidedNovember 7, 1962
Docket14000
StatusPublished
Cited by15 cases

This text of 362 S.W.2d 388 (Bales v. Delhi-Taylor Oil Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bales v. Delhi-Taylor Oil Corporation, 362 S.W.2d 388, 17 Oil & Gas Rep. 811, 1962 Tex. App. LEXIS 1977 (Tex. Ct. App. 1962).

Opinion

BARROW, Justice.

This suit was brought by appellants, M. K. Bales and other landowners, to terminate certain oil, gas and mineral leases on land in the Bales Gas Unit for the alleged failure of lessees to produce oil or gas in paying quantities after expiration of the primary terms of the leases. Appellees are Delhi-Taylor Oil Corporation and Mayfair Minerals, Inc., each being the owner of an undivided one-half interest in the leases. Judgment was rendered in favor of appel-lees based upon favorable findings by the jury.

*390 The jury found substantially as follows: (1) a reasonably prudent operator acting under similar circumstances would not have ceased producing the Bales No. 1 well from the 10,600 foot sand sooner than appellees did, considering only the profits to be realized from this sand; (2) ninety days would be a reasonable period of time within which lessees should be allowed to commence reworking operations after the date upon which a reasonably prudent operator would have ceased producing from the 10,600 foot sand; and (3) appellees commenced reworking operations on January 23, 1959.

Appellants assert that as a matter of law the leases had terminated for non-profitable production and that the leases had not been continued in force through drilling or reworking operations. In the alternative, appellants say that the findings of the jury on each issue are so against the great weight and preponderance of the evidence as to reflect passion and prejudice on the part of the jury. In connection with Issue No. 1, appellants assert that the trial court erred in instructing the jury not to consider as an expense any charge for depreciation of the equipment on said well.

Sixteen leases are unitized under the Bales Gas Unit. Most of the leases are for a primary term of five years and as long thereafter as oil, gas or other mineral is produced from said land or unitized area, and as long as operations are prosecuted under the terms of each lease. There are several different lease forms involved, but each provides substantially that if after discovery of oil or gas the production thereof should cease from any cause, the lease shall not terminate if lessees commence additional drilling or reworking operations or, if it be within the primary term, commence or resume the payment or tender of rentals on or before the rental paying date next ensuing after the expiration of three (four) months from date of completion of a dry hole or cessation of production.

The Bales No. 1 well, which was completed on May 24, 1952, in the 10,600 foot sand, was the only well in said unit. This was a good well and although the reservoir began to be depleted near the middle of 1958, appellants concede that the well operated at a profit until September, 1958. The income from the well, and the lease and plant expenses subsequent to August, 1958, are as follows:

Appellants urge, however, that a depreciation expense of $365.00 each month should have been included. This would result in a net loss for each month after August, 1958, although a net profit was earned for the period from January, 1958, through March, 1959. Appellants’ witness Walker, a certified public accountant, testified that the useful life of the equipment on this well was fifteen years, with a salvage value of. ten per cent. Walker had never seen the equipment or the well site, and admitted that his figures bore no relation to the actual or market value of the equipment. He testified that the figures were assigned on the basis of his own accounting experience as to the normal useful life of similar equipment.

It is well settled that a habendum clause containing the language, “and as long *391 thereafter as oil, gas or other mineral is produced,” means “produced in paying quantities.” Further, if a well pays a profit, even small, over operating expenses, it produces in paying quantities, though it may never repay its costs, and the enterprise as a whole may prove unprofitable. Garcia v. King, 139 Tex. 578, 164 S.W.2d 509.

