Arrowhead Global Solutions, Inc. v. Datapath, Inc.

166 F. App'x 39
CourtCourt of Appeals for the Fourth Circuit
DecidedFebruary 3, 2006
Docket04-2000, 04-2298, 05-1169
StatusUnpublished
Cited by9 cases

This text of 166 F. App'x 39 (Arrowhead Global Solutions, Inc. v. Datapath, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Arrowhead Global Solutions, Inc. v. Datapath, Inc., 166 F. App'x 39 (4th Cir. 2006).

Opinion

PER CURIAM:

“Arbitration can be an effective way to resolve a dispute in less time, at less expense, and with less rancor than litigating in the courts.” Publicis Commc’n v. True North Commc’ns., 206 F.3d 725, 727 (7th Cir.2000). Unfortunately, that truism does not apply in the present case. Appellant, Arrowhead Global Solutions, Inc. (“AGS”), and their former subcontractor, Appellee, Datapath, Inc. (“Datapath”), present this court with a combination of three separate appeals (and assorted motions) all stemming from an acrimonious business arbitration between the parties.

Datapath alleged that AGS breached a contract between the parties and demanded arbitration, which was commenced pursuant to the contract. The resulting arbitration and subsequent litigation led to three separate appeals. First, the arbitrators made an award of immediate equitable relief (hereinafter the “Phase I Award”) in favor of Datapath, enjoining AGS from performing certain work. The district court confirmed the Phase I Award. That confirmation is referred to as the “Confirmation Order.” AGS appeals the Confirmation Order as No. 04-2000, arguing that the Phase I Award should not have been confirmed both because it was interlocutory and because it was wrongly decided on its merits.

While AGS was appealing the Confirmation Order, Datapath moved in the district court to hold AGS in contempt of the Confirmation Order. The district court, instead of ruling on this motion, decided to remand the issue to the arbitrators to *42 “clarify” their Phase I Award. The parties refer to this decision as the “Remand Order,” and AGS appeals it as No. 04-2298. Datapath moves to dismiss No. 04-2298 for a lack of appellate jurisdiction.

Subsequently, the arbitrators ruled in Datapath’s favor regarding damages in the case (hereinafter the “Phase II Award”). The district court confirmed the Phase II Award, and AGS appeals that confirmation as No. 05-1169.

For the reasons set forth below, we hold as follows: 1) in No. 04-2000, that the district court did have authority under the Federal Arbitration Act (“FAA”) to confirm the Phase I Award and that the district court did not err in confirming that Phase I Award on its merits; 2) in No. 04-2298, that the panel does not have appellate jurisdiction over the appeal because the Remand Order is not a final order properly on appeal; and 3) in No. 05-1169, that the district court did not err in confirming the Phase II Award.

I.

AGS designs, builds, and operates satellite and telecommunications networks. AGS has a “Prime Contract” with the Defense Information Systems Agency (“DISA”), which allows AGS to bid for specific “tasks” from the DISA. When AGS is awarded a task, it executes a more specific contract with DISA called a “Task Order.”

AGS used Datapath as a subcontractor on a successful bid to DISA that eventually became Task Order 27. Task Order 27 required AGS to provide DISA with fourteen teleports — a complicated satellite receiving device. The subcontract (hereinafter “Subcontract”) between AGS and Datapath stated that Datapath would supply, install, and test the teleports and AGS would manage the work. The Subcontract contained nondisclosure agreements that limited AGS’s use of Data-path’s protected, proprietary information. The Subcontract also contained an arbitration clause.

While Task Order 27 was being completed, DISA solicited a proposal from AGS for additional teleports. AGS’s proposal was accepted, and this additional work was called “Annex E.” AGS did not, however, award a subcontract for the Annex E work to Datapath. Instead, AGS gave the work to Psi Systems, an entity partly owned by AGS. Based on AGS’s actions, Datapath moved for arbitration pursuant to the mandatory arbitration clause of the Subcontract.

At arbitration, Datapath alleged that AGS was acting in breach of the Subcontract by sharing Datapath’s information with a third party — Psi Systems. Data-path sought immediate equitable relief in the nature of a preliminary injunction, ordering AGS to cease its work with Psi Systems. The arbitrators bifurcated the arbitration into Phase I (the immediate equitable relief) and Phase II (liability and damages).

The arbitrators ruled in Datapath’s favor in the Phase I proceedings and issued an award enjoining AGS from working with Psi Systems. 1 Datapath then moved to have the district court confirm this Phase I Award to give it the force and *43 effect of a court order. After some initial hesitation, the district court confirmed the Phase I Award; the parties refer to that order as the Confirmation Order. AGS appealed the Confirmation Order to this court as No. 04-2000, arguing both that the district court did not have the authority to confirm the Award because it was interlocutory, and that the arbitrators erred in deciding the merits of the Phase I Award.

While the No. 04-2000 appeal was ongoing, Datapath alleged that AGS was continuing to work with Psi Systems and moved in the district court to find AGS in contempt of the Confirmation Order. Instead of deciding whether AGS was in contempt of the Confirmation Order, the district court remanded the issue to the arbitrators to “clarify” the Confirmation Order — the so called “Remand Order.” AGS appeals the Remand Order as No. 04-2298. Datapath moves to dismiss this appeal for a lack of appellate jurisdiction.

Finally, the arbitrators decided the Phase II section of the arbitration in Data-path’s favor and awarded damages of $2,125,799.90, which included $917,499 of lost profits on the Annex E work. The district court confirmed the Phase II Award, and AGS appeals it as No. 05-1169.

II.

We review the district court decisions to confirm the arbitration award de novo. Peoples Sec. Life Ins. Co. v. Monumental Life Ins. Co., 991 F.2d 141, 145 (4th Cir.1993). Both we and the district court are confined by the federal law favoring arbitration agreements. Courts are allowed to vacate arbitration awards only if they meet the narrow statutory factors set forth in 9 U.S.C. § 10(a) or if the award demonstrates a “ ‘manifest disregard’ of applicable law.” Gallus Investments, L.P. v. Pudgie’s Famous Chicken, 134 F.3d 231, 233-34 (4th Cir.1998). More specifically,

[A] court’s belief that an arbitrator misapplied the law will not justify vacation of an arbitral award. Rather, appellant is required to show that the arbitrators were aware of the law, understood it correctly, found it applicable to the case before them, and yet chose to ignore it in propounding their decision.

Remmey v. PaineWebber, Inc., 32 F.3d 143, 149 (4th Cir.1994).

III.

We first review No. 04-2000, the appeal of the Confirmation Order. This appeal raises two issues.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
166 F. App'x 39, Counsel Stack Legal Research, https://law.counselstack.com/opinion/arrowhead-global-solutions-inc-v-datapath-inc-ca4-2006.