Paris of Wayne, Inc. v. Richard A. Hajjar Agency

416 A.2d 436, 174 N.J. Super. 310
CourtNew Jersey Superior Court Appellate Division
DecidedJune 4, 1980
StatusPublished
Cited by16 cases

This text of 416 A.2d 436 (Paris of Wayne, Inc. v. Richard A. Hajjar Agency) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Paris of Wayne, Inc. v. Richard A. Hajjar Agency, 416 A.2d 436, 174 N.J. Super. 310 (N.J. Ct. App. 1980).

Opinion

174 N.J. Super. 310 (1980)
416 A.2d 436

PARIS OF WAYNE, INC., A CORPORATION OF THE STATE OF NEW JERSEY, PLAINTIFF-RESPONDENT,
v.
RICHARD A. HAJJAR AGENCY AND LAWRENCE RUBIN, DEFENDANTS-APPELLANTS, AND ANDREW NESTICO, DEFENDANT.

Superior Court of New Jersey, Appellate Division.

Argued April 15, 1980.
Decided June 4, 1980.

*312 Before Judges CRANE, MILMED and KING.

Roger Kulka argued the cause for appellant Lawrence Rubin.

Paul D. Solomon argued the cause for appellant Richard A. Hajjar Agency (Solomon and Ramer, attorneys).

David Carmel argued the cause for respondent (Edwin C. Eastwood, Jr., of counsel and on the brief).

The opinion of the court was delivered by KING, J.A.D.

Plaintiff, a manufacturer of clothing, brought this suit against defendant Richard A. Hajjar Agency, a real estate broker, and defendant, Lawrence Rubin, its affiliated agent. Plaintiff alleged that defendants acted as its broker in the rental of a property at 1095 Ringwood Avenue, Wanaque, Passaic County. The property was located in a commercial zone and had been used previously as a supermarket. Shortly after plaintiff commenced its clothing manufacturing operation on August 1, 1977, it was told to stop production because manufacturing was not a permitted use of the property. After production was closed down, plaintiff claimed damage because orders could not be met.

The parties stipulated at trial that defendant Rubin was an agent of the Hajjar Agency and that he violated his professional duty to plaintiff by negotiating for a rental property at which plaintiff's contemplated activity, clothing manufacturing, as expressed in the lease which Rubin drew, was illegal. The question for the trial judge, sitting without a jury, was the extent of *313 plaintiff's entitlement to damages. The trial judge found defendants liable for the loss of the full income on four contracts which he found Rubin's negligence prevented plaintiff from completing and entered judgment in the amount of $58,900, which sum also included defendants' $300 broker's fee to plaintiff.

On the appeal appellants contend that the loss of income from interruption of manufacturing was not a proper element of damages because it was not within the fair contemplation of the parties at the time the brokerage contract was consummated. Defendants also argue that the verdict was against the weight of the evidence and that plaintiff failed to mitigate damages.

We recite the facts as we infer them to have been found by the trial judge. In early July 1977 plaintiff's principal, Karrell, who had 28 years' experience in the trade, and plaintiff's fashion designer Chaoui called the Hajjar Agency and spoke to defendant Rubin about renting space for plaintiff's clothing manufacturing operation. Rubin took them to an empty supermarket on Ringwood Avenue in Wanaque which they agreed to rent for $300 a month. On July 27 a handwritten lease prepared by Rubin on an Hajjar Agency form was executed. The lease commenced on August 1 for three months, thereafter to continue month-to-month. Plaintiff paid defendants' broker's fee of $300 and the first month's rental upon execution of the lease.

On July 28 plaintiff installed four sewing machines, a cutting table, an electric scissors and six mannequins, and commenced operation. About 12 days thereafter the building inspector came to the premises and directed plaintiff's personnel to cease operations because of a violation of the local land use ordinance. When this happened Rubin assured Karrell and Chaoui that he knew the mayor and that everything would be all right. Karrell testified that Rubin called back three days later and said that work could be resumed. Plaintiff did resume operations but on August 24 the building inspector returned and again ordered it to cease. Work stopped and was never resumed. Shortly thereafter plaintiff vacated the premises.

