Dick Weatherston's Associated Mechanical Services, Inc. v. Minnesota Mutual Life Insurance

100 N.W.2d 819, 257 Minn. 184, 82 A.L.R. 2d 1004, 1960 Minn. LEXIS 518
CourtSupreme Court of Minnesota
DecidedJanuary 22, 1960
Docket37,730
StatusPublished
Cited by21 cases

This text of 100 N.W.2d 819 (Dick Weatherston's Associated Mechanical Services, Inc. v. Minnesota Mutual Life Insurance) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dick Weatherston's Associated Mechanical Services, Inc. v. Minnesota Mutual Life Insurance, 100 N.W.2d 819, 257 Minn. 184, 82 A.L.R. 2d 1004, 1960 Minn. LEXIS 518 (Mich. 1960).

Opinion

Murphy, Justice.

This case comes to us on appeal from an order denying the defendant’s motion in the alternative for judgment notwithstanding the verdict or for a new trial. The plaintiff recovered a verdict in the sum of $5,691 in an action brought for breach of contract. The principal issue involved in this case requires a construction of M. S. A. 326.02 as it applies to the particular facts before us. We are asked to determine if a contract which includes professional engineering services is in violation of that statute and illegal so as to preclude recovery thereon under circumstances where the contractor is an unlicensed engineer whose services are rendered subject to the approval and supervision of an architect and engineer retained by the other party.

Viewing the record in the light most favorable to the verdict, the jury could have found these facts: The plaintiff’s assignor, Dick Weather-ston, at the time of the events involved in this action, was a contractor in the air-conditioning business. He had received a bachelor of science degree in mechanical engineering from the University of Michigan, after which he was employed by various companies, including General Mills and the Seeger Refrigerator Company, as a plant engineer. For some years before engaging in the contracting business in Minnesota he was employed as a project engineer, and in the course of that work he was registered in that profession under the laws of the States of Ohio and Texas. As a contractor he expected to receive work on projects designed and supervised by registered architects and engineers, and he stated in his testimony that in order to avoid a conflict of interest and to obviate the possibility of being considered a competitor with such architects and engineers he did not register as an engineer in Minnesota.

In the fall of 1956 the Minnesota Mutual Life Insurance Company *187 was in the process of completing the construction of a large home office building in St. Paul. They had retained as their architects the firm of Ellerbe & Company. It appears that during the process of construction of this building the company determined to install certain electronic computing equipment on one of the upper floors of the building. Because of the great amount of heat this machine would give off in operation, there arose a serious problem in providing ventilation and air conditioning in the particular area where the equipment was to be installed.

In the fall of 1956 certain officers of the defendant company discussed the problem with plaintiff. He was advised that the plans submitted by Ellerbe & Company as to this particular phase of the construction and installation would involve costs in excess of the budget set up by the company. They asked him if he would be in a position to give them a proposal, including a design and cost price, to solve the air-conditioning problem in the particular area involved. After being told that Ellerbe & Company were the architects and engineers retained by the builder, Weatherston informed the defendant through its officers that a large part of his business was derived from architectural firms and that if these firms knew that he engaged in designing and engineering work they would discontinue dealing with him. He told them accordingly that he could not compete with Ellerbe in designing the system, but he could submit plans if he obtained the contract for the entire installation. He was told that an arrangement had been made whereby Ellerbe had withdrawn from the “air conditioning phase” of the installation but that they would remain as “consultant” to supervise and approve the system used. Weatherston agreed to this arrangement.

Preliminary plans and specifications were drawn up by Weatherston and submitted to the company with an offer about January 1, 1957. When these plans were submitted to the officers of the defendant company, Weatherston again explained that he was a contractor and did not want to conflict with Ellerbe in doing designing or engineering work. He was told that the company understood his position and that the plans submitted by him would have to be approved by Ellerbe. *188 After some discussion and examination of his proposals, another plan was drawn up and submitted with a new offer for approval by Ellerbe & Company. Later, modifications were made which were suggested by Ellerbe and a final proposal appears to have been submitted sometime in February 1957. During the course of these negotiations there were at least three conferences with Ellerbe & Company, the defendant’s architects. The final plan, except for some minor changes, proved satisfactory to Ellerbe & Company, and after a meeting at their office, it was agreed that the plaintiff would install the necessary equipment and furnish the materials for a price of $16,203. Weatherston testified that, after the final meeting with Ellerbe, the corporate officer who acted for the defendant company told him “to proceed with the work and get the equipment ordered, and then to, just to go ahead and get the job rolling.” In the proposals Weatherston submitted, the sales price of all component parts of the air-conditioning system was included. So far as appears from the record no charge for design or plan was made. Weatherston considered the contract as one for the sale of an entire system and none of his actions in submitting the proposals are inconsistent with that conclusion.

