Beaver Valley Painting, Inc. v. Terminal Construction Corp.

211 F. Supp. 946, 1962 U.S. Dist. LEXIS 4548
CourtDistrict Court, D. New Jersey
DecidedDecember 27, 1962
DocketCiv. A. No. 292-60
StatusPublished

This text of 211 F. Supp. 946 (Beaver Valley Painting, Inc. v. Terminal Construction Corp.) is published on Counsel Stack Legal Research, covering District Court, D. New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Beaver Valley Painting, Inc. v. Terminal Construction Corp., 211 F. Supp. 946, 1962 U.S. Dist. LEXIS 4548 (D.N.J. 1962).

Opinion

WORTENDYKE, District Judge.

The Court’s jurisdiction in this action is appropriately predicated upon diversity of citizenship with the requisite jurisdictional minimum involved. 28 U. S.C. § 1332(a). Plaintiff, Beaver Valley Painting, Inc. (hereinafter Beaver Valley), a painting subcontractor with Terminal Construction Corp. (Terminal), sued Terminal for damages for breach of the subcontract. Terminal counterclaimed against Beaver Valley, joining Beaver Valley’s bond surety as a co-plaintiff to respond, with Beaver Valley, to the counterclaim. Terminal was the general contractor with the designee of the Secretary of Defense of the United States for the construction of a housing project for the accommodation of members of the armed services at Fort Dix, New Jersey.

The case was tried to a jury, which returned a verdict for Beaver Valley against Terminal in the sum of §29,-394.76, a verdict in favor of Terminal against Beaver Valley upon one of the counts of Terminal’s counterclaim, in the amount of $1,324.94, and a verdict of no cause for action against Terminal on the remaining counts of its counterclaim.

At the close of the evidence for Beaver Valley and again at the close of all of the evidence, Terminal moved for dismissal and for a directed verdict of and upon the complaint. Both motions were denied by the Court, and the case was submitted to the jury. The verdicts were returned on October 11, 1962 and judgment thereon was entered on October 25, 1962.

Terminal now moves for judgment notwithstanding the verdict and, in the alternative, for a new trial, F.R.C.P. 41(b) and 50; Montgomery Ward & Company v. Duncan, 1940, 311 U.S. 243, 61 S.Ct. 189, 85 L.Ed. 147.

Terminal contends (1) that the evidence was insufficient to support the verdict in favor of Beaver Valley upon the issue of damages and (2) that Beaver Valley was not entitled to recover from Terminal because Terminal had been released from all claims which accrued prior to April 30, 1959, the date of a release in writing which, by the terms of the contract between the parties, the subcontractor was required to give to the general contractor in exchange for payment of each installment of the contract price.

Terminal contends that the sole measure of damages applicable to that issue in this case is that enunciated in Kehoe v. Mayor, etc., of the Borough of Rutherford, N.J.Sup.1893, 56 N.J.L. 23, 27 A. 912, and that because of the lack of evidence supportive of one of the criteria for the determination of damages in Kehoe, there was a failure of proof of damages in the case at bar which disentitled Beaver Valley to an affirma[948]*948tive verdict against Terminal in more than a nominal amount.

In its main charge in this case, the Court included language from the opinion in Kehoe, as well as language from the opinion in United States v. Behan, 1884, 110 U.S. 338, 4 S.Ct. 81, 28 L.Ed. 168, and permitted the jury to apply the measure of damage enunciated in either of the cited cases, depending upon the jury’s findings respecting evidence or lack of evidence disclosing the elements of proof required by either of the two authorities.

