Apex Metal Stamping Co. v. Alexander & Sawyer, Inc.

138 A.2d 568, 48 N.J. Super. 476, 1958 N.J. Super. LEXIS 324
CourtNew Jersey Superior Court Appellate Division
DecidedJanuary 22, 1958
StatusPublished
Cited by24 cases

This text of 138 A.2d 568 (Apex Metal Stamping Co. v. Alexander & Sawyer, Inc.) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Apex Metal Stamping Co. v. Alexander & Sawyer, Inc., 138 A.2d 568, 48 N.J. Super. 476, 1958 N.J. Super. LEXIS 324 (N.J. Ct. App. 1958).

Opinion

The opinion of the court was delivered by

Ereund, J. A. D.

The defendant appeals from a judgment of $6,993.56, including interest and costs, entered by the trial court sitting without a jury, in a contract action where the plaintiff was precluded by the defendant from fully performing its agreement to manufacture 75,000 tire [479]*479stands. The grounds of appeal relate primarily to the quantum of damage.

The plaintiff, at the time of the inception and breach of the agreement here involved, was a partnership. Milton Tepfer, formerly a partner, and now secretary and treasurer of the plaintiff successor corporation, testified concerning the contract obligations between the litigants.

The testimony of Milton Tepfer disclosed that the agreed contract price for each tire stand was $.435. Each item of the product was manufactured in two identical parts, and the cost of production of each half was given as follows:

Materials
Steel $.0082
Paint .0398
2 screws and 2 nuts .00816
Carton and paper .00217
Labor
Shear blanks .0012
1st press operation .0018
2nd press operation .002
3rd press operation .004
Packing and strapping .002
Overhead (at 25% of labor cost) .00275
Total (%) $.12208
x 2
$.24416 for each unit

However, this witness made an arithmetical error in reaching a sum on these figures when he said that the cost for each tire stand was $.23264. The trial judge was misled into accepting the same erroneous figure.

On cross-examination Tepfer said that the overhead percentage allocation factor (25% of labor cost dollars) was given to him by his accountant Kosenthal, but he stated he knew of his own knowledge how it was computed, and that it included the rent and light of the plant and a salary of $160 a week to his brother Albert Tepfer, a partner who was engaged in the plant as a general supervisor. He did not know whether workmen’s compensation insurance, unem[480]*480ployment and social security taxes and fire insurance were included in the overhead costs. The office administration and selling expenses were not reflected in the overhead computation. There was no descriptive testimony of the duties of any of the employees.

The accountant testified that his estimation of the overhead figure for the period during which this contract was being performed (March and April 1955) was 30% of labor costs, which would amount to a difference in the total cost of an additional $56.21 from a computation based on the 25% factor given by Tepfer. Defendant contends the difference would be several hundred dollars. Rosenthal testified, further, that the estimated overhead percentage included rent, light, heat, power, die write-offs, insurance and taxes, but did not include salaries paid to either partner, since good accounting practice did not generally call for this computation in factory overhead. Eor were the amounts paid to the bookkeeper reflected in the cost estimate because, the accountant testified, he did not “perform any cost operation.”

At one point during the performance of the contract, when the plaintiff had completed 23,900 tire stands, the dies used in the operation were returned to the defendant. This was done, said Tepfer, because the defendant expected the ultimate purchaser of the product to inspect its plant and wanted it to appear that the product was being manufactured there. A memorandum bill was sent with the dies, indicating a net price of $2,000 as their cost. The bill further included the following statement: “Tire stand dies on memo. Dies to be returned to Apex.”

As part of the factual contention in the pretrial order, the plaintiff claimed that it agreed, at the defendant’s request after 22,000 items had been shipped, to cancel the balance of the order if the defendant would return the dies and pay plaintiff $2,000, and that this offer was rejected by the defendant.

During March and April 1955 the plaintiff shipped 23,900 tire stands to defendant and received payment therefor. [481]*481Subsequently, after the defendant had obtained possession of the dies, it manufactured the tire stands for itself as needed. It is conceded that defendant breached the agreement which prevented plaintiff from completing the order for the balance of 51,100 tire stands. Prom the testimony it appears that the date of expected completion of plaintiff’s performance was November 1, 1955.

