Johnson v. Wright

220 N.W. 946, 175 Minn. 236, 1928 Minn. LEXIS 863
CourtSupreme Court of Minnesota
DecidedJuly 20, 1928
DocketNo. 26,770.
StatusPublished
Cited by11 cases

This text of 220 N.W. 946 (Johnson v. Wright) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Johnson v. Wright, 220 N.W. 946, 175 Minn. 236, 1928 Minn. LEXIS 863 (Mich. 1928).

Opinion

Wilson, C. J.

Defendant appealed from an order denying his motion for a new trial.

Defendant and plaintiff Johnson, who live in St. Louis county, made a written contract wherein the former agreed to pay the latter $4.50 per foot for drilling for iron ore on defendant’s 300-acre tract of land in Canada. The contract specified that it should “cover approximately three thousand (3,000) feet of drilling; such drilling to be done in such locations and to such lengths as said first party [defendant] may direct.”

Johnson at considerable expense moved his equipment to Canada and located upon defendant’s land where he constructed camp buildings. He drilled one hole 600 feet deep, and then defendant, as determined by the jury, breached his contract.

In such partial performance of the contract plaintiff Johnson became indebted to five employes in the sum of $1,448.40. In order to secure the payment of this sum, he made an assignment of that amount of his earnings under the contract to O. T. Bundlie, who is joined with Johnson as a party plaintiff in this action to recover damages for breach of contract. Defendant stated in his written *238 consent to the assignment: “No liability attaches to me unless Johnson continues with the contract and earns money thereunder.” Fifty per cent of the earnings under the terms of the contract were to be paid to Bundlie until the indebtedness was paid. Defendant counterclaimed that Johnson had breached the contract, not he. There was a balance of about $1,100 unpaid to Johnson for work actually done.

It is claimed that there is a misjoinder of causes of action and parties plaintiff. The claim is that Bundlie received under the assignment only a right to participate in money earned in the performance of the contract and not in damages awarded for a breach thereof. In so far as the complaint is concerned, there was money earned in the partial performance of the contract though such money was absorbed in the verdict for damages for loss of profits because of the theory upon which the case was submitted to the jury. But that aside, we are of the opinion that the situation and relation of the parties and the assignment clearly show a constructive appropriation of a specified amount of the money coming from defendant to Johnson and arising out of the contract, including a breach thereof. It could hardly have been the intention of the parties to intend any such distinction. Natural justice and essential fairness, regardless of the words contemplating the usual and ordinary thing, command that we construe the instrument as an equitable assignment operative upon any money here involved.

But the argument is that the statute, G. S. 1928, § 9277, requires that the causes of action which may be joined must affect all parties to the action. To this proposition is cited Anderson v. Scandia Bank of Minneapolis, 53 Minn. 191, 54 N. W. 1062, in which the cause of action in behalf of the wife only contained essential ingredients not included in the joint cause of action. What is the cause of action here? It is the breach of the contract. There is but one cause of action. Bundlie in his representative capacity has acquired an interest therein. The proportion of such interest is not important to defendant. The plaintiffs, being interested in a single cause of action, may join in an action to recover thereon notwithstanding the fact that their interests are distinct and severable. *239 Carlton Co. Farmers Mut. F. Ins. Co. v. Foley Brothers, 111 Minn. 199, 126 N. W. 727.

According to the plaintiff’s evidence defendant breached the contract on April 18, 1927, by telling Johnson he could not do any more work. May 2, 1927, Johnson wired Wright charging such cancelation of the contract. On the same day Wright wrote Johnson a letter in strong language denying that he had canceled the contract. This letter and other evidence in the case were sufficient to have supported a finding that there was a withdrawal or renunciation of the breach, which defendant consistently denied making.

A contractor who has improvidently or unadvisedly refused to perform his contract may, before the other party has either manifested an election to rescind the contract or changed his position in reliance on the repudiation in such a way as to make performance more burdensome, retract the refusal and go on with the contract. 13 C. J. 657, § 732(g); 3 Williston, Contracts, § 1335, p. 2389.

This rule of law however is not applicable to the questions before this court. The answer denies the repudiation and does not plead a withdrawal or renunciation of the alleged breach. The court did not, in the charge to the jury, cover this question or make any reference thereto. Nor did defendant request any such charge or take any exception to the absence of appropriate instructions in reference thereto. The record presents nothing relative to this question for our consideration.

An assignment of error is directed at the proof of the loss of profits as the measure of damages. The claim is that upon the record they are speculative, uncertain, contingent, and not within the realm of reasonable certainty.

Anticipated profits may be recovered where they are shown to be the natural and probable consequences of the act or omission complained of and their amount is shown with a reasonable degree of certainty and exactness. This means that the nature of the business or venture upon which the anticipated profits are claimed must be such as to support an inference of definite profits grounded upon a reasonably sure basis of facts. Force v. Gottwald, 149 Minn. *240 268, 183 N. W. 356. This rule does not call for absolute certainty.

The argument is that Johnson could not reasonably foretell what success he would have in drilling 3,000 feet. If this contract called for 3,000 feet in one hole defendant’s argument would be quite convincing. Johnson admits that sometimes he makes a profit and sometimes he sustains a loss in projects of this character. That is true of all work. A driller’s success does not depend solely upon the character of the substance which he must penetrate. The deeper he goes the greater and heavier the load, the greater the strain and peril of breakage. But we must assume that the price contemplates and is commensurate with a certain amount of probable disappointment, trouble, and loss.

In this case Johnson-has made one hole 600 feet deep. He knows the character of the substance which he has gone through. It was not difficult. Johnson has had nearly 40 years’ experience as a driller. The parties intended to make the first hole 1,000 feet unless iron was found. Four hundred feet remained to be drilled. Does the situation permit a jury safely to find that Johnson could make a profit having in mind the possibility of trouble and loss before reaching such depth ? We think it does though the question is a close one. Johnson with his extensive experience contracted to drill 3,000 feet. He had an outfit with which he could go 2,500 feet. He apparently had no fear of finding impenetrable substance, and it is not suggested that such would be at all probable. Indeed no one suggested that such was even possible. The risk is apparently more closely connected with the possible breakage, which is the unusual and not the ordinary.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Edling v. Stanford Township
381 N.W.2d 881 (Court of Appeals of Minnesota, 1986)
Cardinal Consulting Co. v. Circo Resorts, Inc.
297 N.W.2d 260 (Supreme Court of Minnesota, 1980)
Frank Sullivan Company v. Midwest Sheet Metal Works
335 F.2d 33 (Eighth Circuit, 1964)
Midwest Sheet Metal Works v. Frank Sullivan Co.
215 F. Supp. 607 (D. Minnesota, 1963)
Cantrell v. Benefit Ass'n of Railway Employees
348 P.2d 345 (Montana Supreme Court, 1960)
Appliances, Inc. v. Queen Stove Works, Inc.
36 N.W.2d 121 (Supreme Court of Minnesota, 1949)
Appeal From Allowance of Livingston Claim
220 N.W. 946 (Supreme Court of Minnesota, 1928)

Cite This Page — Counsel Stack

Bluebook (online)
220 N.W. 946, 175 Minn. 236, 1928 Minn. LEXIS 863, Counsel Stack Legal Research, https://law.counselstack.com/opinion/johnson-v-wright-minn-1928.