*314 The damage issue focused on four purchase orders, evidence of which was presented as follows:

(1) The Magnificiant Two Boutique, Inc., of Newark: This order was dated August 1, 1977 with a specified delivery date of August 25, 1977. The order was for suits, 24 small, 24 medium and 24 large at $60 each; for coats, 36 small, 36 medium and 48 large at $75 each; a total of $13,320.
(2) Fashion Express, Newark: This order was dated August 1, 1977 and the specified delivery date is August 20, 1977. The order was for suits, 24 small, 24 medium, and 24 large, at $60 each; for coats, 48 small, 48 medium and 48 large, at $75 each; a total of $15,120.
(3) The Cockeyed Parrott, Roslindale, Massachusetts: The order was for 250 coats at $75 apiece with a delivery date of August 23; a total of $18,750.
(4) Kairallo Trousseau Shop, Magnolia, Massachusetts: The order was for 150 coats at $75 apiece to be delivered by August 31; a total of $11,250.

These deadlines keyed into the Fall line which opens right after Labor Day. Neither Rubin, nor any other representative of the Hajjar Agency, were at any time told of the size of these purchase orders or of the delivery deadlines.

Plaintiff presented evidence that about $8,300 was spent on materials (wool, cashmere, thread, buttons, etc.) to fill these orders. Another $4,000 was spent on machinery, furniture and travel and miscellaneous expenses.

At the time plaintiff was forced to cease operations, all of the material had been cut and the garments were partially sewn, but none had been completed for shipment. Plaintiff's principals allegedly still retain the garments. Karrell testified that when operations ceased on August 24 it was impossible to find other jobbers to complete the garments; he testified that the material is now worthless since the garments were out of style.

At trial plaintiff contended that all of the orders would have been filled if the manufacturing operation had not been halted because of the zoning violation. The delivery dates on the four orders were August 23, 25, 30 and 31. Karrell testified that it was the custom in the trade that a manufacturer was permitted to deliver garments up until 12 working days after the deadline specified in the purchase order. Defendants strenuously opposed this alleged trade custom of an automatic extension of delivery dates with evidence that delivery dates in the trade were firm. The trial judge made no specific finding on this *315 point. From the conclusions he reached, as expressed in his oral opinion, we of necessity infer that he believed plaintiff's contention of an automatic 12-day extension of delivery.

The trial judge found that defendants, as professionals, "had a duty to provide premises in which [the] industry was permitted" and that "they were negligent in not checking the local ordinances before providing these premises to the plaintiffs." The judge found that "unquestionably, it was within the contemplation of the parties that manufacturing would ensue and that the plaintiff would suffer if such manufacturing was interrupted."

The trial judge refused to limit plaintiff's damages to the differences between the rental value of the premises and the rent reserved under the lease, as urged by defendants. The trial judge considered plaintiff's cost of materials and capital equipment as irrelevant on the damage issue. The judge looked exclusively to the four purchase orders "to determine what is the nature of the damage." He made the following specific factual findings relevant to the damage issue:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

DiMisa v. Acquaviva
947 A.2d 168 (New Jersey Superior Court App Division, 2008)
Fireman's Fund Insurance v. Lopez
776 A.2d 765 (Supreme Court of New Jersey, 2001)
In Re Estate of Lash
776 A.2d 765 (Supreme Court of New Jersey, 2001)
Lithuanian Commerce Corp. v. Sara Lee Hosiery
23 F. Supp. 2d 509 (D. New Jersey, 1998)
Borough of Fort Lee v. BANQUE NAT. DE PARIS
710 A.2d 1 (New Jersey Superior Court App Division, 1998)
FG v. MacDonell
677 A.2d 258 (New Jersey Superior Court App Division, 1996)
New Jersey Housing & Mortgage Finance Agency v. Bedminster Hills Housing Corp.
666 A.2d 1018 (New Jersey Superior Court App Division, 1995)
Perini Corp. v. Greate Bay Hotel & Casino, Inc.
610 A.2d 364 (Supreme Court of New Jersey, 1992)
Tylle v. Zoucha
412 N.W.2d 438 (Nebraska Supreme Court, 1987)
Rodriguez v. CARDONA TRAV. BUR.
523 A.2d 281 (New Jersey Superior Court App Division, 1986)
Coyle v. Englander's
488 A.2d 1083 (New Jersey Superior Court App Division, 1985)
Donovan v. Bachstadt
437 A.2d 728 (New Jersey Superior Court App Division, 1981)
Paris of Wayne, Inc. v. Richard A. Hajjar Agency
427 A.2d 555 (Supreme Court of New Jersey, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
416 A.2d 436, 174 N.J. Super. 310, Counsel Stack Legal Research, https://law.counselstack.com/opinion/paris-of-wayne-inc-v-richard-a-hajjar-agency-njsuperctappdiv-1980.