On March 2, 1957, about 2 weeks after Weatherston claims his plans were submitted and his offer was accepted, he was informed that the defendant company had determined to give the work to another air-conditioning contractor. No loss was sustained by the plaintiff in the purchase of materials specified for the job. He was able to cancel the orders before delivery. The work was finally performed by Holm-sten Refrigeration, Inc. It appears from the evidence that the latter company was not a registered architect or engineer.

There is a sharp conflict in the evidence in this case. The evidence of the defendant tended to show that no contract was ever entered into between the parties; that the plaintiff was one of a number of contractors invited to submit a bid or proposal setting forth the materials and labor he would furnish and the price he would charge for the proposed work; and that there was no acceptance of any proposal made by the plaintiff. On the other hand, there was evidence supporting the finding of the jury that an offer and acceptance con *189 stituting a valid contract had been made by the parties. Under the circumstances we are controlled by the well-established rule that conflicts are to be resolved upon appeal by stating the controlling facts as the jury, in the light of the whole evidence, reasonably could and must have found them in arriving at its verdict. An appellate court is controlled by this elementary rule even though it might have, on the basis of the record, reached a different conclusion. Hardy v. Anderson, 241 Minn. 478, 63 N. W. (2d) 814; 1 Dunnell, Dig. (3 ed.) § 415b; 14 Id. §§ 7144, 7159. Whether certain witnesses are worthy of belief is primarily for the jury and the trial court. Becker v. Thomson, 208 Minn. 332, 294 N. W. 214.

It is the contention of the defendant that the contract involved is one for professional engineering services and, since the plaintiff was unlicensed as an engineer, the contract is illegal so as to preclude recovery.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Isles Wellness, Inc. v. Progressive Northern Insurance Co.
725 N.W.2d 90 (Supreme Court of Minnesota, 2006)
Bolander v. Bolander
703 N.W.2d 529 (Court of Appeals of Minnesota, 2005)
Bock Clark v. Dept. Consumer Protection, No. Cv 01 0510100s (Apr. 3, 2002)
2002 Conn. Super. Ct. 4098 (Connecticut Superior Court, 2002)
Rolls v. Bliss & Nyitray, Inc.
408 So. 2d 229 (District Court of Appeal of Florida, 1982)
DELLWOOD ENTERPRISES v. Pac. Am. Real Estate Fund
505 F. Supp. 187 (D. Minnesota, 1981)
Martin Investors, Inc. v. Vander Bie
269 N.W.2d 868 (Supreme Court of Minnesota, 1978)
Town Planning & Engineering Associates, Inc. v. Amesbury Specialty Co.
342 N.E.2d 706 (Massachusetts Supreme Judicial Court, 1976)
H. O. Meyer Drilling Co. v. Alton v. Phillips Co.
468 P.2d 1008 (Court of Appeals of Washington, 1970)
Paske v. Liberty Equities Corp.
167 N.W.2d 30 (Supreme Court of Minnesota, 1969)
Scott-Daniels Properties, Inc. v. Dresser
160 N.W.2d 675 (Supreme Court of Minnesota, 1968)
The Telex Corporation v. D. E. Balch
382 F.2d 211 (Eighth Circuit, 1967)
MAGASINY ONIC DEVICES, INC. v. Precision Specialties, Inc.
221 A.2d 755 (New Jersey Superior Court App Division, 1966)
North Central Company v. Phelps Aero, Inc.
139 N.W.2d 258 (Supreme Court of Minnesota, 1965)
State v. Red Owl Stores, Inc.
115 N.W.2d 643 (Supreme Court of Minnesota, 1962)
Boswell v. Rio De Oro Uranium Mines, Inc.
362 P.2d 991 (New Mexico Supreme Court, 1961)

Cite This Page — Counsel Stack

Bluebook (online)
100 N.W.2d 819, 257 Minn. 184, 82 A.L.R. 2d 1004, 1960 Minn. LEXIS 518, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dick-weatherstons-associated-mechanical-services-inc-v-minnesota-mutual-minn-1960.