Cannon v. Sun-Key Oil Co., Inc.

117 S.W.3d 416, 2003 WL 22025908
CourtCourt of Appeals of Texas
DecidedNovember 6, 2003
Docket11-02-00286-CV
StatusPublished
Cited by14 cases

This text of 117 S.W.3d 416 (Cannon v. Sun-Key Oil Co., Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cannon v. Sun-Key Oil Co., Inc., 117 S.W.3d 416, 2003 WL 22025908 (Tex. Ct. App. 2003).

Opinion

Opinion

W.G. ARNOT, III, Chief Justice.

Ernest Cannon sought a declaratory judgment terminating an oil and gas lease *418 covering a 352-acre production unit. In his petition, Cannon alleged alternative theories for termination: (1) “total cessation of production” after the primary term and (2) a “cessation of production in paying quantities” after the primary term. Sun-Key Oil Co., Inc., the lessee by assignment, asserted that the lease never terminated. Alternatively, Sun-Key asserted that Cannon revived the lease after the alleged termination by recognizing its validity in letters that he sent to Sun-Key and another entity.

Cannon’s “total cessation of production” theory was not submitted to the jury. Cannon’s “cessation of production in paying quantities” theory was submitted in Question Nos. 1 and 2. The jury answered Question Nos. 1 and 2 in Cannon’s favor, but also found that Cannon had revived the lease in response to Question No. 6. Based on the jury’s finding of revivor, the trial court entered judgment that Cannon take nothing on his claim for declaratory judgment. The trial court awarded Sun-Key the amount of $10,000 in attorney’s fees. In his appeal, Cannon asserts that there was no evidence to support the jury’s finding of revivor. In a cross-point, Sun-Key maintains that there was no evidence to support the jury’s finding in response to Question No. 2 that a reasonably prudent operator would not have continued to operate the lease as it related to the Parkey No. 1 Well in the manner in which it was operated for the purpose of making a profit and not merely for speculation. We agree with Cannon that there was no evidence to support the jury’s finding of revi-vor. However, we find that there was no evidence to support the jury’s finding in response to Question No. 2. Therefore, we sustain Sun-Key’s cross-point and affirm the trial court’s judgment.

Background Facts

Cannon owns the surface estate and one-half (½) of the mineral estate of approximately 6,034.79 acres known as the Parkey Ranch in Erath County. In 1973, Cannon’s predecessors-in-title, as lessors, entered into an oil and gas lease covering 6,518 acres, including the Parkey Ranch. The lease created 11 units within the 6,518 acres and provided that “each unit will be independent of the other units as though covered by a separate lease.” The lease had a primary term of five (5) years and a secondary term for “as long thereafter as oil or gas is produced therefrom, subject to the conditions as hereinafter provided.”

In 1978, the lessee completed the Par-key No. 1 Well on one of the units covered by the lease. The Parkey No. 1 Well produced gas, and the lessee designated the well as the Parkey Ranch Unit No. 1, Well No. 1 production unit covering 352 acres. This 352-acre unit is the subject of this cause. We will refer to the 1973 lease as it relates to the subject 352 acres as the Lease.

In 1994, D and N Natural Gas Operating Co., Inc. received an assignment of the Lease from the lessee and began operating the Parkey No. 1 Well. The Parkey No. 1 Well continued to produce gas and make a profit, but required substantial monthly compressor costs for production. With the agreement of James R. Parkey, Jr., D and N decided to build a new pipeline on the Parkey Ranch, with plans to have 16 wells feed into the pipeline, including the Parkey No. 1 Well and three other wells operated by D and N on the Parkey Ranch. One benefit of the planned pipeline was that D and N would no longer have to incur substantial compressor costs to produce the Parkey No. 1 Well.

In October 1995, D and N shut down the Parkey No. 1 Well in connection with the decision to build the pipeline but planned to resume production from the well after *419 completion of the pipeline. After completing the pipeline in May 1996, D and N attempted to resume production from the well, but it would not produce. D and N conducted various operations to determine the cause of the problem. In June 1997, D and N discovered a hole in one of the drill collars on the well. D and N replaced the drill collar, and the well began producing immediately. D and N connected the well to the new pipeline.

In August 1997, Cannon purchased his interest in the Parkey Ranch. In 1998, D and N assigned its undivided interest in the Lease to Sun-Key. Sun-Key began operating the Parkey No. 1 Well. Thereafter, Cannon filed this action, alleging that the Lease terminated during D and N’s operation of the well.

Issues Presented

In three issues, Cannon asserts that (1) the trial court erred in submitting Sun-Key’s revivor defense to the jury because there was no evidence to support its submission, (2) the trial court erred in its submission of the revivor question by failing to submit proper instructions of the requirements of revivor, and (3) Sun-Key is not entitled to recover attorney’s fees if this court sustains his revivor issues because Sun-Key would no longer be the successful party. In a cross-point, Sun-Key asserts that the trial court erred in denying its motion for judgment notwithstanding the verdict because there was no evidence to support the jury’s finding in response to Question No. 2 that a reasonably prudent operator would not have continued to operate the Lease in the manner in which it was operated. Therefore, Sun-Key contends that the Lease did not terminate.

We sustain Sun-Key’s cross-point and, therefore, find that the Lease did not terminate. We address the revivor issue, however, because Sun-Key presented the revivor defense as an alternative ground for finding that the Lease is in effect.

Revivor

Sun-Key had the burden of proof on its defense that Cannon revived the lease. Cannon asserts that there was no evidence to support the submission of the revivor issue to the jury. To address Cannon’s “legal sufficiency” or “no evidence” challenge, we must consider only the evidence and inferences that tend to support the finding, disregarding any evidence or inferences to the contrary. Southwest Key Program, Inc. v. Gil-Perez, 81 S.W.3d 269, 274 (Tex.2002); Garza v. Alviar, 395 S.W.2d 821, 823 (Tex.1965); see Merrell Dow Pharmaceuticals, Inc. v. Havner, 953 S.W.2d 706, 711 (Tex.1997), cert. den’d, 523 U.S. 1119, 118 S.Ct. 1799, 140 L.Ed.2d 939 (1998). An appellate court will sustain a no-evidence issue when: (1) the record discloses a complete absence of evidence of a vital fact; (2) the court is barred by rules of law or of evidence from giving weight to the only evidence offered to prove a vital fact; (3) the only evidence offered to prove a vital fact is no more than a mere scintilla; or (4) the evidence establishes conclusively the opposite of a vital fact. Uniroyal Goodrich Tire Company v. Martinez, 977 S.W.2d 328, 334 (Tex.1998). If there is any evidence to support the finding, we must overrule the no-evidence point.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
117 S.W.3d 416, 2003 WL 22025908, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cannon-v-sun-key-oil-co-inc-texapp-2003.