Seymour T. Partridge v. Norair Engineering Corporation, a Corporation, Norair Engineering Corporation, a Corporation v. Seymour T. Partridge

301 F.2d 247
CourtCourt of Appeals for the D.C. Circuit
DecidedMarch 19, 1962
Docket16400, 16416
StatusPublished
Cited by8 cases

This text of 301 F.2d 247 (Seymour T. Partridge v. Norair Engineering Corporation, a Corporation, Norair Engineering Corporation, a Corporation v. Seymour T. Partridge) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Seymour T. Partridge v. Norair Engineering Corporation, a Corporation, Norair Engineering Corporation, a Corporation v. Seymour T. Partridge, 301 F.2d 247 (D.C. Cir. 1962).

Opinions

WILBUR K. MILLER, Chief Judge.

Norair Engineering Corporation, general contractor for the construction of a large building for the Smithsonian Institution, entered into a contract with the Partridge partnership by the terms of which the latter was to furnish the former with a competent mechanical engineer for specialized work on the Smithsonian construction for a term of one year from January 15, 1960. The contract price was $7.50 an hour, which in-' eluded personal supervision by a Partridge partner, if that should become necessary. It was agreed that if the engineer so furnished were found incompetent by Norair within two months after the beginning of the relationship, Part[248]*248ridge would furnish a competent man in his stead, and its failure to do so within two weeks after notice would justify cancellation of the contract.

Early in April, 1960, when more than two months had elapsed, Norair advised Partridge that the work was unsatisfactory, and on April 26 gave written notice of cancellation. Partridge was paid for the period ending April 29, but furnished 26 hours of service from May 2 to May 5, both inclusive, for which it was not paid.

Partridge sued Norair on August 23, 1960, in the United States District Court. In its complaint the partnership alleged that, notwithstanding its competent performance of its obligations, Norair had wrongfully terminated the contract. It sought damages in the sum of $6,753.30. This amount was reduced in the pretrial proceedings, however, when Partridge asked damages of $5,264.55, which it itemized as follows:

“Services performed May 2, 1960 to May 5, 1960—26 hours at $7.50 per hour. $195.00

“Two weeks’ notice to employee, 80 hours at $7.50 [per hour] 600.00 1

“Profit on balance of contract, 1366 man hours, at $3,272 per man hour 4,469.55”

After hearing evidence, during the presentation of which numerous exhibits were introduced, the trial judge, sitting without a jury, made findings of fact which included the following:

“2. On December 7, 1959, Seymour T. Partridge & Co. addressed a ‘proposal’ to defendant in which it was stated that ‘These services are to be furnished by our company to your company on a contract basis and there will be no employer-employee relationship between us.’ On December 11, 1959, the parties signed an ‘Order’ which referred to and incorporated the ‘proposal’ of December 7, 1959, stating ‘This is an acceptance of your proposal of December 7, 1959 in general, but specifically as outlined in this order/ Under the terms of these documents, the plaintiffs were to furnish a competent mechanical engineer and draftsman to take over the detailed layout of the mechanical work on the project. His services were to. be furnished at $7.50 per hour, including any Workmen’s Compensation, Social Security, Unemployment, or other employees’ taxes. Payments were to be made monthly as the bills were presented. The plaintiffs were to personally supervise the engineer’s work, if necessary, at no additional cost. The agreement was to be for one year, commencing January 15, 1960, and the defendant was to guarantee a minimum of forty hours per week in work during this period.
* *-»*•*•*
“5. On the 15th day of January, 1960, the plaintiffs began their work, and one Elmer R. Stange was employed as the mechanical engineer and draftsman to take over the detailed layout of the mechanical work on the project.
“6. Two months went by, during which period Mr. Stange, under the supervision of Mr. Partridge, did the coordination work; and the defendant did not notify either Partridge or Stange, or anyone else that it wanted to terminate Stange’s services. During this period, plaintiff Partridge spent, on occasion, eight hours per day at the job site supervising the work of Stange, and during the same period spent an average of four hours per day at the job site supervising the work of Stange. If the contract had continued to the expiration of its term, such supervision would have continued at the rate of four hours per day.
[249]*249“7. That the value of the super- , . vision time of plaintiff Partridge was $7.50 per hour.
“8. Thereafter, on the 5th day of May, 1960, the defendant terminated the contract by refusing to allow the plaintiffs or their employee to continue on the job. That at that time, the plaintiffs had performed labor under the contract from May 2nd to May 5th inclusive, for which they had not been paid. That the sum due for such services was $195.00.
“9. That upon the breach of the contract by the defendant the plaintiffs were required to give two weeks’ notice to the employee, Stange, becoming indebted to him in the amount of $320.00.
* * * * * *
“12. That there was no proper basis for the breach of the contract by the defendant.”

From these and other findings we think it unnecessary to reproduce, the- District Judge concluded: that the contract between the parties did not create the relation of employer and employee; that in this suit for lost profits, Partridge should recover the difference, if any, between the contract price of $7.50 per hour and the costs it would have incurred in completing its contractual obligations; that the time spent by Seymour T. Part,ridge in supervising the work for an average of four hours per day is properly includible as an item of cost to the partnership in performing the contract; and that there was no profit to the partnership after deducting the cost of supervision. He also concluded: “That the plaintiffs are entitled to recover from the defendant the costs of their performance from May 2, 1960 to May 5, 1960, in the amount of $195.00, and the cost of their two week notice to Stange in the amount of $320.00.” Accordingly, Partridge was awarded judgment against Norair for $515, with interest from January 15, 1961.

The Partridge partnership noted an appeal from the judgment “in favor of said Plaintiffs,” which we treat as a notice of appeal by the partnership from that part of the judgment which was unfavorable to it. This appeal bears our No. 16,400. Norair has also appealed, the case being No. 16,416.

I

In No. 16,416, Norair attacks as clearly erroneous the factual finding that Seymour T. Partridge, the supervising partner, and Elmer R. Stange, the engineer furnished by the partnership, properly performed the work required by the contract, and the finding that there was no proper basis for cancellation by Nor-air. The record contains conflicting evidence as to these matters. We cannot substitute our evaluation of it for that of the trial judge unless we are persuaded that he was plainly in error. As we cannot characterize his conclusions as clearly erroneous, it is necessary to affirm the judgment against Norair.

II

No. 16,400 is Partridge’s appeal from .the denial of its claim of $4,469.55 in damages for the loss of profit of $3,272 per hour on 1,366 hours which the engineer furnished by it would have worked had the contract not been cancelled. This alleged profit of $3,272 for each hour of his work was arrived at by subtracting from $7.50 — the price to be paid by Nor-air — the sum of $4,228 2 which Partridge conceived to be the cost of complying with the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
301 F.2d 247, Counsel Stack Legal Research, https://law.counselstack.com/opinion/seymour-t-partridge-v-norair-engineering-corporation-a-corporation-cadc-1962.