The defendant argues several grounds for reversal, all pertaining to the measure of damages: that the proof of loss of profits was uncertain; error in awarding damages in excess of $2,000, on the theory of rescission; failure to give credit for the release from care, trouble and risk incident to completion of the contract; failure to include the value of services of the partners in the cost of production ; and, finally, the award of interest.

Preliminarily, we noted above that there was a simple mathematical error in adding the figures used by the plaintiff in its computation of cost, arriving at a figure of $.23264 instead of $.24416 for the cost of each tire stand. The greater expense would have resulted in an additional $588.67 cost for 51,100 units, and automatically loss profit by that amount. Were this the sole problem presented on this appeal, wo could, of course, exercise our original jurisdiction to correct such plain error. B. R. l:5-3(c); R. B. 1 :o~4(a); B. R. 2 :5. However, insofar as these cost figures depend upon determination of the substantive question of what may properly be allocated to the cost of production and whether the trial court properly accepted Tepfer’s 25% allocation factor for overhead, we must proceed to consider the stated grounds of appeal which include these matters.

The defendant’s argument that plaintiff’s damages were uncertain and insufficient so as to preclude an award is without merit. In discussing this question, it is necessary to distinguish between uncertainty as to the fact of damage and uncertainty as to its amount. See 5 Willision, Contracts, {rev. ed. 1937), § 1346, p. 3778; 5 Corbin, Contracts (1951), § 1022, p. 119; Restatement, Contracts, § 331(1), p. 515, comment {a) (1932); Annotation, [482]*482“Uncertainty as to Damages ” 78 A. L. R. 858 (1933). The facts in the instant ease clearly establish that damage did result; the amount of the loss may be calculated with reasonable certainty, though not precisely. Where it is certain that damage has resulted and the evidence affords a basis for estimating the damage with some degree of certainty, recovery is allowed. Wolcott, Johnson & Co. v. Mount, 36 N. J. L. 262, 269-270, 272 (Sup. Ct. 1873), affirmed 38 N. J. L. 496, 501 (E. & A. 1875); Weiss v. Revenue B. & L. Assn., 116 N. J. L. 308, 310 (E. & A. 1936); Tessmar v. Grosner, 23 N. J. 193, 203 (1957).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rsb Lab. Services, Inc. v. Bsi Corp.
847 A.2d 599 (New Jersey Superior Court App Division, 2004)
Magnet Resources v. Summit MRI, Inc.
723 A.2d 976 (New Jersey Superior Court App Division, 1998)
Sons of Thunder, Inc. v. Borden, Inc.
690 A.2d 575 (Supreme Court of New Jersey, 1997)
Platinum Management v. Dahms
666 A.2d 1028 (New Jersey Superior Court App Division, 1995)
JL Davis & Associates v. Heidler
622 A.2d 923 (New Jersey Superior Court App Division, 1993)
AM/PM Franchise Ass'n v. Atlantic Richfield Co.
584 A.2d 915 (Supreme Court of Pennsylvania, 1990)
Roblin Hope Industries, Inc. v. J. A. Sullivan Corp.
413 N.E.2d 1134 (Massachusetts Appeals Court, 1980)
Paris of Wayne, Inc. v. Richard A. Hajjar Agency
416 A.2d 436 (New Jersey Superior Court App Division, 1980)
Seaman v. US Steel Corporation
400 A.2d 90 (New Jersey Superior Court App Division, 1979)
Landreth v. Barnard & Kinney, Inc.
561 P.2d 631 (Oregon Supreme Court, 1977)
Cardell, Inc. v. Tp. of Woodbridge
280 A.2d 203 (New Jersey Superior Court App Division, 1971)
Raymond v. Cregar
178 A.2d 29 (New Jersey Superior Court App Division, 1962)
In Re Rinehart
175 A.2d 669 (New Jersey Superior Court App Division, 1961)
Abel v. Elizabeth Bd. of Works
164 A.2d 764 (New Jersey Superior Court App Division, 1960)
Feinbloom v. Camden Fire Ins. Co.
149 A.2d 616 (New Jersey Superior Court App Division, 1959)

Cite This Page — Counsel Stack

Bluebook (online)
138 A.2d 568, 48 N.J. Super. 476, 1958 N.J. Super. LEXIS 324, Counsel Stack Legal Research, https://law.counselstack.com/opinion/apex-metal-stamping-co-v-alexander-sawyer-inc-njsuperctappdiv-1958.