Kehoe involved a written contract with the defendant municipality for the grading of a public street therein. The terms of that agreement provided that the contractor should receive 650 per lineal foot for grading a specified distance of street surface. During the course of the work and when it had only been partially completed, it was found that part of the lineal footage which the contract required the contractor to grade was not owned by or in the control of the municipality. The latter thereupon interrupted the performance of the work and the contractor abandoned its further prosecution. At that point the contractor had received from the municipality the sum of $1,850 on account. The total length of the grading called for by the contract was 4,220 feet. At 650 per foot, the contractor would have become entitled, had he completed the total lineal footage, to the sum of $2,743. The length of the work performed by the contractor was 3,500 feet, and the performance of this work involved the making of 8,000 cubic yards of excavation and the placing of 1,300 cubic yards of fill. In order to complete the total contract it would have been necessary to place 14,000 cubic yards of fill. The contractor sued the Borough for breach of contract and upon quantum meruit for the work done. The evidence disclosed that the fair cost of the work done was $3,153.00 and that the fair cost of the work remaining undone was $1,891.00. Thus, the fair cost of the performance of the whole contract was $5,044.00 (albeit the bid on which the contractor was awarded the work was $2,743.00). The New Jersey Supreme Court affirmed the non-suit of the plaintiff in the trial court, and in its opinion stated that the plaintiff could recover for the work done only such a proportion of the contract price as the fair cost of that work ($3,153.00) bore to the fair cost of the whole work required $5,-044.00), and, in respect of the work not done, only such profit, if any, as the contractor might have made by completing the work for the unpaid balance of the contract price. An equation reflective of the foregoing rule would be X over 2,743 equals 3,153 over 5,044, equals $1,715. (for the work done). Because the evidence disclosed that it would have cost $1,891.00 to perform the work remaining undone, and the unpaid balance of the contract price was only $893.00 ($2,743 minus $1,850), the contractor could earn no profit by completing the contract. Therefore, said the Court, he was overpaid $1,850.00 minus $1,715. equalling $135.00. The Court’s opinion continues in the following language: “[w]hen it can be determined what, according to the contract, the plaintiff would receive for that which he has done, and what profit he would have realized by doing that which, without fault, he has been prevented from doing, then these sums become the legal, as they are the just, measure of his damages.” Plaintiff must show himself to have sustained damage, i. e. (1) that actual compensation will only be given for actual loss; and (2) that the contract itself furnishes the measure of damages. It is the rule in New Jersey that the contractor shall recover the cash value of what he was to receive (Hinchman v. Rutan, 31 N.J.L. 496) thus maintaining the standard fixed by the contract.

In the present case, if Beaver Valley had completed the work called for by the subcontract with Terminal, it would have been entitled to no more than $217,500, the price for which it contracted to perform the work. According to Beaver Valley’s claims, the cost of the work which it had performed was $169,363.12. [949]*949Terminal’s evidence tended to show that as of May 8, 1959, when Beaver Valley concedely left the job, it had performed 33% of the work called for by the subcontract (exclusive of corrective work), and that the reasonable value of the work so performed was $71,775.00. A written stipulation, dated April 5, 1962, signed by counsel, is on file, paragraph 12 of which reveals that certain payments on the contract were made by Terminal to Beaver Valley.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Behan
110 U.S. 338 (Supreme Court, 1884)
Montgomery Ward & Co. v. Duncan
311 U.S. 243 (Supreme Court, 1940)
De Ponte v. Mutual Contracting Co.
86 A.2d 785 (New Jersey Superior Court App Division, 1952)
Goldman v. Shapiro
84 A.2d 628 (New Jersey Superior Court App Division, 1951)
Wilkins v. Bailey Engineering Co., Inc.
91 A.2d 98 (New Jersey Superior Court App Division, 1952)
Wilkinson v. Orange Mountain Land Co.
137 A. 591 (Supreme Court of New Jersey, 1927)
Apex Metal Stamping Co. v. Alexander & Sawyer, Inc.
138 A.2d 568 (New Jersey Superior Court App Division, 1958)
Hinchman v. Rutan
31 N.J.L. 496 (Supreme Court of New Jersey, 1864)
Kehoe v. Mayor of Rutherford
27 A. 912 (Supreme Court of New Jersey, 1893)
Wolcott v. Skahill
27 A. 912 (Supreme Court of New Jersey, 1893)
Ryan v. Remmey
31 A. 766 (Supreme Court of New Jersey, 1895)
Cavanagh v. Borough of Ridgefield
109 A. 515 (Supreme Court of New Jersey, 1920)
Wilson v. Borden
54 A. 815 (Supreme Court of New Jersey, 1903)

Cite This Page — Counsel Stack

Bluebook (online)
211 F. Supp. 946, 1962 U.S. Dist. LEXIS 4548, Counsel Stack Legal Research, https://law.counselstack.com/opinion/beaver-valley-painting-inc-v-terminal-construction-corp-njd-1962.