In order to terminate the leases, it was necessary for appellants to establish two propositions: first, that appellees were not making a profit from operation of the well; and, second, that a reasonably prudent operator would not have continued to operate the well under similar circumstances. Skelly Oil Co. v. Archer, Tex., 356 S.W.2d 774; Clifton v. Koontz, 160 Tex. 82, 325 S.W. 2d 684, 79 A.L.R.2d 774. The Supreme Court in Clifton v. Koontz emphasized that there can be no limit as to time, whether it be days, weeks, or months, to be taken into consideration in determining the question of whether paying production from the lease has ceased. In the case of a marginal well, the standard by which paying quantities is determined is whether or not, under all the relevant circumstances, a reasonably prudent operator would, for the purpose of making a profit and not merely for speculation, continue to operate the well. Further, the Supreme Court there held that several factors are to be considered in addition to net profit; one being the depletion of the reservoir.

We do not believe that appellants established, as a matter of law, either of these propositions necessary for a finding that the leases were terminated. Appellants concede that the issue of speculation is not in the case. If the item of depreciation was omitted, the well showed a profit each month through December, 1958. There is evidence to support the implied finding that appel-lees were prudent in draining this reservoir before abandoning it. The successful production record of the well was another factor to be considered in determining when the well should be shut in. There is evidence that the well declined very rapidly in January, 1959. In December, 1958, ap-pellees began to consider recompleting the well in another sand and contacted a contractor to discuss the cost. On January 23, 1959, appellees blew the well to get liquids out of the well bore, in an attempt to increase production. On January 26th, appel-lees secured a bid from a contractor and approved the expenditure of funds to re-complete the well in 10,500 foot sand. Some preliminary work was done before the contractor moved on the premises on March 14th. The well was satisfactorily completed in the 10,500 foot sand on April 9, 1959.

Appellants made no objection to the instruction under Issue No. 1, not to consider depreciation as an expense, and in fact requested this issue and instruction. Appellants also requested another issue and instruction which allowed depreciation to be considered. They do not complain of the failure of the court to submit their second requested issue and instruction. Appellants waived their objections to the instruction in the submitted issue by their failure to object to same. Rule 274, T.R. C.P. Furthermore, they cannot complain ot their own requested instruction and issue. City of Dallas v. Priolo, 150 Tex. 423, 242 S.W.2d 176; Northeast Texas Motor Lines v. Hodges, 138 Tex. 280, 158 S.W.2d 487; John Hancock Mut. Life Ins. Co. v. Brennan, Tex.Civ.App.,

Related

Avila v. State
252 S.W.3d 632 (Court of Appeals of Texas, 2008)
Cannon v. Sun-Key Oil Co., Inc.
117 S.W.3d 416 (Court of Appeals of Texas, 2003)
Ernest Cannon v. Sun-Key Oil Co., Inc.
Court of Appeals of Texas, 2003
Evans v. Gulf Oil Corp.
840 S.W.2d 500 (Court of Appeals of Texas, 1992)
Michigan Wisconsin Pipeline Co. v. Michigan National Bank
118 Mich. App. 74 (Michigan Court of Appeals, 1982)
Mi. Wis. Pipe. Co. v. Mi. Nat'l Bank
324 N.W.2d 541 (Michigan Court of Appeals, 1982)
Hartfiel v. Owen
618 S.W.2d 902 (Court of Appeals of Texas, 1981)
Stewart v. Amerada Hess Corp.
1979 OK 145 (Supreme Court of Oklahoma, 1979)
Bank of North America v. Bluewater Maintenance, Inc.
578 S.W.2d 841 (Court of Appeals of Texas, 1979)
Corpus Christi National Bank v. Gerdes
551 S.W.2d 521 (Court of Appeals of Texas, 1977)
Wilson v. Century Papers, Inc.
397 S.W.2d 314 (Court of Appeals of Texas, 1965)
Missouri-Kansas-Texas RR. Co. v. Shelton
383 S.W.2d 842 (Court of Appeals of Texas, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
362 S.W.2d 388, 17 Oil & Gas Rep. 811, 1962 Tex. App. LEXIS 1977, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bales-v-delhi-taylor-oil-corporation-texapp-1962.